Cleveland Constr., Inc. v. Kent State Univ.

2011 Ohio 6860
CourtOhio Court of Claims
DecidedNovember 10, 2011
Docket2003-10724
StatusPublished

This text of 2011 Ohio 6860 (Cleveland Constr., Inc. v. Kent State Univ.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cleveland Constr., Inc. v. Kent State Univ., 2011 Ohio 6860 (Ohio Super. Ct. 2011).

Opinion

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

CLEVELAND CONSTRUCTION, INC., Case No. 2003-10724

Plaintiff,

v. Judge Joseph T. Clark

KENT STATE UNIVERSITY,

Defendant. DECISION

{¶1} This case arises out of the construction of four residence halls at defendant, Kent State University (KSU). Plaintiff, Cleveland Construction, Inc. (CCI), brought this action alleging breach of contract. Defendant filed a counterclaim seeking damages for plaintiff’s allegedly defective and incomplete work. {¶2} On June 24, 2010, the Tenth District Court of Appeals issued a decision, affirming in part and reversing in part, this court’s July 23, 2009 judgment in favor of plaintiff. On July 29, 2011, the court issued an entry approving the parties’ July 26, 2011 stipulation and entered judgment in favor of plaintiff in the amount of $2,086,868.69, representing the undisputed contract balance and interest. The remaining issue in the case is now before the court. {¶3} The court of appeals determined that “[b]ecause both waiver and failure to exhaust administrative remedies are affirmative defenses, [defendant] bore the burden of proving both defenses at trial.” Cleveland Constr., Inc. v. Kent State Univ., Franklin App. No.09AP-822, 2010-Ohio-2906, ¶48. On remand, the court must decide “whether [defendant] should prevail on its waiver and exhaustion of administrative remedies defenses given the evidence in the record.” Id. The court of appeals noted “that [defendant] has only preserved these defenses against the breach of contract claims Case No. 2003-10724 -2 - ENTRY

arising from the weather and strike delay and the denial of change order requests 39/160, 44-R, 64, 93, 128, 148, 154 and 206.” Id. at fn. 4.

WAIVER {¶4} Defendant’s waiver defense is based upon Article 8.1.1 of the General Conditions (GC) of the contract, which provides as follows: {¶5} “Any claim against the State shall be made in writing to the Associate [Braun & Steidl Associates, Inc. (BSA)] and filed prior to Contract Completion, provided the Contractor notified the Associate no more than ten (10) days after the initial occurrence of the facts, which are the basis of the claim. To the fullest extent permitted by law, failure of the Contractor to timely provide such notice shall constitute a waiver by the Contractor of any claim for additional compensation or for mitigation of Liquidated Damages.” {¶6} According to the court of appeals, Article 8.1.1 “is unambiguous: CCI waived all claims for additional compensation that it did not file with BSA.” Id. at ¶30. Therefore, the law of this case requires the court to determine which of plaintiff’s claims were not filed with BSA.

EXHAUSTION {¶7} The affirmative defense of exhaustion requires consideration of whether the administrative remedies that plaintiff commenced pursuant Article 8.1.1 were “exhausted” according to the procedures in Articles 8.2, 8.3, and 8.4. The Tenth District Court of Appeals noted that R.C. 153.12(B) “precludes a contractor from bringing a breach of contract action against the state unless ‘administrative remedies provided for in [a public improvement] contract * * * are exhausted.’ The administrative dispute resolution process detailed in Article 8 required CCI to first file all claims with the associate [8.1.1]. If the associate decided against CCI [8.2], then CCI could appeal the Case No. 2003-10724 -2 - ENTRY

