Tymeless Flooring, Inc. v. Rotolo Consultants, Inc.

172 So. 3d 145, 2014 La.App. 4 Cir. 1392, 2015 La. App. LEXIS 1019, 2015 WL 2412296
CourtLouisiana Court of Appeal
DecidedMay 20, 2015
DocketNo. 2014-CA-1392
StatusPublished
Cited by8 cases

This text of 172 So. 3d 145 (Tymeless Flooring, Inc. v. Rotolo Consultants, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tymeless Flooring, Inc. v. Rotolo Consultants, Inc., 172 So. 3d 145, 2014 La.App. 4 Cir. 1392, 2015 La. App. LEXIS 1019, 2015 WL 2412296 (La. Ct. App. 2015).

Opinion

ROSEMARY LEDET, Judge.

| ]This is a breach of contract suit. The narrow issue presented is whether the payment provision in the construction contract between the parties is a “pay-when-paid” clause — a term of payment — or a “pay-if-paid” clause — a suspensive condition.1 The trial court, finding that the contract contained a suspensive condition, sustained the dilatory exception of prematurity filed by the defendant, Rotolo Consultants, Inc. (“RCI”), and dismissed without prejudice the suit filed by the plaintiff, Tymeless Flooring, Inc. (“Tymeless”). From this judgment, Tymeless |2appeals. For the reasons that follow, we find that the contract contains a term of payment— a “pay-when-paid” clause. Accordingly, we reverse and remand.

FACTUAL AND PROCEDURAL BACKGROUND2

This case arises out of a construction contract between Dryades Young Men’s Christian Association (“Dryades”) and Ellis Construction, Inc. (“Ellis”), the prime contractor, for a project -known as the Dryades YMCA Natatorium and Wellness Center in New Orleans, Louisiana (the “Project”). After contracting with Dryades, Ellis entered into a subcontract with RCI for certain portions of the work on the Project. RCI, in turn, entered into a subcontract with Tymeless to perform [147]*147additional work, as an extra to the contract (the “Subcontract”). Tymeless was thus a subcontractor of a subcontractor on the Project.

After fully performing the work under the Subcontract, Tymeless invoiced RCI. Although RCI made a partial payment, it failed, despite amicable demand, to make full payment. On November 16, 2012, Tymeless filed a Statement of Claim and Privilege with the Orleans Parish Recorder of Mortgages in the principal amount of $24,595.00. On November 15, 2013, Tymeless commenced this suit against RCI.3 In its petition, Tymeless alleged that RCI was hable to it for the full amount of its lien claim, plus interest, attorneys’ fees, and costs. In support of its | ¡¡claim, Tymeless cited the Subcontract; the Private Works Act, La. R.S. 9:4801, et seq; and the Open Account statute, La. R.S. 9:2781.

In response, RCI filed a dilatory exception of prematurity. The sole basis for RCI’s exception was the payment provision contained in Section 5 of the Subcontract,4 which provides as follows:

Payments are to be made as follows: 90% of Sub-Contractor’s approved invoices or pay request will be paid subject to the conditions following, after payment by the Owner for Sub-Contractor’s' work. Retention of 10% will be released upon satisfactory completion of this contract and release of final payment by the Owner.5

RCI’s position was that the underlying proceeding is premature because the payment provisions contained in the contract have not been triggered. Stated otherwise, RCI’s position was that the Subcontract specified that the amounts Tymeless was seeking to recover from RCI were not owed by RCI “unless and until” RCI itself was paid by Ellis. Given that Ellis had not yet paid RCI these amounts, RCI contended that Tymeless’ suit to secure payment from RCI was premature.

14Agreeing with RCI, the trial court granted RCI’s exception of prematurity and dismissed Tymeless’ suit without prejudice. Tymeless then filed a motion for new trial, which the trial court summarily denied. This appeal followed.

