Gordon Cons. v. Peterbilt of Cincinnati, Unpublished Decision (9-29-2003)

2003 Ohio 5111
CourtOhio Court of Appeals
DecidedSeptember 29, 2003
DocketCase No. CA2002-11-094.
StatusUnpublished
Cited by2 cases

This text of 2003 Ohio 5111 (Gordon Cons. v. Peterbilt of Cincinnati, Unpublished Decision (9-29-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gordon Cons. v. Peterbilt of Cincinnati, Unpublished Decision (9-29-2003), 2003 Ohio 5111 (Ohio Ct. App. 2003).

Opinions

OPINION
{¶ 1} Defendant-appellant, Peterbilt of Cincinnati, Inc., ("Peterbilt"), appeals the decision of the Clermont County Court of Common Pleas in a breach of contract action. We affirm the decision of the trial court.

{¶ 2} Peterbilt intended to build an addition to their existing dealership. Plaintiff-appellee, Gordon Construction, Inc. ("Gordon"), attempted to sell Peterbilt a building addition through a process called "design and build." Gordon sent Peterbilt a letter of intent describing their "design and build" agreement.

{¶ 3} The letter of intent stated that Gordon "will retain firms to assist in the development of preliminary site drawings, a topographical and site survey and preliminary architectural drawings for this project. Any costs associated with these services will be at the expense of Peterbilt * * * and paid upon their presentation. These costs should not exceed $6,000. When the project is developed, theses costs will be applied to the applicable budget line and equity for the project." Sam Stratton, the manager of Peterbilt in Cincinnati, signed the letter of intent.

{¶ 4} Gordon selected KBA, Inc., as architects and McGill Smith Punshon, Inc. ("MSP"), as engineers to develop the preliminary drawings. On July 18, 2000, Gordon, KBA, and MSP presented a set of plans to Peterbilt. Al Daugherty of Peterbilt asked Gordon, "who do you suppose is going to pay for all these drawings up to this point?" Gordon responded that it was "in the cost of business and would be in the cost of the project itself." However, Gordon stated, "if you get somebody else to build this addition then there will be a charge."

{¶ 5} After the initial meeting, Peterbilt's requirements changed and modifications to the project were made. KBA and MSP both indicated to Peterbilt that the modifications would change the scope of their work and additional drawings would be required. Peterbilt did not object to the additional work.

{¶ 6} Peterbilt and Gordon met again in August of 2000. At that time Peterbilt indicated that the cost of the addition project was too high. A revised budget for the project was presented to Peterbilt in September. However, Peterbilt informed Gordon that it would not proceed with the project.

{¶ 7} KBA billed Gordon $7,293.49 for their services. MSP billed Gordon $10,808.05 for their services. Gordon sent Peterbilt the KBA and MSP invoices. Peterbilt declined to pay the invoices.

{¶ 8} Gordon filed a complaint for breach of contract and unjust enrichment against Peterbilt on January 24, 2001. The issues were tried to the court. The trial court found for Gordon and awarded $18,101.54 plus prejudgment interest at the statutory rate. Peterbilt appeals the decision raising four assignments of error:

Assignment of Error No. 1:
{¶ 9} "THE TRIAL COURT ERRED IN AWARDING PREJUDGMENT INTEREST PURSUANT TO OHIO REVISED CODE 1343.03(A)."

{¶ 10} The decision to award or deny prejudgment interest is within the discretion of the trial court, and will not be reversed absent an abuse of that discretion. Feist v. Plesz, Summit App. No. 21312, 2003-Ohio-2843, at ¶ 18, citing Scioto Mem. Hosp. Assn., Inc. v.Price Waterhouse, 74 Ohio St.3d 474, 479, 1996-Ohio-365. An abuse of discretion is "more than an error of law or judgment; it implies that the court's attitude is unreasonable, arbitrary or unconscionable." Blakemorev. Blakemore (1983), 5 Ohio St.3d 217, 219.

{¶ 11} R.C. 1343.03(A) governs a trial court's award of prejudgment interest on claims arising out of breach of contract. Baldwinv. Rieger, Trumbull App. No. 2001-T-0106, 2002-Ohio-4368. Under R.C.1343.03(A), prejudgment interest is based upon the premise that a party to a contract should not retain the use of money owed under a contract when that amount is due and payable to the other contracting party. Luftv. Perry County Lumber Supply Co., Franklin App. No. 02AP-559, 2003-Ohio-2305.

{¶ 12} When money becomes "due and payable * * * upon a contract or other transaction * * * the creditor is entitled to interest at the rate of ten percent per annum[.]" R.C. 1343.03(A). An award of prejudgment interest "encourages prompt settlement and discourages defendants from opposing and prolonging, between injury and judgment, legitimate claims. Furthermore, prejudgment interest does not punish the party responsible for the underlying damages * * * but, rather, it acts as compensation and serves ultimately to make the aggrieved party whole."Royal Elec. Constr. Corp. v. Ohio State Univ., 73 Ohio St.3d 110,116-117, 1995-Ohio-131.

{¶ 13} The letter of intent states, "Gordon Construction, Inc. will retain firms to assist in the development of preliminary site drawings, a topographic and site survey and preliminary architectural drawings for this project. Any costs associated with these services will be at the expense of Peterbilt of Cincinnati, Inc. and paid upon their presentation. These costs should not exceed $6,000. When the project is developed, these costs will be applied to the applicable budget line and equity for the project."

{¶ 14} Stratton signed the letter of intent on behalf of Peterbilt. Gordon retained KBA and MSP to prepare architectural and engineering drawings. Preliminary drawings were prepared and presented to Stratton. Upon presentation of the drawings to Al Daugherty of Peterbilt, requests were made for modifications of the drawings. Peterbilt wanted to relocate the manner in which vehicles were serviced in the existing building. Peterbilt also wanted the architects to address how oil would be dispensed within the building. KBA and MSP were directed to change their plans.

{¶ 15} Because multiple changes were requested, multiple drawings were prepared. KBA billed Gordon $7,293.49 for their services. MSP billed Gordon $10,808.05 for their services. When it became apparent that Peterbilt was not going forward with the project, Gordon submitted the KBA and MSP bills to Stratton. Stratton forwarded the invoices to Peterbilt. Peterbilt decided not to pay the bills. Gordon paid KBA and MSP.

{¶ 16} Peterbilt was bound by the letter of intent to pay for the project development. Once the $18,101.54 became due and payable the creditor was entitled to interest if the contract was breached. The trial court did not abuse its discretion in awarding prejudgment interest on the amounts that were due and payable. Therefore, the first assignment of error is overruled.

Assignment of Error No. 2:
{¶ 17} "THE TRIAL COURT ERRED IN INTERPRETING THE LETTER OF INTENT BY FINDING THAT THE $6,000.00 COST TERM WAS A MERE ESTIMATE INSTEAD OF A CONTRACT."

{¶ 18} Generally, "a letter of intent is not in principle a contract, but rather merely a contract to continue to bargain in good faith." Mandalaywala v. Zaleski (1997),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bales v. Miami University, Ca2006-11-295 (11-13-2007)
2007 Ohio 6032 (Ohio Court of Appeals, 2007)
Gordon Constr. v. Peterbilt, Unpublished Decision (12-13-2004)
2004 Ohio 6662 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2003 Ohio 5111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gordon-cons-v-peterbilt-of-cincinnati-unpublished-decision-9-29-2003-ohioctapp-2003.