Price v. KNL Custom Homes, Inc.

2015 Ohio 436
CourtOhio Court of Appeals
DecidedFebruary 6, 2015
Docket26968
StatusPublished
Cited by16 cases

This text of 2015 Ohio 436 (Price v. KNL Custom Homes, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Price v. KNL Custom Homes, Inc., 2015 Ohio 436 (Ohio Ct. App. 2015).

Opinion

[Cite as Price v. KNL Custom Homes, Inc., 2015-Ohio-436.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

RON L. PRICE, et al. C.A. No. 26968

Appellee/Cross-Appellants

v. APPEAL FROM JUDGMENT ENTERED IN THE KNL CUSTOM HOMES INC., et al. COURT OF COMMON PLEAS COUNTY OF SUMMIT, OHIO Appellants/Cross-Appellees CASE No. CV 2009-02-1261

DECISION AND JOURNAL ENTRY

Dated: February 6, 2015

MOORE, Judge.

{¶1} Defendant-Appellant/Cross-Appellee, KNL Custom Homes, Inc. (“KNL”),

appeals from the March 16, 2012 verdict, and the December 31, 2012, and May 17, 2013

judgment entries of the Summit County Court of Common Pleas. Plaintiffs/Appellees, Ron L.

Price, et al. (“the Prices”), cross-appealed from the same judgment entries. State Auto

Insurance Company (“State Auto”) filed a brief as an Intervening Plaintiff/Cross-Appellee, and

Todd Folden is listed as a Cross-Appellee. We affirm, in part, reverse, in part, and remand for

further proceedings consistent with this decision.

I.

{¶2} In 2005, the Prices entered into a contract with KNL to design and construct their

custom home. According to the Custom Home Construction Agreement (“Construction

Agreement”), KNL was to build a 5,493 square foot home, with an 882 square foot bonus room,

totaling 6,375 square feet of livable space for the original contract price of $751,386. The work 2

on the Prices’ home was to be substantially completed in approximately eleven months after

excavation began on the basement. The record indicates that KNL began construction on

November 21, 2005, the Summit County Building Department completed its final inspection on

February 12, 2007, and a Certificate of Occupancy was issued by the Summit County Building

Department on February 16, 2007. Per the Construction Agreement, KNL was to schedule a

walk-through of the home with the Prices when construction was substantially completed, and

the Prices were to create a “Final Punch List Agreement” as an indication of their final

acceptance of KNL’s work and contractual obligations. However, after the walk-through, a

disagreement arose between the parties, and the Prices refused to execute the punch list, or to

release the final installment of their construction loan to KNL in order to complete the project.

The record indicates that the remainder of the construction loan, in the amount of $25,000, was

placed into an escrow account, and variations of the punch list went back and forth between the

parties for some time. Although the parties never agreed upon the punch list, the Prices moved

into the home in April of 2007. In October of 2010, the Prices vacated the home due to safety

concerns raised by the structural engineer that they hired to inspect the property and offer

remedial solutions.

{¶3} On February 13, 2009, the Prices filed a complaint against KNL and Todd Folden,

the owner and president of KNL, which, as amended, alleged: (1) breach of contract; (2)

fraudulent misrepresentation; (3) breach of the Ohio Consumer Sales Practices Act (“CSPA”);

and (4) negligence. KNL and Folden filed an answer and counterclaim. In their counterclaim,

they alleged that KNL was still owed $20,597.19 for work and material used in completion of

the project. 3

{¶4} KNL and Folden jointly filed a motion for summary judgment on the Prices’

CSPA and fraud claims, as well as on all claims against Folden individually. As to the CSPA,

KNL and Folden specifically argued that the Prices’ claims are barred by the applicable statute

of limitations. The trial court denied the motion and the matter proceeded to jury trial.

{¶5} At the conclusion of the three week jury trial, KNL and Todd Folden filed a

motion for directed verdict arguing that the trial court should rule in their favor on the Prices’

claims for (1) violations of the CSPA; (2) fraud; and (3) all claims against Todd Folden. The

trial court denied this motion and these matters were submitted to the jury.