DISCUSSION

An exception of prematurity poses the question of “whether the cause of action has matured to the point where it is ripe for a decision by the court.” 1 Frank L. Maraist and Harry T. Lemmon, LOUISI[148]*148ANA CIVIL LAW TREATISE: CIVIL PROCEDURE § 6.6 (1999). An exception of prematurity is governed by La. C.C.P. art. 423, which sets forth the following pertinent rules:

• When the obligation allows a term for its performance, the right to enforce it does not accrue until the term has elapsed.
• If the obligation depends upon a sus-pensive condition,6 the right to enforce it does not accrue until the occurrence or performance of the condition.
• When an action is brought on an obligation before the right to enforce it has accrued, the action shall be dismissed as premature, but it may be brought again after this right has accrued. '

La. C.C.P. art. 423.

In this case, the dispositive facts are not disputed. • The only dispute presented is a legal one. When, as in this case, “there is no dispute as to the dispositive facts, the issue can be decided as a matter of law and the review is de novo.” Demma v. Automobile Club Inter-Insurance Exch., 08-2810, p. 7, n. 4 (La.6/26/09), 15 So.3d 95, 100 (citing Kevin Associates, L.L.C. v. Crawford, 03-0211, p. 15 (La.1/30/04), 865 So.2d 34, 43).

The narrow legal issue presented in this case is whether, under the provisions of the Subcontract, the non-payment by Ellis (a primary contractor) to RCI (a subcontractor) is a suspensive condition — a “pay-if-paid” clause — to RCI’s obligation to pay Tymeless (RCI’s subcontractor). If so, then, as RCI contends and the trial court found, Tymeless’ suit is premature. If not, then, as Tymeless contends, the provision is a term of payment — a “pay-when-paid” clause — and the trial court erred in granting the exception of prematurity and dismissing the suit.7

In order to provide a framework for addressing the issue, we first summarize the jurisprudence distinguishing two types of payment clauses commonly inserted into construction contracts — “pay-when-paid” and “pay-if-paid” clauses.' “The difference between a ‘pay-when-paid’ clause and a ‘pay-if-paid’ clause is vast.” BMD Contractors, Inc. v. Fidelity and Deposit Co. of Maryland, 828 F.Supp.2d 978, 985 (S.D.Ind.2011).8

Explaining the vast difference between these two type of clauses, a commentator notes:

A “pay-when-paid” clause governs the timing within which a general contractor must remit payment to its subcontractor, linking the general contractor’s receipt of payment from the owner to the general contractor’s payment to the subcontractor. Under this type of provision, the general contractor must make payment to the subcontractor within a reasonable time, even if the general contractor does not receive payment from the owner.
IfiThe more restrictive “pay-if-paid” clause, however, does not govern the timing of a general contractor’s payment obligation, but rather dictates whether such payment obligations exist at all. [149]*149Where there is a valid “pay-if-paid” provision in the contract, the general contractor is only required to pay the subcontractor if and to the extent that it receives payment from the owner for the subcontractor’s work. Thus, under a “pay-if-paid” provision, there is a transfer of risk of the owner’s nonpayment from the general contractor to the subcontractor.

Ronald P. Friedberg, “PAY-IF-PAID” CONTRACT PROVISIONS, Providing Some Enforcement Consistency and Predictability in an Unsettled Area of Law, 57 No. 2 DRI For Def. 23 (2015).

A “pay-when-paid” clause is susceptible to the following two interpretations: “(1) as setting a condition precedent to payment or (2) as fixing the point in time when payment would ordinarily occur.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seacor Marine LLC v. GOL, LLC
E.D. Louisiana, 2025
Burgess v. Zheng
257 So. 3d 764 (Louisiana Court of Appeal, 2018)
Bayou Orthotic & Prosthetics Ctr., LL.C. v. Morris Bart, L.L.C.
243 So. 3d 1276 (Louisiana Court of Appeal, 2018)
Boes Iron Works, Inc. v. Gee Cee Group, Inc.
206 So. 3d 938 (Louisiana Court of Appeal, 2016)
A. Zahner company v. McGowan Builders, Inc.
497 S.W.3d 779 (Missouri Court of Appeals, 2016)
Armstrong Airport Concessions v. K-Squared Restaurant, LLC