This text of W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP (W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP, (W.D. Va. 2021).

Opinion

riLely 10/13/2021 JULIA C. DUDLEY, CLERK UNITED STATES DISTRICT COURT BY: si A. Little DEPUTY CLERK WESTERN DISTRICT OF VIRGINIA LYNCHBURG DIVISION

W.C. ENGLISH, INC., CASE NO. 6:17-cv-00018 Plaintiff, v. MEMORANDUM OPINION RUMMEL, KLEPPER & KAHL, LLP., ET AL, JUDGE NORMAN K. Moon Defendants.

I. Summary On June 10, 2021, a jury awarded nearly two million dollars to W.C. English, Inc. in its contract dispute with Rummel, Klepper & Kahl, LLP. It found that the quality assurance subcontract between the parties entitled English to damages or indemnification for costs incurred by English when it was forced to tear down and rebuild an improperly constructed bridge over Interstate 81. RK&K now seeks a directed verdict or, in the alternative, a new trial. Its briefing sets out four arguments for upending the jury’s determination. First, that the jury was not provided with sufficient evidence from which it could rationally allocate responsibility between RK&K and others for construction mistakes. Second, that the evidence proffered by English of its damages was improper in various respects. Third, that the Court’s failure to accept two of RK&K’s proposed jury instructions was error. And fourth, that equitable considerations should have precluded an award of prejudgment interest. The Court disagrees. The jury had ample evidence from which to make a reasonable determination of fault, and it must be presumed to have followed this Court’s instruction that it

do so. Neither is RK&K’s failure to present certain arguments respecting the damages calculation grounds to convene a new jury or substitute this Court’s judgment. With respect to RK&K’s rejected jury instructions, RK&K has not offered any reason for the Court to repudiate its trial determination. Finally, Virginia law gives the factfinder complete discretion to award prejudgment interest. RK&K was free to present relevant equitable considerations to the jury at

trial. But this Court has no legal basis to throw out the verdict because RK&K failed to do so. II. Facts & Trial Evidence In 2009, the Virginia Department of Transportation (“VDOT”) awarded W.C. English, Inc. a $75 million construction contract to build a bridge over Interstate 81 near Lexington, Virginia. English, in turn, retained Rummel, Klepper & Kahn, LLP to provide quality assurance services for the project. During construction, and after much of the bridge’s concrete deck had already been poured, VDOT discovered that the depth of concrete over the deck’s rebars was incorrect. The contract between VDOT and English required an 8.5-inch concrete deck reinforced by two

separate mats of crisscrossed rebars. English was to leave a 1.5-inch concrete cover beneath the mats and a 2.75-inch cover over the top. To create the proper spacing, English initially installed 2.5-inch slab runners between the two mats. But along the way, a decision was made to insert 1.75-inch slab runners instead. That change was fatal, ultimately lifting the top cover to 3.75- inches instead of the required 2.75. VDOT refused to accept the bridge, and eventually demanded that English demolish and rebuild it. Which English did at a cost of over $2.8 million. English brought this diversity action against RK&K for breach of contract and indemnification on the theory that RK&K’s failure to meet its contractual obligations was, at least in part, responsible for its $2.8 million loss.1 This Court initially awarded summary judgment to RK&K, construing the parties’ contract to create a species of contributory negligence liability, such that English’s own negligence barred any recovery from RK&K. But the Fourth Circuit reversed, finding that an equally reasonable interpretation of the contract would impose a comparative negligence scheme, under which each party would be liable for a

percentage of the total loss in accordance with its respective share of fault. Where a contract contains this kind of ambiguity, it is for the factfinder to decide between the competing interpretations. W.C. English, Inc. v. RK&K, 934 F.3d 398, 402 (4th Cir. 2019). The Fourth Circuit concluded with an unequivocal assignment of responsibility to the jury: “On remand, it will fall to the factfinder to interpret the relevant aspects of the contract and to determine the effect of any breach by English on RK&K’s liability.” Id. at 405. A four-day trial was held, in which both RK&K and English attempted to convince the jury that the other party was primarily to blame for the defects in the original bridge. English offered testimony from its project coordinator, Dylan Frazier, that it was Richard Clarke,

RK&K’s Quality Assurance Manager, who originally instructed English to switch from the correct 2.5-inch slab-runners to the incorrect 1.75-inch. 1d Tr. 187: 11–14. Frazier also testified that Clarke stopped English’s work, threatened to exercise his authority as Quality Assurance Manager to withhold payment from English if the 1.75-inch runners were not substituted, and assured English’s on-site employees that the shorter slab runners met the necessary specifications. Id. at 187:20–25.

