Tesar Indus. Contractors v. Republic Steel

2018 Ohio 2089
CourtOhio Court of Appeals
DecidedMay 29, 2018
Docket16CA010957 16CA010960
StatusPublished

This text of 2018 Ohio 2089 (Tesar Indus. Contractors v. Republic Steel) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tesar Indus. Contractors v. Republic Steel, 2018 Ohio 2089 (Ohio Ct. App. 2018).

Opinion

[Cite as Tesar Indus. Contractors v. Republic Steel, 2018-Ohio-2089.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF LORAIN )

TESAR INDUSTRIAL CONTRACTORS, C.A. No. 16CA010957 INC. 16CA010960

Appellee/Cross-Appellant APPEAL FROM JUDGMENT v. ENTERED IN THE COURT OF COMMON PLEAS REPUBLIC STEEL COUNTY OF LORAIN, OHIO CASE No. 13CIV181984 Appellant/Cross-Appellee

DECISION AND JOURNAL ENTRY

Dated: May 29, 2018

SCHAFER, Presiding Judge.

{¶1} Appellant/Cross-Appellee, Republic Steel, appeals the judgment of the Lorain

County Court of Common Pleas. Additionally, Appellee/Cross-Appellant, Tesar Industrial

Contractors, Inc., appeals from the trial court’s judgment. For the reasons set forth below, this

Court affirms.

I.

{¶2} In 2012, Republic initiated a project to construct an electronic arc furnace at

Republic’s facility in Lorain, Ohio. The project involved several components, including the

erection of supporting and surrounding structures. Republic solicited bids for the project, which

required multiple contractors to perform different and overlapping portions.

{¶3} Tesar submitted an initial bid of $5,482,495.00 to perform work on the project as

a structural contractor for the exhaust system. After some negotiation, Tesar submitted a reduced

proposal to Republic on March 22, 2013, with a quote of $4,830,000.00 to perform its portion of 2

work on the project. Republic accepted Tesar’s bid, and issued a purchase order dated March 27,

2013, resulting in the parties’ original contract.

{¶4} The project fell significantly behind schedule and costs began to mount. Republic

faulted Tesar’s mismanagement for these issues, but Republic also acknowledged that it had

some degree of responsibility for initial delays on the project and recognized that unforeseen

difficulties had led to some cost overruns. Both Republic and Tesar desired to push forward and

complete the project quickly, so the parties began to negotiate a revised contract.

{¶5} Tesar, then in a position to appreciate the scope of the remaining work, submitted

a proposal to complete the project. The parties entered into their revised contract when Republic

accepted Tesar’s proposal and issued a purchase order on August 20, 2013, authorizing payment

to Tesar in an amount not to exceed $3,712,701.20 for the scope of work described therein. This

purchase order also specified that, if any additional work should be required, Republic must issue

a revision to the purchase order prior to the work being performed.

{¶6} Once again, the work on the project strayed off course both in terms of time and

costs. Republic accused Tesar of persistent performance failures and failure to abide by

Republic’s policies. Tesar blamed Republic for the delay and increased costs, citing Republic’s

overall failure to adequately manage the project and attempts to cut corners.

{¶7} Tesar contends that Republic’s project manager, Mark Qualls, began to directly

manage the project on a time and materials basis. Further, Tesar claims that Mr. Qualls began

verbally instructing Tesar to perform additional work and “out of scope” work prior to obtaining

additional purchase orders with assurances of payment. Ultimately, Republic determined that

Tesar could not credibly guarantee completion of the project, so it terminated Tesar and obtained

another contractor to complete the work. 3

{¶8} Tesar filed suit against Republic in November of 2013, alleging that Republic

breached the parties’ original agreement from March of 2013, the parties’ revised agreement

from August of 2013, and agreements for “out of scope” work that Republic directed Tesar to

perform in addition to the scope of work described in the original and revised agreements. Tesar

also asserted claims for fraudulent inducement and unjust enrichment. Republic answered

Tesar’s complaint, and filed a counterclaim alleging three causes of action, including a claim that

Tesar breached the original and revised contracts. Republic also asserted a claim for declaratory

judgment and a claim of unjust enrichment.

{¶9} The matter proceeded to a jury trial. At the close of Tesar’s case, the court

granted Republic’s motion for directed verdict, disposing of Tesar’s claim for fraud in the

inducement. After fourteen days of trial, the remaining claims were submitted to the jury. The

jury returned a verdict in favor of Tesar on its breach of contract claim, awarding $3,078,000.00

in damages, and a verdict in favor of Tesar on its claim of unjust enrichment and awarded

damages in the amount of $462,128.00, for a total damage award of $3,540,128.00. As to

Republic’s counterclaims for breach of contract and unjust enrichment, the jury found in favor of

Tesar and entered verdicts against Republic on both claims. The jury’s resolution of these claims

rendered moot, and thereby effectively disposed of, Republic’s claim for declaratory judgment.

