Royal Electric Constr. Corp. v. Ohio State Univ.

1995 Ohio 131, 73 Ohio St. 3d 110
CourtOhio Supreme Court
DecidedAugust 16, 1995
Docket1994-0419
StatusPublished
Cited by15 cases

This text of 1995 Ohio 131 (Royal Electric Constr. Corp. v. Ohio State Univ.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royal Electric Constr. Corp. v. Ohio State Univ., 1995 Ohio 131, 73 Ohio St. 3d 110 (Ohio 1995).

Opinion

[This opinion has been published in Ohio Official Reports at 73 Ohio St.3d 110.]

ROYAL ELECTRIC CONSTRUCTION CORPORATION, APPELLANT, v. OHIO STATE UNIVERSITY ET AL., APPELLEES. [Cite as Royal Electric Constr. Corp. v. Ohio State Univ., 1995-Ohio-131.] Court of Claims—Prejudgment interest—R.C. 2743.18(A), construed and applied—Interest when rate not stipulated—R.C. 1343.03(A), construed and applied. __________________ In a case involving breach of contract where liability is determined and damages are awarded against the state, the aggrieved party is entitled to prejudgment interest on the amount of damages found due by the Court of Claims. The award of prejudgment interest is compensation to the plaintiff for the period of time between accrual of the claim and judgment, regardless of whether the judgment is based on a claim which was liquidated or unliquidated and even if the sum due was not capable of ascertainment until determined by the court. (R.C. 2743.18[A] and 1343.03[A], construed and applied.) __________________ (No. 94-419—Submitted April 18, 1995—Decided August 16, 1995.) APPEAL from the Court of Appeals for Franklin County, Nos. 93AP-399 and 93AP-424. __________________ {¶ 1} This appeal involves prejudgment interest. The parties involved in this case are appellant, Royal Electric Construction Corporation ("Royal"), and appellees, the Ohio State University ("OSU") and the Ohio Department of Administrative Services ("ODAS"). The facts and procedural posture of this appeal can be gleaned from the decisions of the trial court and court of appeals. SUPREME COURT OF OHIO

{¶ 2} The facts giving rise to this appeal concern two contracts entered into by the parties. Royal was hired to work on two buildings located on the campus of OSU. Both projects were publicly bid and Royal submitted the lowest and best bid for each project. {¶ 3} Specifically, on June 4, 1987, Royal entered into a contract to perform electrical renovations involving Lazenby Hall. The project, regarding the work to be performed by Royal, was scheduled to be completed on September 9, 1988. The project was, however, fraught with numerous delays and/or disruptions and, consequently, Royal's work on the project was not completed or substantially completed until March 12, 1989. {¶ 4} Further, during the time that Royal was involved with the Lazenby Hall project, Royal tendered a bid to participate in the renovation of Hamilton Hall. Royal tendered its bid on January 19, 1989, and was later asked to extend the terms of the bid through April 28, 1989. Royal agreed to the extension and was awarded the contract. Thereafter, a notice to proceed was issued authorizing Royal to commence work on May 31, 1989. The work was to be completed by May 31, 1991. However, the commencement date was postponed by appellees until September 1, 1989, and, as a result, the work was not completed or substantially completed by Royal until September 1, 1991. {¶ 5} The delays experienced by Royal involving both the Lazenby Hall and Hamilton Hall projects were not the fault of Royal. Rather, the delays were the responsibility of appellees. {¶ 6} As a result of the delays and other problems associated with the projects, Royal attempted to seek redress under the "Article 8" administrative review procedures set forth in both contracts. Eventually, Royal filed suit in the Court of Claims. {¶ 7} In its amended complaint, Royal alleged that appellees breached both the Lazenby Hall and Hamilton Hall contracts, that appellees were responsible for

