J. Bowers Constr. Co., Inc. v. Gilbert

2014 Ohio 3576
CourtOhio Court of Appeals
DecidedAugust 20, 2014
Docket27044
StatusPublished
Cited by13 cases

This text of 2014 Ohio 3576 (J. Bowers Constr. Co., Inc. v. Gilbert) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Bowers Constr. Co., Inc. v. Gilbert, 2014 Ohio 3576 (Ohio Ct. App. 2014).

Opinion

[Cite as J. Bowers Constr. Co., Inc. v. Gilbert, 2014-Ohio-3576.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

J. BOWERS CONSTRUCTION CO., INC. C.A. No. 27044

Appellee

v. APPEAL FROM JUDGMENT ENTERED IN THE EDWARD L. GILBERT, et al. COURT OF COMMON PLEAS COUNTY OF SUMMIT, OHIO Appellants CASE No. CV 2011 08 4841

DECISION AND JOURNAL ENTRY

Dated: August 20, 2014

WHITMORE, Judge.

{¶1} Defendant-Appellants, Edward and Delphenia Gilbert (collectively, “the

Gilberts”), appeal from the judgment of the Summit County Court of Common Pleas. This Court

affirms.

I

{¶2} In August 2009, the Gilberts received a call from their home security company

notifying them that an alarm had been activated. When the Gilberts arrived home, the police and

fire department were already on scene. The Gilberts discovered their home was flooded from a

burst water pipe in an upstairs room. Someone from the fire department recommended J.

Bowers Construction Company, Inc. (“Bowers”) to do emergency repairs.

{¶3} Bowers was contacted and sent an agent to the Gilberts’ that same day. Edward

Gilbert signed an authorization form for the emergency repairs and Bowers began work

immediately. The Gilberts had a home insurance policy with Travelers Insurance, and Travelers 2

provided a written estimate for the repairs. At some point, it was determined that Bowers would

also do the necessary repairs to the home after the emergency repairs were completed. However,

the Gilberts did not sign any additional documentation.

{¶4} Over the next year-and-a-half, Bowers worked with the Gilberts and Travelers to

complete the repairs. During this process, the Gilberts chose not to repair certain things that

were covered by their insurance policy and to upgrade things that were not covered. While the

repairs were being made, Travelers issued partial payments to the Gilberts, and the Gilberts made

$65,000 in payments to Bowers. In February 2011, Travelers issued a final estimate totaling

$132,451.98. Bowers and Edward Gilbert met on March 2, 2011, and reviewed various credits

and charges for upgrades. Gilbert tendered a check for $6,624.89, and, it appears, both parties

believed the remaining balance of $67,451.98 would be paid by Travelers.

{¶5} In August 2011, having received no additional payments, Bowers filed a claim for

breach of contract and quantum meruit. The Gilberts counterclaimed alleging fraud, damage to

the property by the construction workers, and the use of substandard materials. After a bench

trial, the court entered a judgment in favor of Bowers for $67,451.98. The Gilberts now appeal

and raise seven assignments of error for our review.

II

Assignment of Error Number One

THE TRIAL COURT ERRED WHEN IT RULED THAT J. BOWERS WAS ENTITLED TO JUDGMENT BASED ON QUANTUM MERUIT WHEN IT ALREADY DETERMINED THAT THERE WAS AN EXPRESS CONTRACT.

{¶6} In their first assignment of error, the Gilberts argue that the court erred by

awarding judgment in favor of Bowers under the theory of quantum meruit because the court

found that there was an express contract between the parties. 3

{¶7} The Gilberts’ first assignment of error raises a question of law, which this Court

reviews de novo. See Fuline v. Green, 9th Dist. Summit No. 26586, 2013-Ohio-2171, ¶ 6. In

conducting a de novo review, an appellate court does not give deference to the trial court’s

determination. Akron v. Frazier, 142 Ohio App.3d 718, 721 (9th Dist.2001).

{¶8} “A contract is generally defined as a promise, or a set of promises, actionable

upon breach. Essential elements of a contract include an offer, acceptance, contractual capacity,

consideration (the bargained for legal benefit and/or detriment), a manifestation of mutual assent

and legality of object and of consideration.” Kostelnik v. Helper, 96 Ohio St.3d 1, 2002-Ohio-

2985, ¶ 16, quoting Perlmuter Printing Co. v. Strome, Inc., 436 F.Supp. 409, 414 (N.D.Ohio

1976). There is no valid contract where the parties have not had a meeting of the minds as to the

essential terms. See Minster Farmers Coop. Exchange Co., Inc. v. Meyer, 117 Ohio St.3d 459,

2008-Ohio-1259, ¶ 28.