{¶6} KNL and Todd Folden also objected to the court’s proposed jury instructions and

interrogatories. Further, after the jury concluded its deliberations, an issue arose regarding

possible inconsistencies with the jury’s answers to several CSPA interrogatories and the general

verdict. Specifically, in interrogatories 17(F), 17(J), 17(O), 17(Z) and 17(BB), the jury found

that KNL did not commit “unfair or deceptive act[s],” but still awarded damages to the Prices

under the CSPA. The trial court amended these interrogatories by crossing out language

requiring the jury to find that the acts were “unfair or deceptive,” and, instead, required only

that the jury find KNL committed these acts knowingly, and that the Prices were damaged. The

trial court initialed the revisions and sent the interrogatories back with the jury to “briefly look

over them and see if that makes a difference[.]” KNL and Todd Folden objected to the trial

court’s modification of the interrogatories and argued that if the jury did not find an act to be

unfair or deceptive it is not a violation of the CSPA.

{¶7} Upon reviewing the amended CSPA interrogatories, the jury found that KNL

acted knowingly in: (1) requiring the Prices to pay $2,600 to clear trees from the lot to install

the septic system; (2) failing to install two steel support beams at the foot of the steps in the 4

basement; (3) failing to install properly sized lateral support beams over the glass block

windows in the basement; (4) substituting #2 grade studs for #1 grade studs in the residence; (5)

failing to install the 220 amp electric service; and (6) failing to install insulation with the values

required in the contract. The jury foreman whited out the jury’s previous answers of “no,” as to

whether KNL’s commission of the above acts was “unfair or deceptive,” and changed the jury’s

answers to “yes,” as to whether KNL committed these acts knowingly. The jury never

specifically found that KNL’s acts were unfair or deceptive as to the CSPA claims.

{¶8} On the Prices’ breach of contract claim against KNL, the jury returned a verdict in

favor of KNL, and on KNL’s counterclaim for breach of contract against the Prices, the jury

also returned a verdict in favor of KNL in the amount of $20,597.19. On the Prices’ negligence

claim against KNL, the jury returned a verdict in favor of the Prices in the amount of $20,000,

and on the Prices’ fraud claim against KNL, the jury returned a verdict in favor of KNL. On the

Prices’ CSPA claim against KNL, the jury returned a verdict in favor of the Prices in the

amount of $38,311.62. The jury also returned a verdict in favor of Todd Folden on the Prices’

claims for breach of contract, negligence, fraud, and CSPA violations.

{¶9} KNL filed a motion for judgment notwithstanding the verdict (“JNOV”) arguing

that: (1) the Prices’ CSPA claims are barred by the applicable statute of limitations; and (2)

pursuant to R.C. 1345.09(B), the Prices failed to meet their burden of proof to support their

claim for treble damages and attorney’s fees. The Prices also filed for JNOV, arguing that they

are entitled to judgment in their favor for breach of contract, negligence, CSPA, and KNL’s

counterclaim for breach of contract, or, in the alternative, a new trial pursuant to Civ.R.

59(A)(5), (A)(6), and (A)(7). Further, if the trial court denied their motion for JNOV or new 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)
Molai v. Standing Rock Cemetery Bd. of Trustees
2022 Ohio 3004 (Ohio Court of Appeals, 2022)
Schutte v. Fitzgibbon
2021 Ohio 2669 (Ohio Court of Appeals, 2021)
Hamrick v. Maloof
2021 Ohio 1535 (Ohio Court of Appeals, 2021)
Oberlin v. Lorain Cty. Joint Vocational School Dist. Bd. of Edn.
2019 Ohio 3977 (Ohio Court of Appeals, 2019)
Windward Ents., Inc. v. Valley City Dev. Group, L.L.C.
2019 Ohio 3419 (Ohio Court of Appeals, 2019)
Westfield Ins. Group v. Silco Fire & Sec.
2019 Ohio 2697 (Ohio Court of Appeals, 2019)
Walters v. Goddard
2018 Ohio 5184 (Ohio Court of Appeals, 2018)
Tesar Indus. Contractors v. Republic Steel
2018 Ohio 2089 (Ohio Court of Appeals, 2018)
McMichael v. Akron Gen. Med. Ctr.
2017 Ohio 7594 (Ohio Court of Appeals, 2017)
Knighten v. Erie Islands Resort & Marina
2016 Ohio 7108 (Ohio Court of Appeals, 2016)
Catalanotto v. Byrd
2016 Ohio 2815 (Ohio Court of Appeals, 2016)
Salim v. Smith
2016 Ohio 2764 (Ohio Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2015 Ohio 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/price-v-knl-custom-homes-inc-ohioctapp-2015.