J&H Grading & Paving v. Clayton Construction

CourtCourt of Appeals of South Carolina
DecidedAugust 2, 2023
Docket2019-001950
StatusPublished

This text of J&H Grading & Paving v. Clayton Construction (J&H Grading & Paving v. Clayton Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J&H Grading & Paving v. Clayton Construction, (S.C. Ct. App. 2023).

Opinion

THE STATE OF SOUTH CAROLINA In The Court of Appeals

J&H Grading & Paving, Inc., Respondent,

v.

Clayton Construction Company, Inc., Appellant.

Appellate Case No. 2019-001950

Appeal From Lexington County Walton J. McLeod, IV, Circuit Court Judge

Opinion No. 6022 Submitted December 1, 2022 – Filed August 30, 2023

AFFIRMED

Townes Boyd Johnson, III, of Townes B. Johnson III, LLC, of Greenville, for Appellant.

Wesley Dickinson Peel and Chelsea Jaqueline Clark, of Bruner Powell Wall & Mullins, LLC, of Columbia, for Respondent.

VINSON, J.: Clayton Construction Company, Inc. (Clayton) appeals the circuit court's ruling that Clayton was liable to J&H Grading & Paving, Inc. (J&H) for attorney's fees pursuant to section 27-1-15 of the South Carolina Code (2007). Clayton argues the circuit court erred by finding (1) Clayton failed to make a reasonable and fair investigation into the merits of J&H's claim under section 27-1-15, (2) the "pay when paid" provision in the parties' subcontract created a condition precedent to payment, (3) the "pay when paid" provision was unenforceable under the South Carolina Subcontractors' and Suppliers' Payment Protection Act (the Act) 1, and (4) any delay in payment beyond ninety days was unreasonable. We affirm. 2

FACTS

Clayton, the general contractor for the construction of a new car dealership owned by Herlong Chevrolet-Buick, Inc. and Herlong Family Properties, LLC, (collectively, Herlong) entered into a subcontract (the Subcontract) with J&H on September 24, 2015. Pursuant to the Subcontract, J&H agreed to complete site work for the project. Clayton agreed to pay J&H $688,075.00 for its work and to make progress payments less retainage of ten percent. Over the course of the project, an additional $28,855.70 was added to the contract price, bringing the total to $716,930.70. The Subcontract provided, "Final payment of the balance due shall be made to [J&H] no later than seven (7) days after receipt by [Clayton] of final payment from Owner [for J&H's] work." (hereinafter, "pay when paid" provision). Clayton made progress payments as agreed.

J&H completed its work under the Subcontract and a certificate of occupancy was issued to the dealership on March 20, 2017. J&H submitted its final pay application via email to Clayton on April 26, 2017, seeking payment of $75,298.00, consisting of the retainage and a small outstanding balance. On July 25, 2017, J&H resubmitted its pay application to Clayton. On August 1, 2017, Clayton responded that it had not been paid retainage by Herlong and therefore could not issue the remaining retainage until it was paid. J&H's final day of work on the project, completing punch list items, was in December of 2017. On January 19, 2018, J&H again emailed Clayton seeking its final payment and retainage. Clayton responded on the same day and stated Herlong had not yet paid Clayton as required by the terms of Clayton's contract with Herlong. Clayton did not dispute the amount due or that J&H had satisfactorily completed the work. J&H sent a letter on January 25, 2018, again seeking payment from Clayton. J&H filed a notice and certificate of mechanics' lien 3 on the property on February 27, 2018.

1 S.C. Code Ann. §§ 29-6-10 to -250 (2007 & Supp. 2022). 2 We decide this case without oral argument pursuant to Rule 215, SCACR. 3 See S.C. Code Ann. § 29-5-10(a) (2007) ("A person to whom a debt is due for labor performed or furnished or for materials furnished and actually used in the erection, alteration, or repair of a building or structure upon real estate . . . by virtue of an agreement with . . . the owner of the building or structure . . . shall have a lien upon the building or structure and upon the interest of the owner of the Thereafter, on March 2, 2018, J&H mailed Clayton a demand pursuant to section 27-1-15 requesting payment. In its March 9, 2018 response, Clayton pointed to the Subcontract's "pay when paid" provision. Clayton stated it had not received payment from Herlong for the work, was in litigation seeking payment, 4 and would "remit any undisputed contract balances to J&H" as soon as it received such payment or the litigation was fully adjudicated. Clayton therefore stated that in accordance with the provisions of the Subcontract, "there [we]re no amounts due and owing to J&H" at the time.

