TechDyn Systems Corp. v. Whittaker Corp.

427 S.E.2d 334, 245 Va. 291, 9 Va. Law Rep. 994, 1993 Va. LEXIS 22
CourtSupreme Court of Virginia
DecidedFebruary 26, 1993
DocketRecord 920639
StatusPublished
Cited by21 cases

This text of 427 S.E.2d 334 (TechDyn Systems Corp. v. Whittaker Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TechDyn Systems Corp. v. Whittaker Corp., 427 S.E.2d 334, 245 Va. 291, 9 Va. Law Rep. 994, 1993 Va. LEXIS 22 (Va. 1993).

Opinion

*293 JUSTICE HASSELL

delivered the opinion of the Court.

The primary issue we consider in this appeal is whether a plaintiff, who filed an action for breach of contract, presented sufficient evidence from which a jury could find that the plaintiff’s damages were attributable to the acts and omissions of the defendant.

TechDyn Systems Corporation filed its amended motion for judgment against Whittaker Corporation alleging that Whittaker breached its obligations to perform the terms of a contract. TechDyn sought, among other things, compensation for all unreimbursed delay damages that it incurred as well as lost profits. Whittaker denied any contractual breaches and filed a counterclaim for damages for work performed beyond the scope of the contract.

A jury returned a verdict in favor of TechDyn in the amount of $2,101,000 on its claim for delay and a verdict in favor of Whittaker on its counterclaim of $564,676. Both parties filed post-trial motions and the trial court set aside the jury’s verdict for TechDyn and entered judgment in favor of Whittaker for $564,676. We awarded TechDyn an appeal, and agreed to consider Whittaker’s assignment of cross-error.

I. Facts

Although the trial court set the verdict aside, we accord the recipient of a jury verdict the benefit of all substantial conflicts in the evidence and all reasonable inferences that may be drawn therefrom. Therefore, we will state the facts most favorable to TechDyn regarding its claim for delay damages, and if there is any credible evidence in the record which supports the jury’s verdict, then we must reinstate that verdict and enter judgment thereon. Holland v. Shively, 243 Va. 308, 309-10, 415 S.E.2d 222, 223 (1992).

In 1985, the United States Air Force decided to install an air-to-ground tactical warning and control system in Iceland. The system, a sophisticated electronics network for the command and control of tactical aircraft and ships, is referred to as the Iceland Command and Control Enhancement Project (“Iceland Project”).

The Air Force had extensive discussions with Command, Control and Communications Corporation, which had the experience and computer software necessary for aircraft warning and control systems. The Air Force, however, decided to award the contract for the *294 Iceland Project to a qualified small business through the Small Business Administration’s 8A program and to direct the successful contractor to subcontract a substantial portion of the work to Command, Control and Communications Corporation.

The Air Force selected TechDyn as the general contractor and executed a contract with TechDyn, which is referred to as the prime contract. This contract directed that TechDyn obtain “all hardware, software and related documentation for the processing and display functional area ... as defined in the statement of work and specifications from Command, Control and Communications Corporation.” TechDyn executed a subcontract with Command, Control and Communications Corporation as required by the prime contract.

Shortly after the subcontract was awarded, Command, Control and Communications Corporation was acquired by Whittaker Command and Control Systems, which assumed all obligations and liabilities under the subcontract. Later, Whittaker Corporation, acting through its Whittaker Electronics Systems division, assumed Whit-taker Command and Control Systems’ obligations and liabilities under the subcontract.

Leo S. Morrison, Jr., chairman of the board and president of TechDyn, testified that the date of completion for the processing and display functional area of the Iceland Project was December 31, 1986. According to Morrison, completion of the project was delayed because of numerous contractual breaches committed by Whittaker. For example, David Yennowine, TechDyn’s supervisor of subcontracts and purchasing, received a letter from Marie E. Raymond, Whittaker’s director of contracts, informing TechDyn that work on the project would be delayed because of Whittaker’s corporate reorganization.

