United Telephone Co. v. Williams Excavating, Inc.

707 N.E.2d 1188, 125 Ohio App. 3d 135
CourtOhio Court of Appeals
DecidedDecember 31, 1997
StatusPublished
Cited by13 cases

This text of 707 N.E.2d 1188 (United Telephone Co. v. Williams Excavating, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Telephone Co. v. Williams Excavating, Inc., 707 N.E.2d 1188, 125 Ohio App. 3d 135 (Ohio Ct. App. 1997).

Opinion

Shaw, Judge.

This opinion consolidates the two appeals by appellant Williams Excavating, Inc. (“Williams”) and appellant Southwest Licking Community Water and Sewer District (“Southwest”), which arise from three separate sewer construction projects that are the subject of various claims filed by the parties to the instant appellate action. In addition, the cross-appeal by United Telephone Company of Ohio (“United Telephone”) is now before this court.

Southwest is an Ohio public authority which has jurisdiction over three townships near Pataskala, Ohio, in Licking County. In 1990, Southwest entered into a written contract with Bischoff & Associates, Inc. (“Bischoff’) for it to provide professional engineering services in connection with the following three sanitary sewer improvement projects: Beechwood Trails Sanitary Sewer Improvements Contracts A and B (“Beechwood Trails”), Summit Station Sanitary Sewer Improvements Phase 2A (“Summit Station”), and U.S. Route 40 Environs Contracts A and B (“Environs”). The work included preparation of the project plans for the installation of sewer lines that would serve the three project areas. *139 These plans included certain underground utilities present within the construction sites.

In September 1992, Williams was awarded the Beechwood Trails construction project by competitive bidding in the amount of more than $3.6 million. Hence, Williams entered into a contract with Southwest for the project. Williams was also subsequently awarded the contracts for the Summit Station and Environs projects, the approximate amounts of $883,000 and $1.7 million, respectively.

The record shows that when Williams began to excavate the Beechwood Trails site in November 1992, Williams encountered underground telephone lines in the proposed sewer line path. No such lines were shown on the bid set of plans. Although telephone line locations were designated on the plans to the other two projects, the evidence shows that Williams also encountered underground lines not as marked on the plans during excavation for the proposed sewer lines. As a consequence, it was necessary for underground telephone lines in certain areas to be relocated, thereby delaying the projects. Williams was unable to complete its work as originally scheduled.

This case commenced when United Telephone brought suit against Williams alleging that Williams negligently cut its underground telephone fines during excavation activities in the Beechwood, Trails subdivision. Pertinent to this appeal, Williams’s second amended counterclaim asserts various negligence claims for violations of R.C. 153.64. Specifically, Williams alleged that United Telephone negligently mismarked or failed to mark the location of its underground telephone fines at all three construction sites in issue. Williams also alleged that United Telephone negligently failed to inform or misinformed Southwest as to the existence and location of its underground utility fines, resulting in plans and specifications which were false and misleading. Williams sought to recover damages due to project delays and for the extra materials and work performed.

Williams also filed a third-party complaint against Southwest. In its complaint, Williams alleged that Southwest negligently failed to mark or mismarked the existence and location of United Telephone’s underground fines on the bid plans. Williams also asserted unjust enrichment and breach of contract against Southwest. In its claims, Williams sought to recover damages resulting from project delays and for the extra materials and work required.

Southwest, in turn, filed a fourth-party complaint against Bischoff asserting a right to indemnity or contribution from Bischoff. Bischoff then filed a cross-claim against Williams seeking indemnification if it should be liable to Southwest.

In the subsequent jury trial, the trial court directed a verdict against Williams on its claims against Southwest relative to compliance with R.C. 153.64. Like *140 wise, the trial court directed a verdict against Southwest on all of its claims against Bischoff except for the indemnity claim. On Williams’s remaining claims against Southwest for breach of contract and unjust enrichment, which the trial court allowed to go to the jury, Williams was awarded $6,299 in breach-of-contract damages. With respect to United Telephone’s claims against Williams, the jury awarded United Telephone $18,814.30 in damages. As to the counterclaim against United Telephone, the jury found against Williams. By agreement of the parties, the trial court decided Southwest’s remaining claim for indemnification of legal fees and costs from Bischoff. In its entry dated January 15, 1997, the trial court denied Southwest’s claim under the parties’ contract.

Williams filed a motion for a new trial as to both the judgment in favor of Southwest and the judgment in favor of United Telephone. Williams’s motion was overruled by the trial court, and this appeal followed.

On appeal, Williams challenges the trial court’s dismissal of its claims against Southwest based on R.C. 153.64 and also the jury instructions on the remaining breach-of-contract claim against Southwest and on the negligence claims against United Telephone. United Telephone filed a cross-appeal challenging only the trial court’s denial of its motion for summary judgment as to Williams’s claims. In the appeal of Southwest, the only assignment of error raised concerns its claim for indemnification from Bischoff.

In this opinion, we will first discuss the merits of Williams’s assignments of error. Because the first, second, fifth, and sixth assignments of error challenge either the trial court’s dismissal of Williams’s claims against Southwest or the court’s corresponding instructions to the jury on this matter, we will treat them together. They provide as follows:

“Whether the lower court erred in reversing its prior decision that the Southwest Water and Sewer District has complied, as a matter of law, with its statutory duties imposed as to marking and location of underground utility facilities.
“Whether the lower court erred in ruling as it did concerning the obligations of the owner of a construction project as well as the obligations of the owner of a public underground utility facility on a construction project. 1
“Whether the lower court erred in instructing the jury that the owner had complied with the requirements of the Ohio statute as to markings of underground utility facilities.
*141 “Whether the lower court erred in failing to determine that a question of fact existed for the jury to determine as to whether utility lines were properly marked or relocated.”

Essentially, Williams argues that whether Southwest complied with the statutory obligations imposed by R.C. 153.64 is a question of fact and that Williams presented sufficient probative evidence to overcome a motion for a directed verdict and get the issue before the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yeager v. Carpenter
2010 Ohio 3675 (Ohio Court of Appeals, 2010)
Columbia Gas of Ohio, Inc. v. Columbus Asphalt Paving, Inc.
871 N.E.2d 636 (Franklin County Municipal Court, 2005)
Boggs v. Columbus Steel Castings, Unpublished Decision (9-13-2005)
2005 Ohio 4783 (Ohio Court of Appeals, 2005)
Estate of Schmidt
2001 ND 100 (North Dakota Supreme Court, 2001)
Triple Quest, Inc. v. Cleveland Gear Co.
2001 ND 101 (North Dakota Supreme Court, 2001)
Books a Million, Inc. v. H & N ENTERPRISES, INC.
140 F. Supp. 2d 846 (S.D. Ohio, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
707 N.E.2d 1188, 125 Ohio App. 3d 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-telephone-co-v-williams-excavating-inc-ohioctapp-1997.