Tesar Indus. Contractors v. Republic Steel

2018 Ohio 2089, 113 N.E.3d 1126
Ohio Court of Appeals·Decided May 29, 2018·No. 16CA010957; 16CA010960·Published·Cited by 4 cases

Opinion

SCHAFER, Presiding Judge.

{¶ 1} Appellant/Cross-Appellee, Republic Steel, appeals the judgment of the Lorain County Court of Common Pleas. Additionally, Appellee/Cross-Appellant, Tesar Industrial Contractors, Inc., appeals from the trial court's judgment. For the reasons set forth below, this Court affirms.

I.

{¶ 2} In 2012, Republic initiated a project to construct an electronic arc furnace at Republic's facility in Lorain, Ohio. The project involved several components, including the erection of supporting and surrounding structures. Republic solicited bids for the project, which required multiple contractors to perform different and overlapping portions.

{¶ 3} Tesar submitted an initial bid of $5,482,495.00 to perform work on the project as a structural contractor for the exhaust system. After some negotiation, Tesar submitted a reduced proposal to Republic on March 22, 2013, with a quote of $4,830,000.00 to perform its portion of work on the project. Republic accepted Tesar's bid, and issued a purchase order dated March 27, 2013, resulting in the parties' original contract.

{¶ 4} The project fell significantly behind schedule and costs began to mount. Republic faulted Tesar's mismanagement for these issues, but Republic also acknowledged that it had some degree of responsibility for initial delays on the project and recognized that unforeseen difficulties had led to some cost overruns. Both Republic and Tesar desired to push forward and complete the project quickly, so the parties began to negotiate a revised contract.

{¶ 5} Tesar, then in a position to appreciate the scope of the remaining work, submitted a proposal to complete the project. The parties entered into their revised contract when Republic accepted Tesar's proposal and issued a purchase order on August 20, 2013, authorizing payment to Tesar in an amount not to exceed $3,712,701.20 for the scope of work described therein. This purchase order also specified that, if any additional work should be required, Republic must issue a revision to the purchase order prior to the work being performed.

{¶ 6} Once again, the work on the project strayed off course both in terms of time and costs. Republic accused Tesar of persistent performance failures and failure to abide by Republic's policies. Tesar blamed Republic for the delay and increased costs, citing Republic's overall failure to adequately manage the project and attempts to cut corners.

{¶ 7} Tesar contends that Republic's project manager, Mark Qualls, began to directly manage the project on a time and materials basis. Further, Tesar claims that Mr. Qualls began verbally instructing Tesar to perform additional work and "out of scope" work prior to obtaining additional purchase orders with assurances of payment. Ultimately, Republic determined that Tesar could not credibly guarantee completion of the project, so it terminated Tesar and obtained another contractor to complete the work.

{¶ 8} Tesar filed suit against Republic in November of 2013, alleging that Republic breached the parties' original agreement from March of 2013, the parties' revised agreement from August of 2013, and agreements for "out of scope" work that Republic directed Tesar to perform in addition to the scope of work described in the original and revised agreements. Tesar also asserted claims for fraudulent inducement and unjust enrichment. Republic answered Tesar's complaint, and filed a counterclaim alleging three causes of action, including a claim that Tesar breached the original and revised contracts. Republic also asserted a claim for declaratory judgment and a claim of unjust enrichment.

{¶ 9} The matter proceeded to a jury trial. At the close of Tesar's case, the court granted Republic's motion for directed verdict, disposing of Tesar's claim for fraud in the inducement. After fourteen days of trial, the remaining claims were submitted to the jury. The jury returned a verdict in favor of Tesar on its breach of contract claim, awarding $3,078,000.00 in damages, and a verdict in favor of Tesar on its claim of unjust enrichment and awarded damages in the amount of $462,128.00, for a total damage award of $3,540,128.00. As to Republic's counterclaims for breach of contract and unjust enrichment, the jury found in favor of Tesar and entered verdicts against Republic on both claims. The jury's resolution of these claims rendered moot, and thereby effectively disposed of, Republic's claim for declaratory judgment. On January 29, 2016, the trial court entered judgment accordingly.

{¶ 10} Thereafter, Republic filed post-trial motions for judgment notwithstanding the verdict, a new trial, or remittitur. The trial court denied these motions in its April 28, 2016 journal entry. On May 26, 2016, Republic appealed the trial court's judgment denying the post-trial motions. Tesar filed a cross-appeal on June 6, 2016. Initially, the cross-appeal was docketed separately, but the matters have been consolidated. Republic raises three assignments of error for our review, while Tesar raises one assignment of error in its cross-appeal. For ease of analysis, we consider the assignments out of order.

II.

Republic's Assignment of Error II

The trial court erred by not granting Republic a new trial on the breach of contract claim because the jury was not correctly instructed on the contract duties.

{¶ 11} In its second assignment of error, Republic argues that it is entitled to a new trial because it is error to instruct a jury as to the breach of duties not presented in a contract, and to instruct the jury that they may find a breach based on such nonexistent duties. Specifically, Republic claims that the court erred by including in the instructions an "enumerated list of actions[,]" or purported breaches, which Tesar failed to tie back to a contractual duty. Republic claims to have objected to the format of the instructions enumerating alleged breaches and, further, that it objected specifically to instructing the jury on duties that did not exist in the contract.

{¶ 12} Civ.R. 59(A) provides multiple grounds upon which a party may base a motion for a new trial and, depending on the basis stated in the motion, "this Court will review a trial court's decision to grant or deny the motion under either a de novo or an abuse of discretion standard of review." Jackovic v. Webb , 9th Dist. Summit No. 26555, 2013-Ohio-2520 , 2013 WL 3128281 , ¶ 17. Republic contends that, because its "new trial motion was based on a question of law," this Court must apply a de novo standard of review. Obscuring the issues, however, Republic only cited generally to Civ.R. 59(A) in the portions of its motion for a new trial based on the alleged error in the jury instructions.

{¶ 13} On appeal, as in its motion for a new trial, Republic has failed to designate any particular Civ.R. 59(A) grounds as a basis for this argument. Additionally, Republic made "no attempt to explain why or how Civ.R. 59(A)'s particular components apply to any of its arguments." Ulrich v. Mercedes-Benz USA, LLC ,

Free access — add to your briefcase to read the full text and ask questions with AI

Tesar Indus. Contractors v. Republic Steel, 2018 Ohio 2089, 113 N.E.3d 1126 (Ohio Ct. App. 2018).

2018 Ohio 2089 (Tesar Indus. Contractors v. Republic Steel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

N. Ridgeville v. Standen
Ohio Court of Appeals, 2026
Besancon v. Cedar Lane Farms, Corp.
2024 Ohio 996 (Ohio Court of Appeals, 2024)
McDonald v. Fogel
2019 Ohio 1717 (Ohio Court of Appeals, 2019)
Tesar Indus. Contractors v. Republic Steel
2018 Ohio 2089 (Ohio Court of Appeals, 2018)