ARCO/Murray National Construction Company, Inc. v. Owl Creek Energy, LLC

CourtDistrict Court, E.D. Virginia
DecidedJanuary 5, 2023
Docket2:21-cv-00346
StatusUnknown

This text of ARCO/Murray National Construction Company, Inc. v. Owl Creek Energy, LLC (ARCO/Murray National Construction Company, Inc. v. Owl Creek Energy, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ARCO/Murray National Construction Company, Inc. v. Owl Creek Energy, LLC, (E.D. Va. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Norfolk Division ARCO/MURRAY NATIONAL CONSTRUCTION COMPANY, INC., Plaintiff, Vv. Civil Action No. 2:21-cv-00346 OWL CREEK ENERGY, LLC, et al, Defendants.

OPINION AND ORDER In this construction case, Plaintiff ARCO/Murray National Construction Company, Inc., a general contractor (““ARCO/Murray” or “Contractor”), sued Owl Creek Energy, LLC (“Owl Creek” or “Owner”) for a balance due under a contract to build a manufacturing facility in Virginia Beach. Owl Creek counterclaimed, alleging ARCO/Murray breached the contract through defective performance. The matter is now before the court to resolve Owl Creek’s motion for partial summary judgement on ARCO/Murray’s claims for delay damages. (ECF No. 85). Owl Creek argues that ARCO/Murray is not entitled to the $402,790.00 in delay damages it seeks to recover because it failed to provide notice of the delays, cannot prove Owl Creek caused the delays, and waived delay damage claims when it submitted lien waivers for payment. Def.’s Br. Supp. Mot. Partial Summ. J. (“Def.’s Br.”) (ECF No. 86, at 2), ARCO/Murray opposed the motion, (“PI.’s Opp’n”) (ECF No. 91), and Owl Creek replied, (“Def.’s Reply”) (ECF No. 92). Neither party requested oral argument, and I do not find that argument would aid the decision-making process. Local Civ. R. 7(j). After reviewing the parties’ briefs and accompanying exhibits, I conclude that there are genuine disputes of material fact as to whether ARCO/Murray is entitled

to delay damages. Accordingly, for the reasons detailed below, the court DENIES Owl Creek’s motion for partial summary judgment. (ECF No. 85). I. BACKGROUND On January 4, 2019,' Owl Creek and ARCO/Murray entered into a contract? under which ARCO/Murray would design and construct a 500,000 square foot manufacturing facility in Virginia Beach, Virginia for Owl Creek (“the Project”). Def.’s Br., Ex. 1 (“Contract”) (ECF No. 86-1, at 2). The Contract initially called for substantial completion of the Project “on or before July 12, 2019,” with final completion to “be achieved as expeditiously as reasonably practicable.” Id. at 5. Of the $26 million total original cost for the Project, the Contract required Owl Creek to

' This summary recites facts articulated in the briefing, resolving disputes of fact in favor of ARCO/Murray as the non-moving party. Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150 (2000). The contract consists of many documents in the collective. Contract (ECF No. 86-1, at 3). The main provisions of the contract are found in two separately executed instruments, respectively titled “Modified Form of Agreement Between Owner and Design-Builder — Cost Plus Fee with an Option for a Guaranteed Maximum Price,” (“Base Contract”) and “Modified Form of General Conditions of Contract Between Owner and Design-Builder” (“General Conditions”). Id, at 1-38. The contract also encompasses the 12 exhibits accompanying the Base Contract and General Conditions, which include a Project schedule, design specifications, various lien waivers, a cost schedule, insurance requirements, and other miscellaneous documents not relevant to this motion. Id. at 3. 3 By the terms of the contract, substantial completion means that “the Work, or an agreed upon portion of the Work, is sufficiently complete in accordance with the Contract Documents so that Owner can occupy and use the Work or a portion thereof for its intended purposes or upon issuance of a Temporary Certificate of Occupancy, whichever occurs first.” Contract, (ECF No. 86-1, at 15). Final completion means that “all Work is complete in accordance with the Contract Documents, including but not limited to, any items identified in the punch list prepared under Section 6.6.1 and the submission of all documents set forth in Section 6.7.2.” Id. at 14. The punch list required by Section 6.6.1 details “all remaining incomplete or defective work that does not prevent Owner from utilizing the Work for its intended purpose.” Id. at 27. The documents set forth in Section 6.7.2 include an affidavit confirming that there are no claims, liens, or outstanding debts on the property; a final lien waiver; all operating manuals and warranties; and Certificates of Insurance. Id, at 28.

