Boston Edison Co. v. Boston Redevelopment Authority

371 N.E.2d 728, 374 Mass. 37, 1977 Mass. LEXIS 1222
CourtMassachusetts Supreme Judicial Court
DecidedDecember 21, 1977
StatusPublished
Cited by153 cases

This text of 371 N.E.2d 728 (Boston Edison Co. v. Boston Redevelopment Authority) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Edison Co. v. Boston Redevelopment Authority, 371 N.E.2d 728, 374 Mass. 37, 1977 Mass. LEXIS 1222 (Mass. 1977).

Opinions

Abrams, J.

Pursuant to St. 1960, c. 652, § 13, the plaintiff Boston Edison Company (Edison) instituted a proceeding in the nature of certiorari in the Superior Court to review action taken by the defendant Boston Redevopment Authority (BRA) under its statutory powers as set out at St. 1960, c. 652, and G. L. c. 121A. The specific action which Edison attacks is the BRA’s approval of a plan proposed by the remaining defendants — (1) Citicorp Trans-lease, Inc.; (2) L. Edward Lashman, Jr.; (3) the Medical Area Service Corporation (MASCO); and (4) the President and Fellows of Harvard College (Harvard) (collectively the Applicants) — for the construction of an electric generating and steam power plant, an office building, and related facilities as an urban renewal project. A Superior Court judge heard arguments on two motions to dismiss, one filed by the BRA and the other by the Applicants. Each of the motions to dismiss alleged that Edison lacked standing to maintain its cause of action. Both motions also alleged in substance that the complaint failed to state a claim on which relief could be granted. The judge denied the motions challenging Edison’s standing. Thereafter, after a full hearing, the judge rendered a thorough and well-reasoned opinion which at its conclusion ordered that a judgment dismissing Edison’s complaint (and thereby affirming the BRA’s action) should be entered. Edison duly filed its claim of appeal. We allowed Edison’s application for direct appellate review. The defendants did not take a cross appeal from the [40]*40judge’s adverse ruling on the standing issue. We affirm the decision of the Superior Court judge.

The facts are as follows. MASCO is a charitable corporation established by twelve institutions engaged in medical, educational, and charitable functions.1 MASCO’s purpose is to assist its members in performing these functions more efficiently.

The project contemplates the operation and maintenance by MASCO, through a corporation formed pursuant to c. 652 and G. L. c. 121 A, of a total energy plant which would provide electricity, steam, chilled water, and solid waste incineration for the MASCO member institutions.2 The total energy plant would replace the existing Harvard steam plant on Blackfan Street, which presently supplies some of the steam requirements of some of the MASCO institutions but which is or will be increasingly inadequate to meet these requirements. In addition, the project would provide some nonelectrical services, free of charge, to the Mission Park Housing Project, a publicly assisted housing project previously approved by the BRA.3

The power plant is to be located on 1.4 acres in the city of Boston in a block bounded by Brookline Avenue, Francis Street, Binney Street, and Peabody Street. This area is located within the Fenway Urban Renewal Area and is sub[41]*41ject to the Fenway Urban Renewal Plan (Fenway Plan); approval of the Fenway Plan required a finding that the Fen-way Urban Renewal Area was a decadent area. The area surrounding the site of the proposed power plant is characterized by institutional and commercial uses on three sides and by some residential use on the fourth side.

Edison sells electricity in the city of Boston, and among its customers are the twelve MASCO member institutions whose annual consumption yields to Edison approximately $3,000,000 in gross revenues. Construction of the total energy plant will result in Edison’s loss of this business for a period of at least thirty-five years.

After informal contact between the Applicants and the BRA regarding the likelihood of the plan’s qualifying as a project under St. 1960, c. 652, and G. L. c. 121A, the BRA on April 30, 1975, submitted a draft environmental impact report (EIR) on the project. The Applicants submitted to the BRA a formal application for approval of the project on July 1,1975. On July 7,1975, the Secretary of Environmental Affairs issued a statement finding the draft EIR inadequate.

On August 26, 1975, the BRA conducted a public hearing on the project, as required by c. 121A. Edison participated fully in this hearing and filed with the BRA extensive materials setting forth its views on the proposed project.

On September 29, 1975, the BRA submitted its final EIR. On October 2, 1975, a motion to adopt a draft Report and Decision approving the project was tabled, but on October 9, 1975, by a four to one vote, the BRA adopted a Report and Decision approving the project. Included in the report were the findings required for approval of a project under St. 1960, c. 652, and G. L. c. 121A. The BRA’s vote was approved by the mayor of the city of Boston on December 8, 1975, and on December 17, 1975, copies of the BRA’s vote and the mayor’s approval were filed with the city clerk.

