J. Bowers Constr. Co., Inc. v. Gilbert

2014 Ohio 3576
Ohio Court of Appeals·Decided August 20, 2014·No. 27044·Published·Cited by 13 cases

Opinion

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

J. BOWERS CONSTRUCTION CO., INC. C.A. No. 27044 Appellee

v. APPEAL FROM JUDGMENT ENTERED IN THE

EDWARD L. GILBERT, et al. COURT OF COMMON PLEAS COUNTY OF SUMMIT, OHIO

Appellants CASE No. CV 2011 08 4841

DECISION AND JOURNAL ENTRY Dated: August 20, 2014

WHITMORE, Judge.

{¶1} Defendant-Appellants, Edward and Delphenia Gilbert (collectively, “the Gilberts”), appeal from the judgment of the Summit County Court of Common Pleas. This Court affirms.

I

{¶2} In August 2009, the Gilberts received a call from their home security company notifying them that an alarm had been activated. When the Gilberts arrived home, the police and fire department were already on scene. The Gilberts discovered their home was flooded from a burst water pipe in an upstairs room. Someone from the fire department recommended J. Bowers Construction Company, Inc. (“Bowers”) to do emergency repairs.

{¶3} Bowers was contacted and sent an agent to the Gilberts’ that same day. Edward Gilbert signed an authorization form for the emergency repairs and Bowers began work immediately. The Gilberts had a home insurance policy with Travelers Insurance, and Travelers

provided a written estimate for the repairs. At some point, it was determined that Bowers would also do the necessary repairs to the home after the emergency repairs were completed. However, the Gilberts did not sign any additional documentation.

{¶4} Over the next year-and-a-half, Bowers worked with the Gilberts and Travelers to complete the repairs. During this process, the Gilberts chose not to repair certain things that were covered by their insurance policy and to upgrade things that were not covered. While the repairs were being made, Travelers issued partial payments to the Gilberts, and the Gilberts made $65,000 in payments to Bowers. In February 2011, Travelers issued a final estimate totaling $132,451.98. Bowers and Edward Gilbert met on March 2, 2011, and reviewed various credits and charges for upgrades. Gilbert tendered a check for $6,624.89, and, it appears, both parties believed the remaining balance of $67,451.98 would be paid by Travelers.

{¶5} In August 2011, having received no additional payments, Bowers filed a claim for breach of contract and quantum meruit. The Gilberts counterclaimed alleging fraud, damage to the property by the construction workers, and the use of substandard materials. After a bench trial, the court entered a judgment in favor of Bowers for $67,451.98. The Gilberts now appeal and raise seven assignments of error for our review.

II

Assignment of Error Number One

THE TRIAL COURT ERRED WHEN IT RULED THAT J. BOWERS WAS ENTITLED TO JUDGMENT BASED ON QUANTUM MERUIT WHEN IT ALREADY DETERMINED THAT THERE WAS AN EXPRESS CONTRACT.

{¶6} In their first assignment of error, the Gilberts argue that the court erred by awarding judgment in favor of Bowers under the theory of quantum meruit because the court found that there was an express contract between the parties.

{¶7} The Gilberts’ first assignment of error raises a question of law, which this Court reviews de novo. See Fuline v. Green, 9th Dist. Summit No. 26586, 2013-Ohio-2171, ¶ 6. In conducting a de novo review, an appellate court does not give deference to the trial court’s determination. Akron v. Frazier, 142 Ohio App.3d 718, 721 (9th Dist.2001).

{¶8} “A contract is generally defined as a promise, or a set of promises, actionable upon breach. Essential elements of a contract include an offer, acceptance, contractual capacity, consideration (the bargained for legal benefit and/or detriment), a manifestation of mutual assent and legality of object and of consideration.” Kostelnik v. Helper, 96 Ohio St.3d 1, 2002-Ohio- 2985, ¶ 16, quoting Perlmuter Printing Co. v. Strome, Inc., 436 F.Supp. 409, 414 (N.D.Ohio 1976). There is no valid contract where the parties have not had a meeting of the minds as to the essential terms. See Minster Farmers Coop. Exchange Co., Inc. v. Meyer, 117 Ohio St.3d 459, 2008-Ohio-1259, ¶ 28.

{¶9} In the absence of a valid contract, a party may still recover under a quasi-contract theory. “Recovery in quasi-contract prevents the defendant from unjustly enriching himself at the expense of the plaintiff.” Bokar v. Lax, 9th Dist. Medina No. 2630-M, 1997 WL 557333, *2 (Sept. 3, 1997), citing Hughes v. Oberholtzer, 162 Ohio St.3d 330, 335 (1954). An example of a quasi-contract claim is quantum meruit. See Hammontree & Associates, Ltd. v. Stephens, 9th Dist. Wayne No. 2222, 1987 WL 15106, *2 (July 29, 1987).