pay $815,431.00 to ARCO/Murray as compensation for the design-builder’s General Conditions.‘ Id. at 73-75, 92-93. On January 4, 2019—the same date the parties executed the Contract-—ARCO/Murray and Owl Creek executed Change Order 1, which changed the deadline for substantial completion to March 25, 2020. Def.’s Br., Ex. 2 (ECF No. 86-2, at 1). It also increased the amount of payment for ARCO/Murray’s General Conditions by $350,000.00 to compensate for the extended substantial completion date. Id. at 2. Thereafter, the parties executed eleven additional Change Orders, none of which changed the substantial completion date of March 25, 2020. See Def.’s Br., Ex. 3 (ECF No. 86-3). While the Project was underway, ARCO/Murray provided Owl Creek with several updates about the Project’s progress and timeline for completion. As required by the Contract,’ ARCO/Murray sent “Weekly Updates” to Owl Creek about the ongoing work, each of which included an “Open Issue Log” cataloging “outstanding critical items” requiring action by Owl Creek. See Pl.’s Opp’n, Ex. 6A-6E (ECF Nos. 91-6-91-10). On at least 24 occasions, ARCO/Murray advised Owl Creek of “overdue” action items and asked for prompt responses. Id. On nearly all these occasions, ARCO/Murray also informed Owl Creek that the overdue items were “impacting [its] ability to schedule activities and notify subcontractors of upcoming work.” Id. Additionally, on at least two occasions, ARCO/Murray sent revised Project schedules to Owl Creek showing that completion of the Project would be delayed beyond the March 25, 2020,

4 ARCO/Murray’s General Conditions included expenses for “project management, field supervision, field engineering, testing services, temporary utilities, construction cleaning, and travel expenses.” Contract (ECF No. 86-1, at 73, 92). > Section 1.9 of the Project’s Outline Specifications—which were included in the contract as Exhibit A— states that “ARCO shall provide electronic weekly updates (PDFs) and progress photos during the project.” Contract (ECF No. 86-1, at 45).

completion date set by Change Order 1. See Pl.’s Opp’n, Ex. 4 (ECF No. 91-4, at 3-4) (sent November 12, 2019, showing Project completion on June 19, 2020); Pl.’s Opp’n, Ex. 3 (ECF No. 91-3, at 3-4) (sent February 7, 2020, showing Project completion on July 2, 2020). When the March 25, 2020, deadline arrived, the Project had not yet reached substantial completion. On May 21, 2020, ARCO/Murray sent Owl Creek another revised schedule, this time showing a Project completion date of August 5, 2020. Pl.’s Opp’n, Ex. 2 (ECF No. 91-2, at 3-4). Additionally, throughout its time working on the Project, ARCO/Murray submitted a number of applications for payment to Owl Creek, each accompanied by a lien waiver in which ARCO/Murray “waive[d] and release[d] any and all lien, and claim or right to lien” on the Project “under the Statutes of the State of Virginia relating to Mechanics’ Liens, on account of labor or materials, or both.” Def.’s Br., Exs. 14, 17-19 (ECF Nos. 86-14, 86-17—86-19). The first relevant waiver was executed on July 31, 2020, in the amount of $899,621.40. Def.’s Br., Ex. 14 (ECF No. 86-14). On July 28, 2020, after the Contract date of substantial completion, but with the Project still ongoing, ARCO/Murray’s Director of Operations, Tom Strickland, prepared a document titled “General Conditions Summary — Owl Creek Energy.” Def.’s Br., Ex. 5 (“General Conditions Summary”) (ECF No. 86-5, at 2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Fairfax County Redevelopment & Housing Authority v. Worcester Bros.
514 S.E.2d 147 (Supreme Court of Virginia, 1999)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
TechDyn Systems Corp. v. Whittaker Corp.
427 S.E.2d 334 (Supreme Court of Virginia, 1993)
ADC Fairways Corp. v. Johnmark Construction, Inc.
343 S.E.2d 90 (Supreme Court of Virginia, 1986)
Pebble Building Co. v. G. J. Hopkins, Inc.
288 S.E.2d 437 (Supreme Court of Virginia, 1982)
State Farm Fire & Casualty Co. v. Walton
423 S.E.2d 188 (Supreme Court of Virginia, 1992)
Pettengill v. United States
867 F. Supp. 380 (E.D. Virginia, 1994)
McDevitt & Street Co. v. Marriott Corp.
713 F. Supp. 906 (E.D. Virginia, 1989)
Luria Steel & Trading Corp. v. Ford
9 F.R.D. 479 (D. Nebraska, 1949)
Baker DC, LLC v. Baggette Constr., Inc.
378 F. Supp. 3d 399 (D. Maryland, 2019)
Luria Bros. & Co. v. United States
369 F.2d 701 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
ARCO/Murray National Construction Company, Inc. v. Owl Creek Energy, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arcomurray-national-construction-company-inc-v-owl-creek-energy-llc-vaed-2023.