RAM Construction Services of Cleveland, LLC v. Key Construction, Inc.

CourtDistrict Court, N.D. Ohio
DecidedAugust 26, 2022
Docket1:20-cv-02227
StatusUnknown

This text of RAM Construction Services of Cleveland, LLC v. Key Construction, Inc. (RAM Construction Services of Cleveland, LLC v. Key Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RAM Construction Services of Cleveland, LLC v. Key Construction, Inc., (N.D. Ohio 2022).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF OHIO EASTERN DIVISION

RAM CONSTRUCTION SERVICES ) Case No.1:20-cv-2227 OF CLEVELAND, LLC, ) ) Judge J. Philip Calabrese Plaintiff, ) ) v. ) ) KEY CONSTRUCTION, INC., ) ) Defendant. ) )

OPINION AND ORDER This diversity action arises from the renovation of what is known as the Verizon Cleveland Building in downtown Cleveland. Plaintiff RAM Construction Services of Cleveland, LLC contracted with the general contractor of the renovation, Defendant Key Construction, Inc. to restore the building’s masonry, among other things. RAM Construction finished the façade restoration under the subcontract and sued Key Construction for damages, seeking compensation for additional work that it completed. Defendant moves for summary judgment on all of Plaintiff’s claims, arguing that RAM Construction did not comply with subcontract before commencing the additional work. (ECF No. 16.) For the following reasons, the Court GRANTS Defendant’s motion for summary judgment. STATEMENT OF FACTS At this stage of the proceedings, the record establishes the following facts, which the Court construes in the light most favorable to Plaintiff as the non-movant. A. The Companies Defendant Key Construction, Inc. is a commercial contractor offering facility, pre-construction, and construction services on various projects throughout the United

States. (ECF No. 1-1, ¶ 9, PageID #8; ECF No. 4, ¶ 9, PageID #149.) Plaintiff RAM Construction Services of Cleveland, LLC is a construction company providing waterproofing and restoration services on construction projects throughout the Midwest. (ECF No. 21, PageID #355.) B. The Project Verizon Building Purchasing, LLC owns the seven-story Verizon Cleveland Building in downtown Cleveland. (ECF No. 1-1, ¶ 10, PageID #9; ECF No. 4, ¶ 10, PageID #149.) In 2018, Verizon Building sought to restore and reseal the building’s

façade. (ECF No. 1-1, ¶ 13, PageID #9; ECF No. 4, ¶ 13, PageID #149.) Verizon Building hired Key Construction to act as the general contractor for the project. (ECF No. 1-1, ¶ 10, PageID #9; ECF No. 4, ¶ 10, PageID #149.) Key Construction subsequently hired RAM Construction as a subcontractor for the building’s masonry restoration and tuck-pointing work. (ECF No. 28-2, PageID #526–30.) C. The Subcontract On November 2, 2018, RAM Construction and Key Construction entered into

a subcontract worth $731,934.00. (ECF No. 1-1, ¶¶ 14 & 17, PageID #9; ECF No. 4, ¶¶ 14 & 17, PageID #149.) This price was estimated based on the quantities for labor and materials outlined in the plan and specifications prepared by the project’s architect, EXP (ECF No. 1-1, ¶¶ 14 & 16, PageID #9; ECF No. 4, ¶¶ 14 & 16, PageID #149) and RAM Construction’s per unit price bid (ECF No. 21, PageID #364–65; see also ECF No. 29-1, PageID #649–51 (detailing bid proposal)). The subcontract specifically provides for potential changes to the time or price