2 January Term, 1995

"delays and disruptions" regarding the Lazenby Hall project, and that appellees caused a "substantial delay" in the commencement of the Hamilton Hall project. Royal claimed that the delays were caused by the appellees' failure to issue "change orders" and their refusal to resolve disputes under the terms of the contracts. Royal further alleged that as a result of the delays it was required to perform "extra work," that it "incurred additional costs and expenses," that it "suffered damage to its overhead," and that it "suffered serious damage to its business." Moreover, with respect to the Lazenby Hall contract, Royal claimed that appellees wrongfully refused "to remit $8,184.00 in retainage still owed * * *." Additionally, with regard to the Hamilton Hall contract, Royal alleged that appellees breached the contract "by insisting that Royal * * * revise * * * and replace certain fixtures that were already installed, even though the fixtures originally ordered and supplied by Royal * * * were in full compliance with the Hamilton Hall Contract." {¶ 8} The parties conducted discovery and the case proceeded to trial. At trial, the court heard extensive testimony from numerous witnesses (resulting in approximately four thousand pages of trial transcript) and hundreds of pages of exhibits were admitted into evidence. {¶ 9} Thereafter, the trial court issued an exhaustive decision. The court discussed the various theories and issues raised by the parties in support of their positions, including various methods and data utilized by the parties in determining the amount of damages owed by appellees to Royal. On February 19, 1993, the trial court entered judgment in favor of Royal. {¶ 10} In the February 19, 1993 judgment entry, the trial court set forth the specific damages owed by appellees. With respect to Lazenby Hall, the trial court held that Royal was entitled to $96,541 for "lost man-hours expended," $32,238 for "unabsorbed home office overhead losses," and $58,338 for "prejudgment interest." With regard to the Hamilton Hall project, the trial court held that Royal was entitled

3 SUPREME COURT OF OHIO

to $38,815 "for unabsorbed home office overhead," $50,951 "for losses ocassioned [sic] by the wrongful rejection of plaintiff's R-3 lighting fixtures," and $13,914 for "prejudgment interest." The trial court also found that Royal was entitled to $1,659 from ODAS, individually, for interest on the amount wrongfully retained under the Lazenby Hall contract. {¶ 11} Subsequently, in a judgment entry dated May 3, 1993, the trial court corrected its prior award to Royal involving the light-fixture matter. The court concluded that the proper amount owed by appellees to Royal was $58,320, not $50,951. Given this correction, the court held that Royal was entitled to $15,056 in interest on losses incurred by Royal concerning the Hamilton Hall project. Moreover, in this entry, the trial court reaffirmed the propriety of awarding prejudgment interest to Royal regarding both projects: "* * * After considering all of defendants' arguments, the court finds that the interest awarded is justified for several reasons. Contrary to defendants' analysis, the claims of the plaintiff were capable of calculation by the state and were therefore liquidated debts. Also, the state through reasonable application of its Article 8 proceedings, could have determined the amount due under any number of standards recognized in the construction industry. The mere act of disputing the amount does not control whether the debt is liquidated or unliquidated. Finally, the court considers the award of prejudgment interest necessary to make plaintiff whole." (Emphasis added.) {¶ 12} Upon appeal, the Court of Appeals for Franklin County held, among other things, that the trial court properly awarded damages to Royal for the delays encountered by Royal on the Lazenby Hall and Hamilton Hall projects. The court of appeals also remanded the cause to the trial court to consider and clarify certain matters regarding the trial court's calculations of overhead losses suffered by Royal. The court of appeals, however, held that the trial court erred in awarding prejudgment interest to Royal. The court of appeals determined that the interest

4 January Term, 1995

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Classic Comfort Heating & Supply, L.L.C. v. Miller
2022 Ohio 855 (Ohio Court of Appeals, 2022)
Cleveland Constr., Inc. v. Kent State Univ.
2011 Ohio 6860 (Ohio Court of Claims, 2011)
R.E. Schweitzer Constr. Co. v. Univ. of Cincinnati
2010 Ohio 4339 (Ohio Court of Claims, 2010)
Zanesville Glass Supply v. Goff, Ct2007-0026 (3-10-2008)
2008 Ohio 1243 (Ohio Court of Appeals, 2008)
Peirce v. J.C. Meyer Co. Inc., Unpublished Decision (8-8-2006)
2006 Ohio 4065 (Ohio Court of Appeals, 2006)
Waina v. Abdallah, Unpublished Decision (4-27-2006)
2006 Ohio 2090 (Ohio Court of Appeals, 2006)
Handel's Ent., Inc. v. Wood, Unpublished Decision (12-22-2005)
2005 Ohio 6922 (Ohio Court of Appeals, 2005)
Bunnell Elec. v. Ameriwash, Unpublished Decision (5-23-2005)
2005 Ohio 2502 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
1995 Ohio 131, 73 Ohio St. 3d 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royal-electric-constr-corp-v-ohio-state-univ-ohio-1995.