Wertheimer Construction Corp. v. United States

406 F.2d 1071, 186 Ct. Cl. 836
CourtUnited States Court of Claims
DecidedFebruary 14, 1969
DocketNo. 380-62
StatusPublished

This text of 406 F.2d 1071 (Wertheimer Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wertheimer Construction Corp. v. United States, 406 F.2d 1071, 186 Ct. Cl. 836 (cc 1969).

Opinion

Per Curiam :

This case was referred to Trial Commissioner Bichard Arens with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Buie 57 (a). The commissioner has done so in an opinion and report filed on August 12, 1968. Plaintiff filed a notice of intention to except to the commissioner’s report on September 10,1968. However, on December 13,1968, plaintiff filed a motion for permission to withdraw its notice of intention to except and further moved that the court adopt the commissioner’s report as its findings of fact and opinion. On December 17,1968, defendant filed a motion agreeing and concurring in plaintiff’s request that the commissioner’s report be adopted by the court.

Since the court agrees with the commissioner’s opinion, findings and recommended conclusion of law, as hereinafter set forth, it hereby grants the aforementioned motions of the parties, and adopts the said opinion, findings and recommended conclusion of law as the basis for its judgment in this case without oral argument. Therefore, plaintiff is entitled to recover and judgment is entered for plaintiff in the sum of $4,540.

OPINION OP COMMISSIONER

Arens, Oommissioner:

Plaintiff, a general construction contractor, seeks remission of liquidated damages assessed [839]*839against it and costs which it incurred after substantial completion of a 183 dwelling unit project which it constructed in Washington, D.C., under a contract entered into in April 1958, with the National Capital Housing Authority (sometimes hereinafter referred to as the Authority).

No administrative appeal from any decision of the contracting officer was provided for in the contract. The parties accordingly proceeded in this court by trial de novo. Under the circumstances of this case, the decision of the contracting officer is not entitled to Wunderlich Act finality and the resolution of the factual issues is to be made on the basis of a preponderance of the evidence before the court. L. Rosenman Corp. v. United States, 182 Ct. Cl. 586, 390 F. 2d 711 (1968); Earl N. Davis, Trustee of Astrotherm Corp. v. United States, 180 Ct. Cl. 20 (1967). The factual issues, which constitute the bulk of the controversy, are set forth in detail and resolved by ultimate findings in the accompanying findings of fact, and are, therefore, only outlined in this opinion.

The work to be performed under the contract was divided into two groups which were to be “progressively completed, suitable and ready for occupancy” within the prescribed number of consecutive calendar days, and plaintiff was liable for liquidated damages for each calendar day of delay until the work was completed or accepted. Plaintiff was not to be charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond its control and without its fault or negligence, including “unusually severe weather.” The contract contained a disputes clause and other provisions, hereinafter alluded to in connection with relevant subject matter.

Liquidated Damages

Paving of Sayles Place (finding 5). The contracting officer granted plaintiff 130 days’ extension of contract time for completion of group 1 buildings due to delay caused by a paving contractor, but granted no extension of contract time for completion of group 2 buildings. The testimony of both plaintiff’s and defendant’s witnesses establishes, however, that [840]*840tbe delay of tbe work on group 1 buildings interfered witb tbe planned sequence of tbe operations witb a resultant delaying effect on the work on group 2 buildings. Plaintiff claims that it should have been granted 70 days’ extension of contract time for completion of group 2 buildings, but, as set forth in finding 5(f), 15 days’ extension is found to be warranted. Adams v. United States, 175 Ct. Cl. 288, 358 F. 2d 986 (1966); Blount Bros. Constr. Co. v. United States, 180 Ct. Cl. 35 (1967).

Weather delays (finding 6). Plaintiff requested tbe contracting officer for an extension of contract time of 128 days because of “extreme weather conditions,” but tbe contracting officer, after comparing the weather conditions during tbe months of the contract work with the weather conditions during similar months of a preceding eight-year period, granted 22 days’ extension for each group of buildings. Plaintiff contends that “from the testimony and exhibits, particularly the Government’s daily records, the project was delayed by adverse weather conditions for a substantially longer period than granted by the contracting officer”; but, as stated in finding 6(b), the evidence adduced by plaintiff regarding weather delays was vague and fragmentary, and does not establish that it was entitled to an extension of the contract time for a period longer than that allowed by the contracting officer. Banks Constr. Co. v. United States, 176 Ct. Cl. 1302, 364 F. 2d 357 (1966).

Vandalism (finding 7). Section 26 of the General Conditions provided in part:

26. CARE OE WORK
a. The Contractor shall be responsible for all damages to persons or property that occur as a result of his fault or negligence in connection with the prosecution of the work and shall be responsible for the proper care and protection of all materials delivered and woi*k performed until completion and final acceptance, whether or not the same has been covered by partial payments made by the Authority, and whether or not the damage to his work was caused by the Contractor or by other contractors or by others than the employees of the Authority in the course of their employment.
[841]*841b. In the event of delay in completion of the contract work due to loss or damage caused by failure of the contractor to adopt reasonable and continuous protective methods, the contractor shall not be relieved from payment of liquidated damages because of such delay.

In denying plaintiff’s request for an extension of contract time because of delay due to vandalism, the contracting officer emphasized that it was not defendant’s responsibility under the contract to protect the project from theft or damage while it was in the hands of the contractor, and that there was no requirement in the contract for an extension because of delay due to vandalism. In reaching this conclusion, it is clear that the contracting officer was in error because the contract provisions which exonerated plaintiff from liquidated damages because of any delays in the completion of the work “due to unforeseeable causes beyond its control and without its fault or negligence,” do not depend upon fault or responsibility of defendant. Moreover, when one couples this language with the contract language which provided that the contractor should not be relieved from payment of liquidated damages because of delay caused by failure of the contractor to adopt reasonable and continuous protective methods, the conclusion is inescapable that if the delay was because of the above-described unforeseeable causes and was not caused by failure of the contractor to adopt the protective methods, then the contractor was entitled to be relieved from payment of liquidated damages. The contract is, of course, to be interpreted so as to harmonize all provisions wherever it is reasonable to do so. Hol-Gar Mfg. Corp. v. United States, 169 Ct. Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Banks Construction Company, Inc. v. The United States
364 F.2d 357 (Court of Claims, 1966)
L. Rosenman Corporation v. The United States
390 F.2d 711 (Court of Claims, 1968)
Fox Valley Engineering Inc. v. United States
151 Ct. Cl. 228 (Court of Claims, 1960)
Commerce International Co. v. United States
167 Ct. Cl. 529 (Court of Claims, 1964)
Connolly-Pacific Co. v. United States
358 F.2d 995 (Court of Claims, 1966)
Davis v. United States
180 Ct. Cl. 20 (Court of Claims, 1967)
Blount Bros. Construction Co. v. United States
180 Ct. Cl. 35 (Court of Claims, 1967)
Bishop Engineering Co. v. United States
180 Ct. Cl. 411 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
406 F.2d 1071, 186 Ct. Cl. 836, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wertheimer-construction-corp-v-united-states-cc-1969.