Cornerstone Construction Services, L.L.C. v. Davison

81 Va. Cir. 328, 2010 Va. Cir. LEXIS 286
CourtCircuit Court of the 9th Judicial Circuit of Florida, Orange County
DecidedNovember 3, 2010
DocketCase No. CL07-000181
StatusPublished

This text of 81 Va. Cir. 328 (Cornerstone Construction Services, L.L.C. v. Davison) is published on Counsel Stack Legal Research, covering Circuit Court of the 9th Judicial Circuit of Florida, Orange County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornerstone Construction Services, L.L.C. v. Davison, 81 Va. Cir. 328, 2010 Va. Cir. LEXIS 286 (Fla. Super. Ct. 2010).

Opinion

By Judge Daniel R. Bouton

This case is before the court for a ruling on all disputed issues. Atrial was conducted on July 12th, July 13th, and August 18th. Subsequent to the completion of the ore tenus hearing, counsel submitted written arguments in support of their respective positions. The court has now had an opportunity to review the evidence, study the trial exhibits, and give consideration to the arguments of counsel. I am writing to advise you as to how the disputed issues will be resolved.

Cornerstone s Claim for Damages under the Contract

Cornerstone’s claim here is premised on the refusal of Davison to pay the fifth and final draw. Prior to the request for payment, the parties had worked together on the project in a reasonably cooperative way. All previous draws had been paid without any major disputes or disagreements. Davison explained at trial why he refused to pay the final draw. However, it is not necessary for the court to analyze his testimony on this point for two reasons. First, Cornerstone failed to prove that it complied with the contractual conditions that had to be satisfied before Davison was obligated to pay the draw. Second, Cornerstone’s evidence on its damage claim is not sufficient for an award.

[329]*329With regard to the contract, three conditions had to be met before Davison was required to make any payment. First, the contract states that receipts “for all of the above transactions shall be given to the owner periodically in order to make draws.” In the court’s view, the only sensible way to construe the “above transactions” clause of the contract is for it to refer to and incorporate the preceding provisions on out of pocket expenses. Here, Davison’s obligation was to “reimburse the GC for any out of pocket expenses incurred relating to this project.” Therefore, “periodically” producing the receipts for out of pocket expenses was Cornerstone’s duty under the contract. Cornerstone’s second obligation was to provide Davison with “receipts for all labor, material, equipment, subcontractors, or any other direct cost.” Third, Cornerstone had to furnish Davison with an “updated schedule.” Once Cornerstone supplied Davison with all of the documents covered by these three provisions of the contract, the conditions for the payment of the draw would be satisfied. Davison would then be required to make payment within five days.

The court will now turn its attention to the evidence that Cornerstone introduced regarding what it turned over to Davison before demanding that he pay the final draw. Specifically, at trial, Cornerstone produced the following documents: the contract, an expense summary, and a “stop work” letter. Nevertheless, with regard to the conditions pertaining to the disputed draw, the plaintiff did not introduce any receipts for out of pocket expenses that were delivered to Davison prior to the request for payment. Furthermore, no evidence of any receipts for labor, materials, subcontractors, or any other direct cost was produced. Finally, there was no proof that Davison was furnished with an updated schedule. Witnesses for Cornerstone testified that Davison was given “everything” that was available and that the company provided him with “all of the receipts.” However, the court finds that these general statements do not prove that Cornerstone complied with the draw provisions of the contract. The court rejects this testimony as insufficient on this point. As a result, the court rules that Cornerstone did not prove that it supplied Davison with the specific items required by the contract and thus did not satisfy the conditions for the payment of the draw.

The second reason why Cornerstone is not entitled to any relief under the contract stems from the evidence on damages. Here, under Virginia law, a plaintiff seeking a recovery in a contract case is not required to prove the exact amount of his damages. Nevertheless, a plaintiff is not entitled to recover unless he elicits sufficient facts and circumstances that permit the trier of fact to make a reasonable estimate of the damages. Clark v. Scott, 258 Va. 296(1999).

The only evidence presented to the court on damages is contained in Plaintiff’s Exhibit 2. Yet this document is merely a summary sheet that contains a plethora of figures, many of which are unrelated to the fifth and final draw. The exhibit is filled with numbers and computations that have [330]*330little to do with what can be claimed under the contract. Significantly, the draw itself, or a copy of it, was never introduced at trial. Furthermore, the witnesses who testified for the plaintiff did not provide the court with credible information about the amount and the details of the draw. They did not explain how or whether the trial exhibit could be relied on to determine the amount of the draw and what damages, if any, could be attributed to the failure to pay it. The court is not required to review the trial exhibits and then guess whether some of the figures on it might comprise part of a damage award. Such an exercise would amount to judicial speculation, surmise, and conjecture. Rather, Cornerstone has the burden of proof on damages and must point or direct the court to specific evidence in the record that establishes a reasonable amount of damages. At best, the evidence here suggests that Davison might owe some additional money to the plaintiff. This is not sufficient proof for a damage award, however, and the company has failed to sustain its burden.

Davison’s Counterclaim under the Contract

The court will dismiss Davison’s counterclaim for two reasons. First, the pleadings do not contain any theory of relief that can be based on the contract between the parties. Second, regardless of what Davison states in his pleadings, he has not produced sufficient evidence to prove any claim.

With regard to the pleadings, Davison’s counterclaim asserts that he was “operating under strict budget requirements” and that he “needed to keep track of costs to avoid going over budget.” Davison states that Cornerstone “failed to keep track of costs, resulting in a house costing $175,000.00 more to complete than originally anticipated.” To begin with, it must be stressed that there is nothing in the contract about these allegations. Specifically, the contract does not include an agreed upon price, and it provides no remedy to Davison in the event that the house cost “more than he anticipated.” A critical factor in this context is that the parties never negotiated or agreed on a set price for the construction of the home. Furthermore, there is no provision in the contract that required Cornerstone to take into account Davison’s “strict budget requirements.” The contract was a “cost plus fixed fee agreement,” and either party could terminate it by giving the other side five days notice. As a result, the court finds that the duties that Davison claims were breached by Cornerstone were never part of the contract.

Next, in his trial brief, Davison argues that he made “overpayments” to Cornerstone and that he paid sums that were not properly documented based on the contract. However, these facts were not pleaded as a basis of the counterclaim. Therefore, the court may not consider them in determining whether Davison should prevail. This principle was cited by the Supreme Court of Virginia as part of its holding in Ted Lansing [331]*331Supply v. Royal Aluminum, 221 Va. 1139(1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mongold v. Woods
677 S.E.2d 288 (Supreme Court of Virginia, 2009)
ITT Hartford Group, Inc. v. Virginia Financial Associates, Inc.
520 S.E.2d 355 (Supreme Court of Virginia, 1999)
Clark v. Scott
520 S.E.2d 366 (Supreme Court of Virginia, 1999)
Po River Water & Sewer Co. v. Indian Acres Club of Thornburg, Inc.
495 S.E.2d 478 (Supreme Court of Virginia, 1998)
TechDyn Systems Corp. v. Whittaker Corp.
427 S.E.2d 334 (Supreme Court of Virginia, 1993)
Marine Development Corp. v. Rodak
300 S.E.2d 763 (Supreme Court of Virginia, 1983)
Ted Lansing Supply Co. v. Royal Aluminum & Construction Corp.
277 S.E.2d 228 (Supreme Court of Virginia, 1981)
Hendrickson v. Meredith
170 S.E. 602 (Supreme Court of Virginia, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
81 Va. Cir. 328, 2010 Va. Cir. LEXIS 286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornerstone-construction-services-llc-v-davison-flacirct9ora-2010.