On November 5, 1975, the Secretary of Environmental Affairs found the final EIR inadequate. After the submis[42]*42sion of supplementary information, the EIR was found acceptable by the Secretary on January 23, 1976.4

Edison challenges the BRA’s approval of the project on the grounds (1) that the total energy plant does not constitute a “project” as defined in G. L. c. 121A, § 1; (2) that, contrary to the BRA’s findings, the site for the plant was not a “decadent and/or substandard area,” and the project does not constitute a “public use and benefit” as required by c. 652, § 13, and c. 121A, §§ 1 and 2; (3) that deviations from the Boston zoning code granted by the BRA substantially derogate from the intent and purposes of the zoning code; (4) that the plan conflicts with the Master Plan for Boston and with the Fenway Plan; (5) that the vote of the BRA is invalid because the failure to disclose the amount of the additional tax payment on the project is a violation of G. L. c. 121 A, § 6A; and (6) that the terms of four of the five BRA members who voted on the application had expired prior to the vote, thus rendering that action invalid.

Prior to examining the merits of these allegations, we confront the defendants’ threshold claim that Edison is without standing to maintain the present suit. That argument was advanced in the Superior Court as a basis for the defendants’ motions to dismiss. The motions were denied. Al[43]*43though the defendants did not take a cross appeal from that ruling, they are not precluded from raising it here. A party who prevails in the Superior Court may present on appeal any ground which was previously asserted below in support of the judgment.5 Boston Police Patrolmen’s Ass’n v. Boston, 367 Mass. 368, 373-374 (1975). We therefore address this matter at the outset.

1. Standing.

Statute 1960, c. 652, § 13, provides that “any person . . . who is aggrieved” by a vote of the BRA may file a petition for a writ of certiorari against the authority to correct errors of law. Edison contends that its projected loss of approximately $3,000,000 a year over the next thirty-five years is an injury of sufficient magnitude to confer standing on it. The defendants argue, on the other hand, that business competition as the result of governmental action is not the type of injury which satisfies the standing requirement of the statute.

As the defendants maintain, the threat of competition is generally not a sufficient injury to confer standing. SDK Medical Computer Servs. Corp. v. Professional Operating Management Group, Inc., 371 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller Fence Co. v. Gordon Davis.
Massachusetts Appeals Court, 2025
JEFFREY GODERE v. CITY OF CHICOPEE & Another.
Massachusetts Appeals Court, 2023
Reagan v. Commissioner of Revenue
Massachusetts Supreme Judicial Court, 2023
Caplan v. Town of Acton
92 N.E.3d 691 (Massachusetts Supreme Judicial Court, 2018)
Massachusetts State Automobile Dealers Association, Inc. v. Tesla Motors MA, Inc.
15 N.E.3d 1152 (Massachusetts Supreme Judicial Court, 2014)
Figgs v. Boston Housing Authority
14 N.E.3d 229 (Massachusetts Supreme Judicial Court, 2014)
Bevilacqua v. Rodriguez
955 N.E.2d 884 (Massachusetts Supreme Judicial Court, 2011)
Adoption of Mariano
933 N.E.2d 677 (Massachusetts Appeals Court, 2010)
Pollard v. Conservation Commission
897 N.E.2d 1242 (Massachusetts Appeals Court, 2008)
Black Rose, Inc. v. City of Boston
744 N.E.2d 640 (Massachusetts Supreme Judicial Court, 2001)
Boston Herald, Inc. v. Sharpe
737 N.E.2d 859 (Massachusetts Supreme Judicial Court, 2000)
Perseus of N.E., MA, Inc. v. Commonwealth
706 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1999)
St. Botolph Citizens Committee, Inc. v. Boston Redevelopment Authority
429 Mass. 1 (Massachusetts Supreme Judicial Court, 1999)
Ginther v. Commissioner of Insurance
427 Mass. 319 (Massachusetts Supreme Judicial Court, 1998)
Raso v. Lago
958 F. Supp. 686 (D. Massachusetts, 1997)
Marashlian v. Zoning Board of Appeals
421 Mass. 719 (Massachusetts Supreme Judicial Court, 1996)
Fay v. Federal National Mortgage Ass'n
647 N.E.2d 422 (Massachusetts Supreme Judicial Court, 1995)
Robinson's Case
623 N.E.2d 478 (Massachusetts Supreme Judicial Court, 1993)
Vining Disposal Service, Inc. v. Board of Selectmen
616 N.E.2d 1065 (Massachusetts Supreme Judicial Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
371 N.E.2d 728, 374 Mass. 37, 1977 Mass. LEXIS 1222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-edison-co-v-boston-redevelopment-authority-mass-1977.