Dairyland Power Cooperative v. United States

128 Fed. Cl. 499, 2016 U.S. Claims LEXIS 1417
CourtUnited States Court of Federal Claims
DecidedSeptember 28, 2016
Docket12-902C
StatusPublished
Cited by2 cases

This text of 128 Fed. Cl. 499 (Dairyland Power Cooperative v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dairyland Power Cooperative v. United States, 128 Fed. Cl. 499, 2016 U.S. Claims LEXIS 1417 (uscfc 2016).

Opinion

*500 Motion in Limine; Causation; System Fuels, Inc. v. United States, 120 Fed Cl. 685 (2015); System Fuels, Inc. v. United States, 120 Fed. Cl. 737 (2015)

OPINION AND ORDER

EDWARD J. DAMICH, Senior Judge

This order concerns two motions in li-mine: (1) Dairyland’s Motion To Implement System Fuels, filed on August 3, 2016, and (2) Dairyland’s Motion in Limine To Exclude Evidence and Argument Regarding Causation In Evaluating Reasonableness of Dairy-land’s Mitigation Efforts (“Dairyland’s Motion on Causation”), filed on July 20, 2016. Briefing was completed for both motions on September 1, 2016. As explained below, the Court does not accept Dairyland’s view of how System Fuels affects this case, and the Court denies Dairyland’s Motion on Causation.

I. System Fuels

System Fuels concerned damages for partial breach of the U.S. government’s contractual obligation .owed to utilities to pick up spent nuclear fuel (SNF) and store it. System Fuels, Inc. v. United States, 818 F.3d 1302, 1303 (Fed.Cir.2016). The appeal involved two Court of Federal Claims cases: System Fuels, Inc. v. United States, 120 Fed.Cl. 635 (2015) (“Grand Gulf’) and System Fuels, Inc. v. United States, 120 Fed.Cl. 737 (2015) (“Arkansas Nuclear One”). The issue in both cases was a reduction of damages due to the costs incurred by System Fuels in loading SNF into storage casks for dry storage in Independent Fuel Storage Installations (“ISFSIs”), the construction of which were the result of the government’s breach. See Sys. Fuels, 818 F.3d at 1304. The Federal Circuit noted that the loading process included the loading of the SNF into canisters before it was loaded into the dry storage casks. Id. at 1305-06.

In both cases, the trial courts reduced the damages to account for the fact that System Fuels would have had costs to load SNF into different Department of Energy (“DOE”) transportation casks had the government performed. Grand Gulf, 120 Fed.Cl. at 661-662; Arkansas Nuclear One, 120 Fed.Cl. at 750-52. The damages reductions in both cases were made despite the fact that the courts had found that neither the canisters nor the dry storage casks were acceptable for DOE transportation under the contract or current regulations; thus, the SNF would have to be reloaded for DOE pick-up. In *501 reversing the trial courts’ reductions in damages, the Federal Circuit stated:

[T]he costs of loading future transportation casks, or the difference between the costs of loading these storage casks' and loading transportation casks, are irrelevant to System Fuels’ entitlement to the expenses it incurred for loading these storage casks. These are expenses incurred entirely for storage due to the government’s breach. And because, as admitted by the government, these storage casks cannot be used for transportation under the Standard Contracts, System Fuels will be required, if and when the government begins to comply, as both Court of Federal Claims decisions acknowledge, to unload the spent nuclear fuel from these storage casks and reload it into suitable transportation casks provided by the government. As we have explained, “the government cannot prematurely claim a payment that has not become due.”

Sys. Fuels, 818 F.3d at 1307 (quoting Carolina Power & Light Co. v. United States, 573 F.3d 1271, 1277 (Fed.Cir.2009)).

II. The Impact of System Fuels: The Arguments of the Parties

For Dairyland, System Fuels stands for the proposition that “there may be no deduction in present cases for the nonbreach cost of fuel loading unless the very same (not similar) effort cost would have been undertaken in both worlds.” ECF No. 150 at 2. This interpretation is more modest than its position in its opening brief that “System Fuels provides that the government is not entitled to any deduction for the costs to load fuel in the nonbreach world.” ECF No. 129 at 2. From its opening brief, this Court had the impression that the expenses of the entire project of loading SNF into casks for storage in the ISFSI would be immune from challenge by the government. Now it seems that Dairyland is asking the Court first to look at the breakdown of tasks (or “efforts”) and the cost attached to each and determine which of these tasks would not be the same tasks in the nonbreach world. Then, the Court should grant full recovery for the amounts assigned to those tasks if the amounts were reasonably accurate.

The government, by contrast, argues that just the recovery for costs associated with actually loading the dry storage casks (called “labor costs” by the government) is immune from challenge, while the other costs (“nonla-bor costs”) of dry storage are not. 1 The government resists the approach of breaking down the costs of the dry storage project into tasks and comparing these tasks to the tasks to be performed in the nonbreach world. For the government, the Court is comparing costs—not tasks—-in the breach and non-breach worlds.

III. The Decisional Context of System Fuels

The parties agree that System Fuels must be interpreted to harmonize with certain significant prior Federal Circuit decisions, namely, Carolina Power & Light Co. v. United States, 573 F.3d 1271 (Fed.Cir.2009), Energy Northwest v. United States, 641 F.3d 1300 (Fed.Cir.2011), and Vermont Yankee Nuclear Power Corp. v. United States, 683 F.3d 1330 (Fed.Cir.2012). In Carolina Power, most relevant is the court’s discussion of loading costs; in Energy Northwest, most relevant is the court’s discussion of plant modification costs; and in Vermont Yankee, most relevant is the court’s discussion of fuel characterization 2 costs.

In Carolina Power, the trial court declined to deduct from the plaintiffs damages the cost of loading DOE transportation casks. The government argued that this was an avoided cost, but the Federal Circuit disagreed: “Plaintiffs have not avoided the costs of loading. Rather, they have merely de *502 ferred these costs.” 573 F.3d at 1277. In other words, the cost of loading into DOE transportation casks would have to be borne by the plaintiff once DOE showed up to pick up the SNF.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Entergy Gulf States, Inc. v. United States
129 Fed. Cl. 135 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
128 Fed. Cl. 499, 2016 U.S. Claims LEXIS 1417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dairyland-power-cooperative-v-united-states-uscfc-2016.