Blount Bros. Construction Co. v. United States

180 Ct. Cl. 35, 1967 U.S. Ct. Cl. LEXIS 74, 1967 WL 8928
CourtUnited States Court of Claims
DecidedMay 12, 1967
DocketNo. 249-61
StatusPublished
Cited by4 cases

This text of 180 Ct. Cl. 35 (Blount Bros. Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blount Bros. Construction Co. v. United States, 180 Ct. Cl. 35, 1967 U.S. Ct. Cl. LEXIS 74, 1967 WL 8928 (cc 1967).

Opinion

Collins, Judge,

delivered the opinion of the court:

By opinion of this court, entered on July 16, 1965,1 count two of the above-titled case was dismissed pursuant to the Government’s motion for summary judgment. A like motion was denied as to count one; this phase of the case was returned to Trial Commissioner Bernhardt, pursuant to Buie 47, for a determination of the amount of plaintiff’s recovery.2 Blount Bros. Constr. Co. v. United States, 172 Ct. Cl. 1, 348 F. 2d 471 (1965). Plaintiff’s disagreement with the commissioner’s findings and recommendations brings the case to our attention once again.

The point of disagreement is a narrow one. It concerns a dispute as to the amount of undischarged or lost overhead due plaintiff’s second-tier subcontractor, General Metals Company (hereinafter referred to as General Metals), as a result of a Government-issued hold order suspending plaintiff’s work on its “wavemaker” contract during the period March 1, 1957, to February 28, 1958. Although we reach a different figure from that recommended by the commissioner, we accept, in large measure, his approach to the problem.

Performance of the contract in issue commenced in January 1957 with completion anticipated by February 1958. On February 19, 1957, a hold order was issued by the Department of the Navy, Bureau of Yards and Docks — the contracting agency — which remained in effect until February 7, 1958, at which time work was ordered resumed. [38]*38Thereafter, General Metals completed the balance of the contract. Entitlement to recover the additional delay costs resulting from the stated suspension was resolved in our earlier decision in this case. As stated, the problem now is to find a means of allocating General Metals’ “hold-order-period” overhead between the work then in progress and its suspended wavemaker contract.3

In its initial approach to the problem, plaintiff had taken the position that an appropriate allocation could be made simply by apportioning the total hold-order-period overhead {i.e., $284,823.28 4) between the amount of lost sales {i.e., $313,723, the balance remaining on the suspended wavemaker contract) and the total of all other sales for this same period {i.e., $831,829.51). This suggested allocation formula proceeds on the premise that had the Government not suspended the wavemaker contract, General Metals would have been able to enlarge its sales by the corresponding amount, and this $313,723 worth’ of additional performed work would, in turn, have absorbed its proportionate share of the established overhead (i.e., $284,823.28).

In rejecting this approach, the commissioner correctly pointed out that had General Metals not experienced its “lost” sale, that is, had it been permitted to work on the wavemaker contract without interruption and thereby increase its sales for the period by the stated amount {i.e., $313,723), then, in such event, its actual overhead costs would likewise have increased. Thus, the flaw in plaintiff’s reasoning was the assumption that recorded sales (here meaning performed work) could be increased without any change in operating costs. Further, and as our commissioner also noted, this method of allocation was defective in another sense — namely, it excluded from the list of contracts, to [39]*39wbicb overhead was chargeable, the so-called “tunnel” contract.

This latter contract, which General Metals entered into at the same time that it undertook performance upon the wavemaker, involved the construction of a steel tunnel (a project related to the wavemaker). But, unlike the wave-maker, actual construction of the tunnel was a matter which General Metals contemplated achieving through subcontractors (although in this it was never successful). The record shows that, unlike the usual subcontract, General Metals expended considerable administrative effort in attempting to secure the satisfactory fulfillment of the tunnel project. Its activities, which ran the gamut from the purchasing of supplies to the participation in numerous negotiations designed to secure a relaxation of the contract’s specifications, were of a magnitude sufficient to have contributed significantly to the total overhead incurred during the hold order period. In seeking to exclude the tunnel contract from the list of overhead chargeable contracts, plaintiff was clearly wrong.

As an alternative to plaintiff’s unacceptable approach, the commissioner decided upon an historical one, i.e., to compare General Metals’ normal or average operating costs with those obtaining during the hold-order period and treating the percentage difference between the two as the measure of its unabsorbed overhead during the base period.

This established, as the ratio of overhead to sales, an average operating cost of 29.24 percent for a given 5-year period,5 compared with a 34.24 percent operating cost during the hold-order period. The resulting difference of 5 percent, computed against total hold-order-period overhead, yields a sum of $41,591.48. This, then, represents the total amount of excess or unabsorbed overhead which General Metals sustained during the time that performance on its wavemaker contract had been suspended. And while this figure is different from that which either party had initially put forth, [40]*40both have since agreed to accept it as the total amount available for allocation. Thus, there remains, at this point, the question as to what percentage of the $41,591.48 should be allotted to each of General Metals’ two contracts. On this issue, the parties differ drastically.

The commissioner’s solution, which defendant would now have us accept, divides the $41,591.48 in amounts proportionately equal to the respective dollar values of the two contracts. The idled portion of the wavemaker contract ($313,723) was allocated 57.33 percent of the $41,591.48 (i.e., $23,844.40), while the undelivered tunnel contract (representing a $233,500 sale) was allocated 42.67 percent of the total (i.e., $17,747.08) 6 This allocation we cannot accept because it treats, as equal, two contracts which, from the standpoint of overhead allocation, must receive differentiation.

Broadly speaking, the concept of overhead comprises two categories of expenses. The first, which we shall term “home office” overhead includes, inter alia, secretarial and administrative expenses, and the second category, which we refer to as “factory burden” or “factory overhead,” includes, inter alia, depreciation on manufacturing equipment, rent, fuel, maintenance, and power. By their nature, these expenses are continuous in the sense that they are incurred and must be paid even, in circumstances like the present, where actual performance of work has been temporarily halted. To be sure, these expense items are not fixed, for as work increases so also does overhead, but it is their existence, even in the absence of actual contract performance, which makes them a factor properly cognizable as an element of delay damages. Insofar as the plaintiff’s wavemaker contract is concerned, overhead allocation should be directed towards satisfying both categories. However, the same does not obtain with respect to the tunnel contract.

[41]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town Center Management Corp. v. United States
39 Cont. Cas. Fed. 76,691 (Federal Claims, 1994)
Wertheimer Construction Corp. v. United States
406 F.2d 1071 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
180 Ct. Cl. 35, 1967 U.S. Ct. Cl. LEXIS 74, 1967 WL 8928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blount-bros-construction-co-v-united-states-cc-1967.