Columbia Gas of Ohio v. Crestline Paving, Unpublished Decision (2-21-2003)

CourtOhio Court of Appeals
DecidedFebruary 21, 2003
DocketCourt of Appeals No. L-02-1093, Trial Court Nos. CVE-00-10549, CVE-01-02528.
StatusUnpublished

This text of Columbia Gas of Ohio v. Crestline Paving, Unpublished Decision (2-21-2003) (Columbia Gas of Ohio v. Crestline Paving, Unpublished Decision (2-21-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas of Ohio v. Crestline Paving, Unpublished Decision (2-21-2003), (Ohio Ct. App. 2003).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} This is an appeal from a partial summary judgment issued by the Toledo Municipal Court in favor of the owner of buried utility facilities.

{¶ 2} Appellee, Columbia Gas of Ohio, Inc., is a supplier of natural gas to commercial and residential customers through a network of underground pipes. Appellant, Crestline Paving Excavating Co., Inc., is a contractor engaged in excavation for various public improvements.

{¶ 3} On June 21, 2000, appellee sued appellant in the Toledo Municipal Court alleging that on 19 separate occasions between 1998 and 2000, appellant negligently damaged appellee's buried pipeline while excavating. Appellee sought damages in the amount of $8,444.44, the cost to repair the pipes.

{¶ 4} On February 7, 2001, appellant filed a separate suit against appellee, seeking $11,335.04 in "economic damages" from lost time allegedly sustained by it while appellee repaired pipes damaged, according to appellant, because appellee or its agent had mismarked the location of its underground pipes. The two cases were consolidated, following which appellee counterclaimed for an additional nine allegations of damaged buried pipe.

{¶ 5} Appellant did not dispute 12 of the original claims. On these, appellee was granted summary judgment. In the same judgment entry, the court found appellant's claims barred by application of Ohio's Economic Loss rule and also granted appellee summary judgment on appellant's complaint. Appellant subsequently consented to judgment on five of appellee's counterclaims. The remaining claims went to trial, resulting in a verdict for appellant on all but one of the claims and counterclaims still at issue.

{¶ 6} On appeal, appellant limits its challenge solely to the trial court's decision to bar its "economic loss" claims. Appellant sets forth the following single assignment of error:

{¶ 7} "The trial court erred in granting Columbia Gas Company's motion for summary judgment dismissing Crestline's complaint."

{¶ 8} Amicus curiae briefs have been filed by the Ohio Gas Association in support of appellee's position and the Ohio Contractor's Association in support of appellant's argument.

{¶ 9} On review, appellate courts employ the same standard for summary judgment as trial courts. Lorain Natl. Bank v. Saratoga Apts. (1989), 61 Ohio App.3d 127, 129. The motion may be granted only when it is demonstrated:

{¶ 10} "* * * (1) that there is no genuine issue as to any material fact; (2) that the moving party is entitled to judgment as a matter of law; and (3) that reasonable minds can come to but one conclusion, and that conclusion is adverse to the party against whom the motion for summary judgment is made, who is entitled to have the evidence construed most strongly in his favor." Harless v. Willis Day WarehousingCo. (1978), 54 Ohio St.2d 64, 67, Civ.R. 56(C).

{¶ 11} A "material" fact is one which would affect the outcome of the suit under the applicable substantive law. Russell v. InterimPersonnel, Inc.(1999), 135 Ohio App.3d 301, 304; Needham v. ProvidentBank (1996), 110 Ohio App.3d 817, 826, citing Anderson v. Liberty Lobby,Inc. (1986), 477 U.S. 242, 248.

{¶ 12} Both parties devote substantial argument as to whether appellee did, or should have, properly marked the location of its underground lines when properly notified by appellant of its intention to dig. This is a question that is only material if Ohio law allows recovery of "economic damages" under the circumstances before us.

{¶ 13} In this context, "economic damage" is an intangible economic loss that does not arise from tangible physical harm to persons or property. Floor Craft Floor Coverings, Inc. v. Parma Comm. Gen. Hosp. (1990), 54 Ohio St.3d 1, 3, citing Keeton, Prosser and Keeton on Torts (5 ed. 1984), 657, Section 92. Here, appellant alleges that because appellee was negligent in marking the location of its underground lines, appellant dug into those lines during its excavation. Since, for safety reasons, appellant was required to halt its work until appellee's crews repaired the damaged gas lines, appellant seeks compensation for its loss of productivity during this "down time."

{¶ 14} The economic loss rule provides that where there is no physical damage and loss is only pecuniary, such, "* * * purely economic interests are not entitled to protection against mere negligence, and so have been denied recovery." Chemtrol Adhesives v. American Mfrs. Ins.Co. (1989), 42 Ohio St.3d 40, 45, citing Prosser, Law of Torts (4 ed. 1971), 665, Section 101. This is the majority rule and the one to which Ohio adheres. Id.; Inglis v. Am. Motors Corp. (1965), 3 Ohio St.2d 132, paragraph one of the syllabus.

{¶ 15} The adoption of the rule represents a policy that limits the duty owed by one to another who has sustained only a loss of expectations. Absent some agreement between the parties, no duty exists with respect to purely economic harm. Chemtrol Adhesives, supra. The decision to draw the line here reflects a social judgment as to where the loss should fall. See Wallace v. Ohio Dept. of Commerce, 96 Ohio St.3d 266,274, 2002-Ohio-421024. "[A]bsen[t] privity of contract no cause of action exists in tort to recover economic damages * * *." FloorCraft, supra, syllabus.

{¶ 16} Appellant, in this matter, however, insists that the syllabus rule of Floor Craft was modified by Foster WheelerEnviresponse, Inc. v. Franklin Cty. (1997), 78 Ohio St.3d 353. Appellant maintains that in Enviresponse the court "held," at 365-366, that "[p]rivity, or its substitute" is sufficient to make purely economic damages recoverable in a negligence action. Moreover, according to appellant, that substitute exists, at least in public improvement projects, by virtue of R.C. 153.64.

{¶ 17} R.C. 153.64 requires, inter alia, that a contractor, who intends to commence excavation in an area where there may be underground utilities, notify the owners of such buried facilities at least two working days before the contractor begins to dig. The utility, then, is required to mark the location of the buried facilities before the dig begins. R.C. 153.65(C). Citing United Telephone v. Williams Excavating (1997), 125 Ohio App.3d 135

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Russell v. Interim Personnel, Inc.
733 N.E.2d 1186 (Ohio Court of Appeals, 1999)
Lorain National Bank v. Saratoga Apartments
572 N.E.2d 198 (Ohio Court of Appeals, 1989)
Marsh v. State Automobile Mutual Insurance
704 N.E.2d 280 (Ohio Court of Appeals, 1997)
Needham v. the Provident Bank
675 N.E.2d 514 (Ohio Court of Appeals, 1996)
United Telephone Co. v. Williams Excavating, Inc.
707 N.E.2d 1188 (Ohio Court of Appeals, 1997)
Inglis v. American Motors Corp.
209 N.E.2d 583 (Ohio Supreme Court, 1965)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
Haddon View Investment Co. v. Coopers
436 N.E.2d 212 (Ohio Supreme Court, 1982)
Wallace v. Ohio Dept. of Commerce
2002 Ohio 4210 (Ohio Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Columbia Gas of Ohio v. Crestline Paving, Unpublished Decision (2-21-2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-of-ohio-v-crestline-paving-unpublished-decision-2-21-2003-ohioctapp-2003.