for RAM Construction’s work on the project. (ECF No. 1-1, ¶ 20 PageID #9–10; ECF No. 4, ¶ 20, PageID #149; see also ECF No. 28-2, PageID #533.) Section 8 of the subcontract states, in relevant part: When Contractor [Key Construction] orders in writing, Subcontractor [RAM Construction] shall make any and all changes in the Work which are within the general scope of this Subcontract. Adjustments in the Subcontract price or Subcontract time, if any, resulting from such changes shall be set forth in a written change order. No such adjustments shall be made for any changes performed by Subcontractor that have not been ordered in writing by Contractor. (ECF No. 28-2, PageID #533.) Additionally, the subcontract attaches an exhibit that contains special provisions. (ECF No. 28-2, PageID #541.) This exhibit provides that, where a conflict exists between the special provisions and any other document of the subcontract, the more stringent will apply. (Id., § 33, PageID #545.) Sections 33 and 34 of the special provisions detail requirements for change orders and construction change directives. (Id., PageID #545–46.) Section 33 states, in relevant part: Only written change orders issued by Key and signed by both parties will be considered for payment. No change orders will be considered for payment unless approved by Key’s Project Manager prior to work being performed. The authorized Project Manager for Key on this project is Will Daniel. Field authorized changes will not be considered an authorized change order until approved by Key’s project manager. (Id., PageID #545.) Also, Section 34 explains that: Construction Change Directives may from time to time be issued in the absence of a total agreement on the terms of a subcontract change order, or in the absence of total approval of the subcontractor requested change by the Owner & Architect. If a Construction Change Directive is issued, the changed work will be required to progress in a manor not to [a]ffect the project schedule while the terms of the change order are negotiated and resolved. (Id., PageID #546.) Further, the subcontract details how RAM Construction may notify Key Construction of a claim for an increase in the subcontract price or change in time. (Id., § 9, PageID #534.) Section 9 of the subcontract provides that RAM Construction must give Key Construction “advance written notice of any claim for an increase in the Subcontract price and/or the Subcontract time within ten (10) days after the occurrence giving rise to the claim or within ten (10) days after Subcontractor first recognizes the condition giving rise to the claim, whichever is earlier.” (Id.) Additionally, Section 9 disallows any adjustment for work performed without a timely, written claim, which Key Construction authorizes through a written change order. (Id.) “[F]ailure or delay by Contractor [Key Construction] to require performance of any provision of this Subcontract shall not be deemed a waiver of its right to enforce such provision.” (Id., § 21, PageID #537.) Finally, the subcontract contains a lien waiver in Section 17. (Id., PageID #536.) This section provides that, “[n]otwithstanding any other provisions herein and, to the fullest extent permitted by law, Subcontractor irrevocably waives any right to file a mechanic’s lien or materialman’s lien on the Project.” (Id.) D. Work Under the Subcontract Initially, the work proceeded as planned, and RAM Construction worked on one elevation at a time. As each elevation neared its end, Chris Schrank, EXP’s

engineer and the person who helped oversee the project’s progress, reviewed the work and issued punch lists to RAM Construction, which listed any deficiencies in the completed work that need to be corrected before moving on to the next elevation. (ECF No. 27-1, PageID #508–10.) Occasionally, RAM Construction’s Project Manager, Michael Smith, submitted change requests for additional quantities or the scope of work. For example, RAM Construction submitted a change order for additional quantities to fix part of the

building that posed a hazard of falling concrete. (ECF No. 27-1, PageID #499.) In that change request, RAM Construction stated that Chris Schrank (EXP’s engineer) directed RAM Construction to repair the hazard. (ECF No. 28-3, PageID #548.) Will Daniel, Key Construction’s project manager, then submitted this request to Verizon Building for approval and subsequently issued a change order. (ECF No. 27-1, PageID #500.) Key Construction issued a total of five change orders, each of which

was issued by February 2019, after the work they had covered had already started or finished. (ECF No. 21, PageID #361.) E. The Disputed Work In March 2019, Smith left his position at RAM Construction, and James Nystrand, who previously directed façade restorations, took over as the project lead. (ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Alexander v. CareSource
576 F.3d 551 (Sixth Circuit, 2009)
Reed v. FREEBIRD FILM PRODUCTIONS, INC.
664 F. Supp. 2d 840 (N.D. Ohio, 2009)
A & J Plumbing, Inc. v. Huntington Natl. Bank
2014 Ohio 5707 (Ohio Court of Appeals, 2014)
Micrel, Inc. v. TRW, Inc.
486 F.3d 866 (Sixth Circuit, 2007)
City of Cincinnati v. Cincinnati Reds
483 N.E.2d 1181 (Ohio Court of Appeals, 1984)
Langford v. Sloan
833 N.E.2d 331 (Ohio Court of Appeals, 2005)
Aultman Hospital Ass'n v. Community Mutual Insurance
544 N.E.2d 920 (Ohio Supreme Court, 1989)
Corporex Development & Construction Management, Inc. v. Shook, Inc.
106 Ohio St. 3d 412 (Ohio Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
RAM Construction Services of Cleveland, LLC v. Key Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ram-construction-services-of-cleveland-llc-v-key-construction-inc-ohnd-2022.