A series of mergers and acquisitions at Whittaker and its acquired companies caused numerous personnel changes and further delayed work on the Iceland Project. Morrison testified that each time there was a change in personnel, key people from the Whittaker organization “disappeared” and new people “who had not been involved in the project . . . came on the scene.”

Donald Ray Ellis was TechDyn’s project manager. He and certain Air Force officials were present when Whittaker employees undertook performance verification tests on software provided by Whittaker. Numerous deficiencies in the operational software were discovered, and the Air Force refused to accept it. There were so many failures that Ellis and an Air Force program manager requested a *295 meeting with Whittaker’s representatives to resolve the poor state of operational software. Other tests disclosed deficiencies in the operational software, and the Air Force declared the software unacceptable.

In 1988, T. Brancati, president of Whittaker, informed TechDyn that Whittaker intended to stop its work on the Iceland Project and ordered TechDyn to remove its equipment from Whittaker’s facilities within 30 days. Furthermore, Whittaker informed TechDyn that if it failed to remove its equipment, TechDyn would be charged $20,000 per month in rent.

TechDyn approached the Air Force several times seeking permission to terminate its subcontract with Whittaker, but the Air Force refused. TechDyn eventually terminated Whittaker with respect to other portions of the work because TechDyn was not contractually required to acquire those services from Whittaker.

TechDyn filed a claim with the Air Force requesting an equitable adjustment to the prime contract for numerous reasons, including certain delay attributable to the Air Force. After extensive negotiations, the Air Force made an equitable adjustment, and TechDyn received a settlement of approximately $1.7 million. TechDyn’s claim against the Air Force did not represent compensation for any delay or damages caused by Whittaker.

Greg D. Crider, a consultant, was permitted to testify as an expert witness on behalf of TechDyn. Crider, who had extensive experience identifying causes of delays on construction projects, performed a schedule analysis on the Iceland Project.

At trial, Crider was asked to analyze the Iceland Project, identify the delays that occurred, and describe the effect of the delays on the overall project completion. Crider identified critical delays in four major areas: software design, software development, software testing and correction, and final system delivery. Crider attributed a total of 53 months of critical delay solely to Whittaker. Crider testified that TechDyn was not claiming compensation for any delay that was attributable to the Air Force.

William Curtis Hise, TechDyn’s vice president and director of management support operations and chief financial officer, also testified regarding the Iceland Project’s delays.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JTH Tax, Inc. v. Aime
236 F. Supp. 3d 929 (E.D. Virginia, 2017)
Cornerstone Construction Services, L.L.C. v. Davison
81 Va. Cir. 328 (Orange County Circuit Court, 2010)
United States v. Church
701 F. Supp. 2d 814 (W.D. Virginia, 2010)
Commonwealth of Virginia, etc. v. AMEC Civil, LLC
677 S.E.2d 633 (Court of Appeals of Virginia, 2009)
AMEC Civil, LLC v. Commonwealth of Virginia, etc.
Court of Appeals of Virginia, 2009
Teleguz v. Com.
643 S.E.2d 708 (Supreme Court of Virginia, 2007)
Microstrategy, Inc. v. Business Objects, s.a.
429 F.3d 1344 (Federal Circuit, 2005)
7-Eleven, Inc. v. Department of Environmental Quality
590 S.E.2d 84 (Court of Appeals of Virginia, 2003)
Clark v. Scott
520 S.E.2d 366 (Supreme Court of Virginia, 1999)
E. J. Miller Construction Co. v. Holt
56 Va. Cir. 153 (Roanoke County Circuit Court, 1998)
Paws With A Cause v. Crumpler
Fourth Circuit, 1996

Cite This Page — Counsel Stack

Bluebook (online)
427 S.E.2d 334, 245 Va. 291, 9 Va. Law Rep. 994, 1993 Va. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/techdyn-systems-corp-v-whittaker-corp-va-1993.