Stanley Miller Constr. Co. v. School Facilities Comm.

2012 Ohio 3995
CourtOhio Court of Claims
DecidedMay 8, 2012
Docket2006-04351
StatusPublished

This text of 2012 Ohio 3995 (Stanley Miller Constr. Co. v. School Facilities Comm.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanley Miller Constr. Co. v. School Facilities Comm., 2012 Ohio 3995 (Ohio Super. Ct. 2012).

Opinion

[Cite as Stanley Miller Constr. Co. v. School Facilities Comm., 2012-Ohio-3995.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

STANLEY MILLER CONSTRUCTION CO.

Plaintiff

v.

OHIO SCHOOL FACILITIES COMMISSION, et al.

Defendants

Case No. 2006-04351

Judge Joseph T. Clark

DECISION

{¶ 1} Plaintiff, Stanley Miller Construction Company (Stanley Miller), brought this action against defendants, Ohio School Facilities Commission (OSFC) and State of Ohio, alleging breach of contract, negligence, and unjust enrichment. The case was tried to the court on the issues of liability and damages. {¶ 2} On March 1, 2010, this court entered judgment in favor of Stanley Miller in the total amount of $404,276.93 (Stanley Miller I). The court concluded that Stanley Miller was entitled to an equitable adjustment to the contract as follows: $273,925.85 for masonry; $8,658.35 for site work; $80,930.10 for roof trusses; $4,018.79 for sewer work; and $36,074.04 for interest earned. OSFC appealed the decision of this court and Stanley Miller filed a cross-appeal. On December 28, 2010, the court of appeals reversed the decision of this court and remanded the case for further proceedings. Stanley Miller Constr. Co. v. Ohio Sch. Facilities Comm., 10th Dist. Nos. 10AP-298, 10AP-299, 10AP-432, 10AP-433, 2010-Ohio-6397. (Stanley Miller II.) Case No. 2006-04351 -2- ENTRY

{¶ 3} On October 19, 2011, the parties were ordered to submit briefs upon remand and on January 6, 2012, all such briefs were submitted.1 The case is now before the court for a decision.2 {¶ 4} Stanley Miller entered into a contract with OSFC and Canton in January 2003, for the construction of what was to be the Lehman Middle School (Lehman project). During the construction phase, ownership of the proposed middle school was to be shared by OSFC (77 percent) and Canton (23 percent).3 Stanley Miller was a prime contractor on the project having been awarded a contract for numerous divisions of the work, including the division for masonry, which was the largest single component of the project. Jeffrey Tuckerman, OSFC’s project administrator, selected Ruhlin Construction (Ruhlin) as construction manager for the Lehman project. According to Tuckerman, Ruhlin was an extension of OSFC with respect to the management of the Lehman project. {¶ 5} Stanley Miller alleges that their work on the Lehman project was plagued by a myriad of costly inefficiencies that were caused by factors outside of its control. For example, Stanley Miller alleges that the combined effect of a hopelessly flawed construction schedule and the persistent meddling of Ruhlin resulted in delays and extra work. {¶ 6} On July 2, 2004, the scheduled project completion date, Stanley Miller submitted a one-page document to OSFC wherein Stanley Miller demanded that OSFC make an equitable adjustment to the contract price of more than $1.1 million in order to compensate Stanley Miller for unanticipated additional costs it had incurred on the project. The document was authored by Stanley Miller Vice President and Co-owner,

1 For good cause shown, Stanley Miller’s December 29, 2011 motion for an extension of time is GRANTED instanter and OSFC’s December 19, 2011 motion to strike is DENIED. 2 On September 1, 2006, Canton City School District (Canton) filed a petition seeking the removal of a case arising from the same transaction pending in Stark County Common Pleas Court. See Stanley Miller Constr. Co. v. OSFC, Ct. of Cl. No. 2006-05632-PR. Although the two cases were combined for trial, the court will issue a separate decision for each case. 3 OSFC and Canton will be referred to collectively as “OSFC” throughout this decision. Case No. 2006-04351 -2- ENTRY

Steve Miller, and became known at trial as the “one-page, $1.1 million claim.” (Plaintiff’s Exhibit 64.) The document reads as follows:

Est. Actual Difference Masonry costs including labor, material and equipment 2,274,738.00 2,751,130.77 (476,392.77) Cold Weather Protect 0.00 35,973.27 (35,973.27) Backfill Retaining Walls 17,400.00 51,707.84 (34,307.84) Concrete Costs 404,200.00 507,029.96 (102,829.96)

Clean Up Costs 23,000.00 56,583.29 (33,583.29) Temp. Roads, Repair Sub- grade 8,500.00 25,973.04 (17,473.04) Sewer Work 53,700.00 71,364.53 (17,664.53) Roof Trusses 221,600.00 291,974.39 (70,374.39) Total Losses (788,598.79)

Total OH & Profit (350,000.00) (1,138,598.79)

Current Contract 5,923,846.19 Costs as of this date (7/1/04) (6,660,747.80) (736,901.61) Estimated costs to complete, (Concrete bills yet to arrive and labor (51,697.18) to install curb and sidewalk along Broad St.)

(788,598.79)

{¶ 7} Although there were some subsequent communications between the parties regarding the claim and a brief meeting which occurred in July 2004, it is clear that no payment was made. Plaintiff now seeks to recover these additional costs under theories of breach of contract, negligence, and unjust enrichment. The third-party complaint states a claim for contractual indemnity. Case No. 2006-04351 -2- ENTRY

I. MASONRY CLAIM {¶ 8} In Stanley Miller I, the court awarded Stanley Miller the sum of $273,925.85 on its claim for damages arising out of bid package 4A pertaining to masonry.4 For this division of the work, Stanley Miller was to provide “all labor, equipment, material and supervision as required to complete exterior and interior masonry, including site work masonry, insulation, caulking and related work as shown on the Contract Documents.” This court determined that OSFC breached the contract by failing to provide Stanley Miller with a workable construction schedule and by wrongfully interfering with Stanley Miller’s means and methods. {¶ 9} In reversing the decision of this court, the court of appeals, in Stanley Miller II, stated: “[I]t is clear that the trial court in the instant matter considered the issue of whether Stanley Miller waived its right to an equitable adjustment under Article 8. Although the record contains evidence relating to the position that OSFC may have waived strict compliance with Article 8, it is clear that the trial court did not base its decision on this evidence. Instead, the trial court based its decision upon evidence

4 Stanley Miller was awarded a contract for multiple divisions of the work on the Lehman project, including the following: “1. Bid Package 2B - Site Work is generally all labor, equipment, material and supervision as required to complete: site development, removal of existing concrete and asphalt, earthwork, asphalt paving, concrete walks and curbs, sewer collection systems, bicycle parking racks, landscape work, and site concrete. “2. Bid Package 3B - Interior Concrete Slabs is generally all labor, equipment, material and supervision as required to complete: slab on grade and slab of deck. “3. Bid Package 4A - Masonry is generally all labor, equipment, material and supervision as required to complete: exterior and interior masonry, including site work masonry, insulation, caulking and related work as shown on the Contract Documents. “4. Bid Package 5B - Miscellaneous Metals is generally all work required to provide materials and complete installation of materials such as ladders, stairs, handrails, etc., which includes offloading, shakeout, raising, bolting, cutting, welding, alignment, shop priming, galvanizing and touch-up. The Prime Contractor responsible for this work shall be termed the Miscellaneous Steel Installation Contractor (MSIC). “5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tritonservices, Inc. v. Univ. of Cincinnati
2011 Ohio 7010 (Ohio Court of Claims, 2011)
National City Bank v. Rini
834 N.E.2d 836 (Ohio Court of Appeals, 2005)
Conti Corp. v. Ohio Department of Administrative Services
629 N.E.2d 1073 (Ohio Court of Appeals, 1993)
McMahon v. Shumaker, Loop & Kendrick, LLP
834 N.E.2d 894 (Ohio Court of Appeals, 2005)
Inglis v. American Motors Corp.
209 N.E.2d 583 (Ohio Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 3995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanley-miller-constr-co-v-school-facilities-comm-ohioctcl-2012.