On January 29, 2016, the trial court entered judgment accordingly.

{¶10} Thereafter, Republic filed post-trial motions for judgment notwithstanding the

verdict, a new trial, or remittitur. The trial court denied these motions in its April 28, 2016

journal entry. On May 26, 2016, Republic appealed the trial court’s judgment denying the post-

trial motions. Tesar filed a cross-appeal on June 6, 2016. Initially, the cross-appeal was

docketed separately, but the matters have been consolidated. Republic raises three assignments 4

of error for our review, while Tesar raises one assignment of error in its cross-appeal. For ease

of analysis, we consider the assignments out of order.

II.

Republic’s Assignment of Error II

The trial court erred by not granting Republic a new trial on the breach of contract claim because the jury was not correctly instructed on the contract duties.

{¶11} In its second assignment of error, Republic argues that it is entitled to a new trial

because it is error to instruct a jury as to the breach of duties not presented in a contract, and to

instruct the jury that they may find a breach based on such nonexistent duties. Specifically,

Republic claims that the court erred by including in the instructions an “enumerated list of

actions[,]” or purported breaches, which Tesar failed to tie back to a contractual duty. Republic

claims to have objected to the format of the instructions enumerating alleged breaches and,

further, that it objected specifically to instructing the jury on duties that did not exist in the

contract.

{¶12} Civ.R. 59(A) provides multiple grounds upon which a party may base a motion

for a new trial and, depending on the basis stated in the motion, “this Court will review a trial

court’s decision to grant or deny the motion under either a de novo or an abuse of discretion

standard of review.” Jackovic v. Webb, 9th Dist. Summit No. 26555, 2013-Ohio-2520, ¶ 17.

Republic contends that, because its “new trial motion was based on a question of law,” this Court

must apply a de novo standard of review. Obscuring the issues, however, Republic only cited

generally to Civ.R. 59(A) in the portions of its motion for a new trial based on the alleged error

in the jury instructions. 5

{¶13} On appeal, as in its motion for a new trial, Republic has failed to designate any

particular Civ.R. 59(A) grounds as a basis for this argument. Additionally, Republic made “no

attempt to explain why or how Civ.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. Leimbach
2011 Ohio 6238 (Ohio Supreme Court, 2011)
Jackovic v. Webb
2013 Ohio 2520 (Ohio Court of Appeals, 2013)
Magnum Steel & Trading, L.L.C. v. Mink
2013 Ohio 2431 (Ohio Court of Appeals, 2013)
Wojcik v. Pratt
2011 Ohio 5012 (Ohio Court of Appeals, 2011)
Cromer v. Children's Hosp. Med. Ctr. of Akron (Slip Opinion)
2015 Ohio 229 (Ohio Supreme Court, 2015)
Price v. KNL Custom Homes, Inc.
2015 Ohio 436 (Ohio Court of Appeals, 2015)
Brooks v. Wilson
648 N.E.2d 552 (Ohio Court of Appeals, 1994)
Lapos Constr. Co. v. Leslie, Unpublished Decision (11-6-2006)
2006 Ohio 5812 (Ohio Court of Appeals, 2006)
Lance v. Leohr
459 N.E.2d 1315 (Ohio Court of Appeals, 1983)
J.A. Industries, Inc. v. All American Plastics, Inc.
726 N.E.2d 1066 (Ohio Court of Appeals, 1999)
Davidson v. Hayes
590 N.E.2d 18 (Ohio Court of Appeals, 1990)
Johnson v. Church of the Open Door
902 N.E.2d 1002 (Ohio Court of Appeals, 2008)
Lepera v. Fuson
613 N.E.2d 1060 (Ohio Court of Appeals, 1992)
Kane v. O'day, Unpublished Decision (2-21-2007)
2007 Ohio 702 (Ohio Court of Appeals, 2007)
Harper v. J.D. Byrider of Canton
772 N.E.2d 190 (Ohio Court of Appeals, 2002)
Desai v. Franklin
895 N.E.2d 875 (Ohio Court of Appeals, 2008)
Blair v. McDonagh
894 N.E.2d 377 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 2089, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tesar-indus-contractors-v-republic-steel-ohioctapp-2018.