{¶10} Quantum meruit is an equitable remedy giving “rise to obligations imposed by law, irrespective of the intentions of the parties, in order to prevent an injustice when one party retains a benefit from another’s labors.” (Internal quotations and citations omitted.) In re Suchodolski, 9th Dist. Lorain No. 10CA009833, 2011-Ohio-6333, ¶ 8, quoting In re Estate of Kirkland, 175 Ohio App.3d 73, 2008-Ohio-421, ¶ 23 (2d Dist.). “Quantum meruit is generally

awarded when one party confers some benefit upon another without receiving just compensation for the reasonable value of services rendered.” (Emphasis sic.) Aultman Hosp. Assn. v. Community Mut. Ins. Co., 46 Ohio St.3d 51, 55 (1989). To prevail on a claim of quantum meruit, a plaintiff is required to show “(1) a benefit has been conferred by [the] plaintiff upon [the] defendant; (2) the defendant had knowledge of the benefit; and (3) the defendant retained the benefit under circumstances where it would be unjust to do so without payment.” In re Suchodolski at ¶ 8, quoting Bldg. Industry Consultants, Inc. v. 3M Parkway, Inc., 182 Ohio App.3d 39, 2009-Ohio-1910, ¶ 16 (9th Dist.).

{¶11} Because a quasi-contract claim only exists when there is no valid contract, “a party cannot claim that both an express contract and a quasi-contract exist over the same subject matter.” (Emphasis omitted.) Champion Contracting Const. Co., Inc. v. Valley City Post No. 5563, 9th Dist. Medina No. 03CA0092-M, 2004-Ohio-3406, ¶ 25. “While it is true that a party may not recover for the same services under both a contractual claim and a claim for quantum meruit, a party is not barred from seeking alternative theories and recovering under a quantum meruit theory if his contractual claim fails.” Bldg. Industry Consultants, Inc. at ¶ 17.

{¶12} On September 12, 2009, the Gilberts received a call from their security company that an alarm had been activated at their home. When the Gilberts arrived at their house, the police and fire department were already there. The Gilberts opened the door and discovered that their house was flooded from a burst water pipe. According to Edward Gilbert’s testimony, someone from the fire department recommended Bowers to come out and perform emergency repairs. There is some dispute about who actually contacted Bowers. In any event, it is undisputed that a representative of Bowers went to the Gilberts’ home that same day, and

Edward Gilbert signed a document entitled “Access & Authorization for Emergency & Temporary Repairs.” This authorization form provided:

I hereby give access and authorization to J. Bowers Construction Inc. for the purpose of making necessary temporary emergency repairs to the above address as a result of 9-12-09, date of loss 9-12-09. It is my understanding that the services performed by J. Bowers Construction Inc. will be limited to those which are authorized by owner/agent or by my/our insurance company, unless other arrangements for payment are agreed upon in writing in advance. All charges will be based on time and material. All labor costs are charged portal to portal.

Free access — add to your briefcase to read the full text and ask questions with AI

J. Bowers Constr. Co., Inc. v. Gilbert, 2014 Ohio 3576 (Ohio Ct. App. 2014).

2014 Ohio 3576 (J. Bowers Constr. Co., Inc. v. Gilbert) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Domaradzki v. Dennis
2025 Ohio 5692 (Ohio Court of Appeals, 2025)
ParkPlay Solutions, L.L.C. v. Avon Lake
2023 Ohio 3103 (Ohio Court of Appeals, 2023)
Sycamore Twp. v. Carr
2022 Ohio 1337 (Ohio Court of Appeals, 2022)
Frye v. Am. Honda Motor Co., Inc.
2022 Ohio 878 (Ohio Court of Appeals, 2022)
Eltibi v. Kocsis
2021 Ohio 2911 (Ohio Court of Appeals, 2021)
Clark v. Corwin
2018 Ohio 1169 (Ohio Court of Appeals, 2018)
Keller & Kehoe, L.L.P. v. Smart Media of Delaware, Inc.
2016 Ohio 5409 (Ohio Court of Appeals, 2016)
Home S. & L. Co. of Youngstown v. Evergreen Land Dev.
2016 Ohio 1248 (Ohio Court of Appeals, 2016)
Price v. KNL Custom Homes, Inc.
2015 Ohio 436 (Ohio Court of Appeals, 2015)
Patterson v. Godale
2014 Ohio 5615 (Ohio Court of Appeals, 2014)
Sliwinski v. St. Edwards
2014 Ohio 4655 (Ohio Court of Appeals, 2014)