{¶9} In the absence of a valid contract, a party may still recover under a quasi-contract

theory. “Recovery in quasi-contract prevents the defendant from unjustly enriching himself at

the expense of the plaintiff.” Bokar v. Lax, 9th Dist. Medina No. 2630-M, 1997 WL 557333, *2

(Sept. 3, 1997), citing Hughes v. Oberholtzer, 162 Ohio St.3d 330, 335 (1954). An example of a

quasi-contract claim is quantum meruit. See Hammontree & Associates, Ltd. v. Stephens, 9th

Dist. Wayne No. 2222, 1987 WL 15106, *2 (July 29, 1987).

{¶10} Quantum meruit is an equitable remedy giving “rise to obligations imposed by

law, irrespective of the intentions of the parties, in order to prevent an injustice when one party

retains a benefit from another’s labors.” (Internal quotations and citations omitted.) In re

Suchodolski, 9th Dist. Lorain No. 10CA009833, 2011-Ohio-6333, ¶ 8, quoting In re Estate of

Kirkland, 175 Ohio App.3d 73, 2008-Ohio-421, ¶ 23 (2d Dist.). “Quantum meruit is generally 4

awarded when one party confers some benefit upon another without receiving just compensation

for the reasonable value of services rendered.” (Emphasis sic.) Aultman Hosp. Assn. v.

Community Mut. Ins. Co., 46 Ohio St.3d 51, 55 (1989). To prevail on a claim of quantum

meruit, a plaintiff is required to show “(1) a benefit has been conferred by [the] plaintiff upon

[the] defendant; (2) the defendant had knowledge of the benefit; and (3) the defendant retained

the benefit under circumstances where it would be unjust to do so without payment.” In re

Suchodolski at ¶ 8, quoting Bldg. Industry Consultants, Inc. v. 3M Parkway, Inc., 182 Ohio

App.3d 39, 2009-Ohio-1910, ¶ 16 (9th Dist.).

{¶11} Because a quasi-contract claim only exists when there is no valid contract, “a

party cannot claim that both an express contract and a quasi-contract exist over the same subject

matter.” (Emphasis omitted.) Champion Contracting Const. Co., Inc. v. Valley City Post No.

5563, 9th Dist. Medina No. 03CA0092-M, 2004-Ohio-3406, ¶ 25. “While it is true that a party

may not recover for the same services under both a contractual claim and a claim for quantum

meruit, a party is not barred from seeking alternative theories and recovering under a quantum

meruit theory if his contractual claim fails.” Bldg. Industry Consultants, Inc. at ¶ 17.

{¶12} On September 12, 2009, the Gilberts received a call from their security company

that an alarm had been activated at their home. When the Gilberts arrived at their house, the

police and fire department were already there. The Gilberts opened the door and discovered that

their house was flooded from a burst water pipe. According to Edward Gilbert’s testimony,

someone from the fire department recommended Bowers to come out and perform emergency

repairs. There is some dispute about who actually contacted Bowers. In any event, it is

undisputed that a representative of Bowers went to the Gilberts’ home that same day, and 5

Edward Gilbert signed a document entitled “Access & Authorization for Emergency &

Temporary Repairs.” This authorization form provided:

I hereby give access and authorization to J. Bowers Construction Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Domaradzki v. Dennis
2025 Ohio 5692 (Ohio Court of Appeals, 2025)
ParkPlay Solutions, L.L.C. v. Avon Lake
2023 Ohio 3103 (Ohio Court of Appeals, 2023)
Sycamore Twp. v. Carr
2022 Ohio 1337 (Ohio Court of Appeals, 2022)
Frye v. Am. Honda Motor Co., Inc.
2022 Ohio 878 (Ohio Court of Appeals, 2022)
Eltibi v. Kocsis
2021 Ohio 2911 (Ohio Court of Appeals, 2021)
Clark v. Corwin
2018 Ohio 1169 (Ohio Court of Appeals, 2018)
Keller & Kehoe, L.L.P. v. Smart Media of Delaware, Inc.
2016 Ohio 5409 (Ohio Court of Appeals, 2016)
Home S. & L. Co. of Youngstown v. Evergreen Land Dev.
2016 Ohio 1248 (Ohio Court of Appeals, 2016)
Price v. KNL Custom Homes, Inc.
2015 Ohio 436 (Ohio Court of Appeals, 2015)
Patterson v. Godale
2014 Ohio 5615 (Ohio Court of Appeals, 2014)
Sliwinski v. St. Edwards
2014 Ohio 4655 (Ohio Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 3576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-bowers-constr-co-inc-v-gilbert-ohioctapp-2014.