J&H brought this action against Clayton and Herlong on May 21, 2018, for foreclosure of its mechanics' lien and alleging causes of action for breach of contract and quantum meruit. In its answer, Clayton claimed that no amounts were currently due to J&H pursuant to the Subcontract. In February 2019, Herlong, Clayton, and J&H entered into a settlement agreement pursuant to which Herlong "agree[d] to release $75,298.00 under its contract with Clayton directly to J&H as payment for J&H's subcontract with Clayton on the [p]roject" and J&H agreed to dismiss its claims against Herlong. The settlement agreement provided, however, that J&H reserved its claims and rights against Clayton for attorney's fees and interest on the allegedly wrongfully withheld contract balance. Thereafter, both parties filed motions for summary judgment, which the circuit court denied.

The circuit court held a bench trial on the matter in August 2019. The only issue at trial was whether J&H was entitled to attorney's fees under section 27-1-15 based on Clayton's reliance on the "pay when paid" provision in the Subcontract. The circuit court found in favor of J&H and concluded it was entitled to attorney's fees under section 27-1-15. The circuit court rejected Clayton's argument that pursuant to Elk & Jacobs Drywall v. Town Contractors, Inc., 267 S.C. 412, 229 S.E.2d 260 (1976), "pay when paid" clauses were not conditions precedent to payment such that they violated the Act. The circuit court concluded the "pay when paid" provision in the Subcontract was unenforceable because the plain language of the Act expressly prohibited such terms. It therefore determined "Clayton's refusal to pay [wa]s unreasonable on its face." The circuit court ruled the Act—which was passed decades after Elk—was controlling as to the issue and, at most, Elk stood only for the proposition that a contractor had a reasonable time to attempt to obtain

building or structure in the lot of land upon which it is situated to secure the payment of the debt due to him."). 4 In August 2017, Clayton filed a mechanics' lien on the property and sued Herlong for the balance owed on the project. payment from the owner before paying a subcontractor. The circuit court determined that a reasonable delay was "such that would not force [J&H] to resort to legal action" to comply with the provisions of the mechanics' lien statute. The circuit court found delaying payment to J&H longer than ninety days after it requested payment was per se unreasonable because J&H was required to file a mechanics' lien within ninety days of completing its work to preserve its right to payment. The circuit court reasoned that by suspending payment past the statutory deadline for filing the mechanics' lien, Clayton required J&H to initiate legal proceedings that dragged on for two years before J&H was finally paid, even though Clayton did not dispute the amount or that J&H had satisfactorily completed its work. The circuit court "additionally f[ound] Clayton failed to conduct a reasonable and fair investigation" pursuant to section 27-1-15 when it knew the amount owed was undisputed yet still refused to pay J&H. Clayton filed a motion to reconsider, which the circuit court denied. This appeal followed.

ISSUES ON APPEAL

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Summerville v. City of North Charleston
662 S.E.2d 40 (Supreme Court of South Carolina, 2008)
TNS Mills, Inc. v. South Carolina Department of Revenue
503 S.E.2d 471 (Supreme Court of South Carolina, 1998)
Hodges v. Rainey
533 S.E.2d 578 (Supreme Court of South Carolina, 2000)
Lindsay v. Lindsay
491 S.E.2d 583 (Court of Appeals of South Carolina, 1997)
Moore Electric Supply, Inc. v. Ward
450 S.E.2d 96 (Court of Appeals of South Carolina, 1994)
Elk & Jacobs Drywall v. Town Contractors, Inc.
229 S.E.2d 260 (Supreme Court of South Carolina, 1976)
Hardaway Concrete Co. v. Hall Contracting Corp.
647 S.E.2d 488 (Court of Appeals of South Carolina, 2007)
Gowdy v. Gibson
706 S.E.2d 495 (Supreme Court of South Carolina, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
J&H Grading & Paving v. Clayton Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jh-grading-paving-v-clayton-construction-scctapp-2023.