1 English also sued CDM Smith, Inc., which had subcontracted with English to provide quality control services for the bridge construction. But English settled its claims against CDM Smith for $100,000. Def.’s Ex. 49. English also offered evidence that RK&K conducted dry-run measurements a few days later to ensure that the mats were at the correct height before the concrete was poured. 2d Tr. 104:17–105:18. Those measurements showed that most of the bridge deck was out of specification. Id. at 105:21. According to English’s evidence, Clarke was told this information. Id. at 106:21–107:11. But, also according to English’s evidence, neither Clarke nor anyone else

at RK&K took action to correct the problem before it was, quite literally, set in stone. 4d Tr. 41:22–42:5. Instead, Clarke completed an inspection shortly before the concrete pour, in which he certified that “spacing, location and edge clearances of all reinforcing mats conform.” Pl.’s. Ex. 18; 4d Tr. 44–46. Contributing perspective to these facts, English provided the jury with the expert testimony of Charles Gee. Gee opined that RK&K failed to meet its standard of care to English. 2d Tr. 172: 8–12. More specifically, he testified that Clarke failed in his standard of care if he threatened to withhold payment if English did not use the shorter, incorrect, slab runners; that Clarke had actual knowledge of the nonconformity that ultimately caused the bridge to be torn

down; and that Clarke should not have approved the deck to be poured. Id. at 163–173. While everyone shared some blame for what happened, Gee concluded that RK&K’s Quality Assurance Manager Richard Clarke bore “primary responsibility” for the cost of removing and replacing the bridge. Id. at 168. Of course, RK&K offered its own version of events. For example, Clarke denied on cross examination that he ever instructed English to use the shorter slab runners. 4d Tr. 52–53. And he testified on direct that he had attempted to convince English’s superintendent, Matt Hackney, that the pour should be postponed because the dry run numbers were outside of specification. 4d Tr. 25. RK&K offered evidence that English’s superintendent was made aware that the bridge was outside of specification before the pour by other individuals as well. 2d Tr. 49, 76; Pl.’s Ex. 12, 4/21/2012. Unsurprisingly, RK&K’s expert, Kevin Bocock, testified that RK&K had met its standard of care and was not primarily responsible for the loss because “the whole project team is working together.” 4d Tr. 88. After hearing all the evidence—consisting of twelve fact witnesses, three expert

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Noel v. Artson
641 F.3d 580 (Fourth Circuit, 2011)
King v. McMillan
594 F.3d 301 (Fourth Circuit, 2010)
Shepard v. Capitol Foundry of Virginia, Inc.
554 S.E.2d 72 (Supreme Court of Virginia, 2001)
Fairfax County Redevelopment & Housing Authority v. Worcester Bros.
514 S.E.2d 147 (Supreme Court of Virginia, 1999)
Reid v. Ayscue
436 S.E.2d 439 (Supreme Court of Virginia, 1993)
Younger v. Appalachian Power Co.
202 S.E.2d 866 (Supreme Court of Virginia, 1974)
Hale v. Fawcett
202 S.E.2d 923 (Supreme Court of Virginia, 1974)
Continental Insurance v. City of Virginia Beach
908 F. Supp. 341 (E.D. Virginia, 1995)
Hughston v. New Home Media
552 F. Supp. 2d 559 (E.D. Virginia, 2008)
Grayson O Company v. Agadir International LLC
856 F.3d 307 (Fourth Circuit, 2017)
W. C. English, Inc. v. Rummel, Klepper & Kahl, LLP
934 F.3d 398 (Fourth Circuit, 2019)
BioVeris Corp. v. Wohlstadter
69 F. Supp. 3d 574 (W.D. Virginia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wc-english-inc-v-rummel-klepper-kahl-llp-vawd-2021.