Trade West Construction, Inc.

CourtArmed Services Board of Contract Appeals
DecidedOctober 8, 2020
DocketASBCA No. 61068
StatusPublished

This text of Trade West Construction, Inc. (Trade West Construction, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trade West Construction, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Trade West Construction, Inc. ) ASBCA No. 61068 ) Under Contract No. W912PM-15-C-0024 )

APPEARANCES FOR THE APPELLANT: Karl Dix, Jr., Esq. Lochlin B. Samples, Esq. Smith, Currie & Hancock LLP Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney David C. Brasfield, Jr., Esq. Carl E. Pruitt, Jr., Esq. Engineer Trial Attorneys U.S. Army Engineer District, Mobile

OPINION BY ADMINISTRATIVE JUDGE STINSON

Appellant Trade West Construction, Inc., (Trade West), appeals a contracting officer’s denial of its October 21, 2016, claim, in the amount of $304,062, for shaping armor stone prior to placing it on top of an existing jetty. Trade West argues that the government wrongfully rejected the armor stone it wished to use, thereby forcing it to spend time and money shaping the armor stone to make it acceptable to the government. (R4, tab 3) We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. The parties submitted cross-motions for summary judgment, reply briefs, and exhibits to be considered in deciding this appeal. 1 Appellant also submitted two affidavits. For the reasons stated below, the parties’ cross-motions for summary judgment are denied.

1 The government’s motion for summary judgment and appellant’s cross-motion for summary judgment/response to the government’s motion are referred to herein as “gov’t mot.” and “app. mot.” The government’s response to appellant’s cross-motion/reply in support of its own motion is referred to as “gov’t resp.” Appellant’s reply in support of its motion for summary judgment is referred to as “app. reply.” STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

1. On September 25, 2015, the United States Army Corp of Engineers (USACE), Wilmington District, awarded Trade West Contract No. W912PM-15-C-0024 (the Contract), in the amount of $3,294,362.00, for South Jetty repairs to the Masonboro, Inlet located in New Hanover County, North Carolina (R4, tab 4.1 at 126, 132-33). The Contract required placement of armor stone weighing of 14 to 22 tons on an existing jetty, insuring that the armor stone “form a compact mass and interlock with each other and the existing stones” (R4, tab 4.1 at 134, 298).

2. The Contract included specifications for “Exterior Improvements,” Section 32 05 00.38, entitled “Stone.” Contained within that section was Part 1, “General,” Part 2, “Products,” and Part 3, “Execution.” (R4, tab 4.1 at 293)

3. Part 1.1, entitled “Scope,” provided, “[t]he work under this section shall include all plant, labor, materials, work surface, and equipment required for the furnishing, transportation, storage, and placing of stone as shown on the drawings” (R4, tab 4.1 at 294).

4. Part 2.1, entitled “Materials,” provided, in part:

2.1.2 Armor Stone

Stone shall consist of fresh, sound, hard, dense, durable, crystalline igneous or metamorphic rock which shall be separated from bedrock by quarrying. The stone shall be of such quality that the individual stone integrity and permanence within the jetty is assured under all conditions to which it is subjected.

....

The stone shall be free from open or incipient cracks, joints, seams, fissures and structural planes of weakness which might contribute to spalling or breakdown from; handling and placing, freeze-thaw cycles, wet-dry cycles, or from wave action. The stone shall be furnished in blocky and angular shapes. Flat stones, tabular stones, slabs, boulders and parts of boulders will be rejected. No

2 stone will be permitted which has a longest dimension that is three times (3X) or greater, than its least dimension.

(R4, tab 4.1 at 296)

5. Part 2.1.3, entitled “Stone Size and Gradations,” provided “[f]or the granite/granite gneiss armor stone, the specified weight range shall be 14.0 tons to 22.0 tons with 75% weighing more than 18.0 tons” (R4, tab 4.1 at 297).

6. Part 2.1.4, entitled “Stone Sources,” provided:

The source(s) from which the Contractor proposes to obtain stone materials as required for these specifications shall be selected and identified to the Contracting Officer or his/her designated representative within 15 days of receipt of Notice to Proceed. This source(s) shall be inspected by a Corps of Engineers Geologist. The stone source(s) shall provide test results of ASTM D5312/D5312M and ASTM D5313/D5313M and records of successful use on similar projects. The stone sampled by the Contractor shall be no less than 5 inches per side, excluding the thickness, and shall be tested by a Corps of Engineers validated commercial testing laboratory, or a Corps of Engineers laboratory. The tests shall include; bulk specific gravity, saturated surface dry (SSD) unit weight, absorption (all three tests as per ASTM C127), abrasion, wetting and drying (ASTM D5313/D5313M), and freeze-thaw (ASTM D5312/D5312M). The results of the testing shall be submitted to the Contracting Officer or his/her designated representative for review and approval at least 30 days prior to being shipped to the construction site.

(R4, tab 4.1 at 297)

7. Part 2.1.5, entitled “Stone Not Meeting The Specifications,” provided, in part:

If, during the progress of the work, it is found that the stone being furnished and/or placed by the Contractor does not meet all the requirements of the specifications, the Contractor shall furnish other stone of a quality acceptable to the Contracting Officer or his/her designated

3 representative. Any stone rejected at the site of work as not meeting the requirements of these specifications for quality, condition, size, or otherwise, shall be removed from the site by and at the expense of the Contractor. All stones which are broken during shipment to the work site or during placement shall be rejected. The Contractor shall dispose of all rejected stone in a manner that is approved by the Contracting Officer or his/her designated representative.

8. Part 3.2, entitled “Placement of Stone,” provided, in part:

3.2.1 General

Care shall be taken to place the stone so that they will form a compact mass, and form as nearly as practicable a cross- section of the height, width, and slopes as shown on the contract drawings. All stones shall be carefully placed so as to form a compact mass and to minimize the voids between them. Special care shall be taken during placement of stone to avoid damaging the existing sheetpile wall.

(R4, tab 4.1 at 298)

9. Part 3.2.4, entitled “Armor Stone Placement,” provided:

Armor stone shall be placed in a single layer to achieve the design cross sections and top elevation, as shown on the drawings. Begin placement of the stone at the toe of the placement limits and work upslope to reduce the risk of stone rolling and launching. Dropping of stones onto the structure is strictly prohibited. Each armor stone shall be lowered to rest before being released and shall be placed to the satisfaction of the Contracting Officer or his/her representative. All stones shall be carefully placed so as to minimize the size of voids between them. The armor stones of various sizes and shapes shall be distributed such

4 that they form a compact mass and interlock with each other and the existing stones.

10. Part 3.3, entitled “Quality Control,” provided, in part:

3.3.1 General

The Contractor shall establish and maintain quality control for the armor stone and all other operations in connection therewith to assure compliance with contract requirements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Bethlehem Steel Co.
205 U.S. 105 (Supreme Court, 1907)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
IMMUNOCEPT, LLC v. Fulbright & Jaworski, LLP
504 F.3d 1281 (Federal Circuit, 2007)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
Gulf & Western Industries, Inc. v. United States
32 Cont. Cas. Fed. 73,100 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Trade West Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/trade-west-construction-inc-asbca-2020.