Champion Contracting v. Valley City Post, Unpublished Decision (6-30-2004)

2004 Ohio 3406
CourtOhio Court of Appeals
DecidedJune 30, 2004
DocketC.A. No. 03CA0092-M.
StatusUnpublished
Cited by14 cases

This text of 2004 Ohio 3406 (Champion Contracting v. Valley City Post, Unpublished Decision (6-30-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Champion Contracting v. Valley City Post, Unpublished Decision (6-30-2004), 2004 Ohio 3406 (Ohio Ct. App. 2004).

Opinions

decision and journal entry
{¶ 1} Plaintiff-Appellant Champion Contracting Construction Co., Inc. has appealed from a decision of the Medina County Court of Common Pleas that entered judgment in its favor in the amount of $2,800, but denied its claim for unjust enrichment. This Court affirms.

I
{¶ 2} On August 11, 2003, Plaintiff-Appellant Champion Contracting Construction Co., Inc. ("Champion") filed a complaint against Defendant-Appellee Valley City Post No. 5563, Veterans of Foreign Wars of the United States ("VFW"). In the complaint, Champion contended that the VFW was indebted to it in the amount of $21,064.15 for services Champion rendered to the VFW under a construction contract. Champion was hired by the VFW to construct a new addition to an already existing building. Champion also requested the trial court to find that it held a valid lien against certain property owed by the VFW; said lien was created to secure payment of the VFW's unpaid debt.

{¶ 3} The VFW filed an answer and counterclaim on March 2, 2001. In the counterclaim, the VFW maintained that Champion breached the construction contract by failing to complete the construction in a timely manner and that said construction was still uncompleted at the time the complaint was filed. As a result of Champion's failure to complete the construction project, the VFW claimed that it was unable to rent the new addition as a party center and was damaged in the amount of $7,700 in lost rentals. The VFW further maintained that Champion failed to construct the building in accordance with the contract drawings and documents. As a result, the VFW claimed that it had to repair and replace certain items, at a cost of $16,850.90. The VFW requested damages totaling $24,550.90. Champion replied to the VFW's counterclaim. The matter was set for a hearing before a magistrate.

{¶ 4} After a hearing, the magistrate found that the VFW owed Champion $8,039, which was $13,025.15 less than the amount Champion requested in its complaint. The magistrate concluded that the VFW was not liable to Champion for the payment of additional expenses that were a result of oral modifications to the contract. As to Champion's claim for unjust enrichment, the magistrate held that Champion could not recover under this theory because the subject matter of its claim was covered by an express contract that existed between the parties.

{¶ 5} The magistrate found merit in the VFW's cross-claim. Although it rejected the VFW's claim for the value of lost rentals, the magistrate concluded that Champion owed the VFW $5,239 for unfinished work which Champion was obligated to complete pursuant to the terms of the contract. After set-off of the two amounts, Champion was granted judgment against the VFW in the amount of $2,800.

{¶ 6} Champion filed objections to the magistrate's decision. The VFW filed a response to Champion's objections. The trial court overruled Champion's objections and adopted the magistrate's decision. The trial court held that the VFW owed Champion $8,039, which was the unpaid balance under the written contract. The trial court further held that Champion owed the VFW $5,239 for unfinished work which Champion had an obligation to complete under the contract. After set-off of the two amounts, the trial court granted judgment against the VFW in the amount of $2,800.

{¶ 7} Champion has timely appealed, asserting three assignments of error.

II
Assignment of Error Number One
"The judgment entry appealed from is not a final appealable order in failing to adjudicate all issues within the findings of the court."

{¶ 8} In Champion's first assignment of error, it has argued that the order from which it has appealed is not a final, appealable order. This Court disagrees.

