Moore Electric Supply, Inc. v. Ward

450 S.E.2d 96, 316 S.C. 367, 1994 S.C. App. LEXIS 131
CourtCourt of Appeals of South Carolina
DecidedOctober 3, 1994
Docket2230
StatusPublished
Cited by7 cases

This text of 450 S.E.2d 96 (Moore Electric Supply, Inc. v. Ward) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore Electric Supply, Inc. v. Ward, 450 S.E.2d 96, 316 S.C. 367, 1994 S.C. App. LEXIS 131 (S.C. Ct. App. 1994).

Opinion

Shaw, Judge:

Moore Electric Supply, Inc. sued Tom Ward and others to recover an amount allegedly owed for material Moore Electric supplied to a State Highway Department project. Moore later added St. Paul Fire & Marine Insurance Co. as a defendant and sought to recover against a labor and materials bond St. Paul issued for the project. After confessions of judgment and motions to dismiss, St. Paul remained the lone defendant in the case. On April 30, 1993, the trial court, sitting without a jury, entered judgment in favor of Moore Electric. St. Paul appeals the judgment, and Moore appeals the court’s failure to award attorney’s fees and prejudgment interest. We affirm.

*369 SCOPE OF REVIEW

A bond is nothing more than an agreement or contract under seal to pay money or to do some thing, and an action upon the bond is an action at law. Anderson v. Aetna Casualty & Surety Co., 175 S.C. 254, 178 S.E. 819 (1935). In an action at law, tried without a jury, the findings of fact of the judge will not be disturbed on appeal unless found to be without any evidence with reasonably supports them. Republic National Bank v. DLP Industries, Inc. — S.C. —, 441 S.E. (2d) 827 (1994).

FACTS

The South Carolina Department of Highways and Public Transportation entered into a contract with L-J, Inc., to construct a weigh station on 1-26. Pursuant to statute, L-J obtained a payment bond from St. Paul Fire and Marine Insurance Company, to cover the labor and materials supplied to the project. L-J subcontracted a portion of the work to RDC Constructors, Inc., which sub-subcontracted with White Electric Company to supply labor for the electrical portion of the contract.

White Electric ordered supply materials from Moore Electric for the project. Because White Electric was in poor financial shape, RDC agreed to pay Moore Electric directly for items supplied for use on the project. Moore Electric extended an open line of credit to RDC to finance the purchases. Moore Electric’s invoices stated the material was sold to RDC and was shipped to the weigh station site. Although RDC made some payments to Moore Electric, RDC failed to pay for all material it used, and left a balance due to Moore Electric of $40,751.74, of which $40,330.15 represented materials actually consumed on the project.

The trial court ruled that, although Moore Electric was a sub-subcontractor, it was also a supplier to RDC, and supplied materials pursuant to a contract with RDC and RDC’s credit application. The court found the relationship between RDC and Moore Electric was not terminated on January 23, 1991, as St. Paul contended and Moore Electric continued to furnish materials, the last supply date being April 22, 1991. Hence, the court concluded, the July 9, 1991 notice given to St. Paul was within 90 days. The court found- the statute involved is *370 similar to the mechanic’s lien statute, and runs from the last day materials were supplied to the project. Although each item might be separate and Moore Electric did not have any continuing obligation to supply items for the project, the court held the statute allows recovery of the entire amount.

The court further found RDC owed Moore Electric the entire amount claimed, with the exception of two items totalling $355.96. The court found the pull line and the circuit tracer kit were tools which were not totally consumed but could be reused on other projects. Hence, the court ruled Moore Electric may recover $40,330.15.

Lastly, the trial court held St. Paul did not fail to make a fair investigation and did not unreasonably refuse to pay the claim. The court stated St. paul had several defenses, and, although the court ruled against St. Paul, this did not mean the defenses were not viable. The court added that Moore Electric’s own witnesses testified the claim included tools which could be reused, and therefore the whole amount sought was not awarded, implying the sum stated was not liquidated since part was in dispute. For this reason, the court refused to award statutory interest. The court further found Moore Electric was not entitled to attorney’s fees.

APPEAL OF ST PAUL FIRE & MARINE INSURANCE CO.

St. Paul argues Moore Electric failed to prove it supplied materials to the weigh station project, and that the materials were actually incorporated into the project. We disagree. Under our limited scope of review, we find the record contains evidence which reasonably supports the trial court’s finding. The invoices themselves indicate the materials were delivered to the weigh station on behalf of White Electric and RDC. Moore Electric’s credit manager, Goldie Harmon, identified the series of invoices, and testified the materials were designated for the project and he believed they were so used. Jerry Haskell, manager of Moore Electric’s Charleston office, testified that, in his opinion, the items supplied were those which ordinarily would be needed for this project. It was for the court, as trier of fact, to resolve any issue of credibility. In this case, the court did so in favor of Moore Electric.

*371 St. Paul next contends Moore Electric failed to establish it entered into a direct contractual relationship with RDC and, therefore, may not recover against the bond under S.C. Code Ann. § 57-5-1660 (1991). St. Paul claims the evidence demonstrates Moore Electric had a direct contractual relationship only with White Electric, a sub-subcontractor, and therefore may not proceed under the statute. We disagree.

S.C. Code Ann. § 57-5-1660 (1991) provides, in part:

(a) The South Carolina Department of Highways and Public Transportation 1 shall require that the contractor on every public highway construction contract, exceeding ten thousand dollars, furnish the South Carolina Department of Highways and Public Transportation, county, or road district the following bonds, which shall become binding upon the award of the contract to such contractor:
(2) A payment bond with a surety or sureties satisfactory to the awarding authority, and in the amount of not less than fifty per cent of the contract, for the protection of all persons supplying labor and materials in the prosecution of work provided for in the contract for the use of each such person.
(b) Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which such a bond has been furnished under this section and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made, shall have the right to sue on such bond for the amount, or the balance thereof, unpaid at the time of the institution of such suit and to prosecute such action to final execution and judgment for the sum or sums justly due him; provided, however, that any person having direct contractual rela *372

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J&H Grading & Paving v. Clayton Construction
Court of Appeals of South Carolina, 2023
Hardaway Concrete Co. v. Hall Contracting Corp.
647 S.E.2d 488 (Court of Appeals of South Carolina, 2007)
Capital Coatings & Co. v. Browning Construction Co.
Court of Appeals of South Carolina, 2003
Syro Steel Co. v. EAGLE CONST. CO., INC.
460 S.E.2d 371 (Supreme Court of South Carolina, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
450 S.E.2d 96, 316 S.C. 367, 1994 S.C. App. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-electric-supply-inc-v-ward-scctapp-1994.