associate’s decision to the project administrator [8.3]. If the project administrator could not reach a mutually agreeable resolution of CCI's claim, CCI could appeal to the Office of the University Architect [8.4]. Kent State contends that it proved that CCI did not submit its delay and change order request claims through each step of the administrative dispute resolution process. Consequently, Kent State argues that R.C. 153.12(B) bars CCI from filing these claims in the Court of Claims.” Id. at ¶28. {¶8} R.C. 153.12(B) states in pertinent part: {¶9} “If a dispute arises between the state and a contractor concerning the terms of a public improvement contract let by the state or concerning a breach of the contract, and after administrative remedies provided for in such contract and any alternative dispute resolution procedures provided in accordance with guidelines established by the director of administrative services are exhausted, the contractor may bring an action to the court of claims in accordance with Chapter 2743 of the Revised Code. * * * As used in this division, ‘dispute’ means a disagreement between the state and the contractor concerning a public improvement contract let by the state.” (Emphasis added.) {¶10} Furthermore, R.C. 153.16(B) sets a time limit for administrative procedures regarding claims made pursuant to a public works contract. {¶11} R.C. 153.16(B) provides as follows: {¶12} “Notwithstanding any contract provision to the contrary, any claim submitted under a public works contract that the state or any institution supported in whole or in part by the state enters into for any project subject to sections 153.01 to 153.11 of the Revised Code shall be resolved within one hundred twenty days. After the end of this one hundred twenty-day period, the contractor shall be deemed to have exhausted all administrative remedies for purposes of division (B) of section 153.12 of the Revised Code.” See Painting Co. v. Ohio State Univ., Franklin App. No. 09AP-78, 2009-Ohio-5710, ¶13-15. (“Under the terms of R.C. 153.12(B) and 153.16(B), plaintiff’s cause of action for breach of contract accrued * * * when the 120-day period lapsed Case No. 2003-10724 -2 - ENTRY

after plaintiff’s appeal to the State Architect, regardless of whether the State Architect subsequently issued a final decision on the validity of plaintiff’s claims.”)

CHANGE ORDERS {¶13} Michael Bruder, defendant’s project manager, testified extensively regarding the change order requests (COR) that were submitted by plaintiff. At the liability trial, counsel for defendant inquired as to Bruder’s knowledge about each COR. During the examination on COR 44-R, counsel asked Bruder, for the first time, whether he recalled Article 8 processing. Bruder’s testimony on these issues included the following: {¶14} “Q. Do you know – incidentally, do you know whether Cleveland undertook any Article 8 procedures with respect to 44-R? {¶15} “A. I don’t know. {¶16} “Q. Okay. Do you recall any Article 8 procedures? {¶17} “A. I recall that there were some requests for some Article 8s, yes. {¶18} “Q. With respect to Change Order Request 44-R, you don’t recall any? And I’m going to ask you about Article 8s on every one of these. {¶19} “A. I don’t recall on this instance. {¶20} “Q. You are a person at the University that – during some stage in the Article 8 process does review Article 8 requests; is that right? {¶21} “A. That’s correct. {¶22} “Q. What is your role exactly? {¶23} “A. The first stage is a hearing at the field level is what’s specified, and that would be me.” (Emphasis added.) (Liability Trial Transcript, pages 2337-2338.) {¶24} Bruder specifically addressed Article 8 requests for CORs 64 and 93 during direct examination. Regarding COR 64, Bruder testified that plaintiff did not comply with Case No. 2003-10724 -2 - ENTRY

Article 8 filing requirements, and plaintiff concedes that defendant has met its burden of proving its waiver defense to that claim. As to COR 93, Bruder testified that defendant rejected plaintiff’s Article 8 request inasmuch as “there’s a requirement that the request be made within a certain time frame of the conflict, and that time had passed.” (Liability Trial Transcript, page 237, lines 13-16.) Based upon Bruder’s testimony, the court finds that defendant has met its burden of proof on both CORs 64 and 93.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Progressive Preferred Insurance
862 N.E.2d 850 (Ohio Court of Appeals, 2006)
Royal Electric Constr. Corp. v. Ohio State Univ.
1995 Ohio 131 (Ohio Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 6860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleveland-constr-inc-v-kent-state-univ-ohioctcl-2011.