{¶ 9} Pursuant to Civ.R. 53, a court may adopt a magistrate's decision and enter judgment without waiting for objections to be filed by the parties. Civ.R. 53(E)(4)(c). If objections are filed, the court must then rule on the objections and either "adopt, reject, or modify the magistrate's decision, hear additional evidence, recommit the matter to the magistrate with instructions, or hear the matter." Civ.R. 53(E)(4)(b). If no objections are filed, the court may adopt the magistrate's decision, unless there is an error of law or other defect on the face of the magistrate's decision. Civ.R. 53(E)(4)(a). However, regardless of which option is chosen, "the trial court entry reflecting action on the magistrate's decision must be a separate and distinct instrument from the magistrate's decision and must grant relief on the issues originally submitted to the trial court." In re Dortch (1999),135 Ohio App.3d 430, 432; see, also, Harkai v. Scherba Indus. (2000),136 Ohio App.3d 211, 218. The Court in Dortch further explained that "[i]n granting such relief, the trial court simply `must sufficiently address those issues so that the parties may know of their rights and obligations by referring only to that document known as the judgment entry.'" Dortch, 135 Ohio App.3d at 432, quoting In re Zakov (1995),107 Ohio App.3d 716, 717.

{¶ 10} In the case sub judice, Champion has argued that the order from which it has appealed does not comply with Dortch, Zakov or Daly v.Martin (May 14, 1997), 9th Dist. No. 2599-M, at 3-4, overruled byHarkai, 136 Ohio App.3d 211. Champion has contended that the order does not "[r]esolve amounts claimed by Champion under the legal theory of unjust enrichment and elements of the VFW's off set" because "no findings regarding unjust enrichment and elements of the VFW's off sets are made in" the order. Specifically, Champion has maintained that "[n]o final order has been made regarding Champion's work completed on the premises, which was done under oral request at a time and material value of $10,721.11 work completed and remaining on the VFW real estate." This Court rejects Champion's argument because Dortch, Daly, and Zakov are inapposite to the instant matter.

{¶ 11} In Dortch, an objecting party filed objections to the magistrate's decision pursuant to Civ.R. 53(E). The trial court issued a judgment entry in which the court overruled the objections, described the magistrate's orders, and stated: "The Magistrate's Decision is approved and becomes an order of this Court." Dortch, 135 Ohio App.3d at 431. Relying on our previous holding in Daly, the Dortch court held that "[t]o constitute a final appealable order, the trial court entry reflecting action on the magistrate's decision must be a separate and distinct instrument from the magistrate's decision and must grant relief on the issues originally submitted to the trial court." Id. at 432. Although the judgment entry from which the appellant appealed described the magistrate's orders, the Dortch court held that the order was not a final, appealable order because "the entry fail[ed] to set forth the orders of the court." Id. at 432.

{¶ 12} Similarly, in Zakov

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rupp v. Premier Health Partners
2025 Ohio 985 (Ohio Court of Appeals, 2025)
Bunta v. Superior VacuPress, L.L.C.
2022 Ohio 4363 (Ohio Supreme Court, 2022)
Carter v. Univ. Park Dev. Corp.
2022 Ohio 3462 (Ohio Court of Appeals, 2022)
Spalsbury v. Gill Construction Co., Inc.
2018 Ohio 2616 (Ohio Court of Appeals, 2018)
In re A.T.
2017 Ohio 5821 (Ohio Court of Appeals, 2017)
Americana Invest. Co. v. Natl. Contracting & Fixturing, L.L.C.
2016 Ohio 7067 (Ohio Court of Appeals, 2016)
Keller & Kehoe, L.L.P. v. Smart Media of Delaware, Inc.
2016 Ohio 5409 (Ohio Court of Appeals, 2016)
J. Bowers Constr. Co., Inc. v. Gilbert
2014 Ohio 3576 (Ohio Court of Appeals, 2014)
Wochna v. Mancino, 07ca0059-M (3-10-2008)
2008 Ohio 996 (Ohio Court of Appeals, 2008)
Henley v. Henley, Unpublished Decision (5-25-2005)
2005 Ohio 2568 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 3406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/champion-contracting-v-valley-city-post-unpublished-decision-6-30-2004-ohioctapp-2004.