Capital Coatings & Co. v. Browning Construction Co.

CourtCourt of Appeals of South Carolina
DecidedJanuary 8, 2003
Docket2003-UP-021
StatusUnpublished

This text of Capital Coatings & Co. v. Browning Construction Co. (Capital Coatings & Co. v. Browning Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capital Coatings & Co. v. Browning Construction Co., (S.C. Ct. App. 2003).

Opinion

THE STATE OF SOUTH CAROLINA

THE STATE OF SOUTH CAROLINA
In The Court of Appeals

Capital Coatings & Co., Inc.,        Respondent/Appellant,

v.

Browning Construction Company & United States Fidelity & Guaranty Company,        Appellants/Respondents.


Appeal From Horry County
J. Stanton Cross, Jr., Circuit Court Judge


Unpublished Opinion No. 2003-UP-021
Submitted October 8, 2002 – Filed January 8, 2003


AFFIRMED


Brian P. Robinson, of Columbia, for respondent/appellant.

Robert L. Barnett, of Myrtle Beach, for appellants/respondents.


PER CURIAM:  Capital Coatings & Company, Inc., (“Subcontractor”) sued Browning Construction Company (“Contractor”) alleging causes of action for breach of contract and quantum meruit.  Subcontractor also sued Contractor’s surety, United States Fidelity and Guaranty Company (“USF&G”) seeking attorney’s fees.  Contractor counterclaimed seeking damages for breach of contract and attorney’s fees.  The master-in-equity ruled in favor of Subcontractor finding Contractor breached the contract.  Both the Contractor and Subcontractor appeal.  We affirm.

FACTS/PROCEDURAL BACKGROUND

Contractor was the prime contractor hired to build North Myrtle Beach Middle School (“the School”).  On August 23, 1996, Contractor hired Subcontractor to paint the walls.  Preparation of the walls for painting, called “point-up work,” [1] was to be performed by another entity under Contractor’s supervision. 

On March 24, 1997, Subcontractor temporarily withdrew from the project claiming Contractor failed to prepare the walls properly for painting.  In response, Contractor terminated Subcontractor. 

Subcontractor notified USF&G of its claim for payment.  USF&G conducted an investigation by discussing the claim with representatives of Contractor. Contractor informed USF&G that Contractor did not pay Subcontractor because Subcontractor did not complete the project.  USF&G did not interview the project architect or any employee of Subcontractor.  Based on this information, USF&G denied Subcontractor’s claim.

Subsequently, Subcontractor sued Contractor seeking damages for breach of contract and recovery in quantum meruit.  Subcontractor also sued USF&G seeking attorney’s fees, claiming USF&G did not conduct a reasonable investigation pursuant to South Carolina Code Annotated section 27-1-15 (Supp. 2001).  Contractor counterclaimed, seeking damages for breach of contract and attorney’s fees. 

The case was referred to the master, who concluded: Contractor breached the contract by failing to adequately prepare the walls for painting; Subcontractor failed to mitigate its damages as to unused paint and was thus not entitled to the damages therefrom; and Subcontractor was not entitled to attorney’s fees from Contractor’s surety for failing to perform a reasonable investigation.

LAW/ ANALYSIS

A.          Contractor’s Issues on Appeal

1.                Subcontract

Contractor argues the master abused his discretion in ruling a written subcontract submitted to Subcontractor by Contractor did not form a part of the agreement between the parties.  We disagree.

A contract action is an action at law. Hofer v. St. Clair, 298 S.C. 503, 508, 381 S.E.2d 736, 739 (1989). In an action at law, tried without a jury, a judge’s findings of fact will not be disturbed unless found to be without any evidence which reasonably supports them.  Republic Nat’l Bank v. DLP Indus., Inc., 314 S.C. 108, 110, 441 S.E.2d 828, 829 (1994).  The existence of a contract is a question of fact.  Columbia Hyundai, Inc., v. Carll Hyundai, Inc., 326 S.C. 78, 82, 484 S.E.2d 468, 470  (1997); Small v. Spring Indus. Inc., 292 S.C. 481, 483, 357 S.E.2d 452, 454 (1987) (stating under the common law, the issue of existence of a contract is an issue of fact when its existence is questioned and the evidence is either conflicting or admits of more than one inference). 

On August 23, 1996, Contractor and Subcontractor signed an Acceptance of Estimate Bid (“the Agreement”).  Pursuant to the Agreement, Contractor was responsible for preparing the walls of the School for paint, and Subcontractor agreed to paint and damp-proof the walls.  Additionally, the Agreement specified walls should not be painted until being adequately prepared.  Moreover, Dexter A. Weaver, an officer, director, and shareholder of Subcontractor, testified the Agreement was the contract between the parties. 

Approximately five months after Subcontractor began working, Contractor submitted a proposed subcontract (“subcontract”) to Subcontractor.  Neither Subcontractor nor Contractor signed the Subcontract.

Donald Browning, the president of Contractor, testified the subcontract was not signed because it was subject to negotiation.  Furthermore, Browning wrote a letter to Subcontractor stating the payment arrangements in the Agreement controlled because the subcontract was never signed.

“It is well settled in South Carolina that in order for there to be a binding contract between parties, there must be a mutual manifestation of assent to the terms.”  Edens v. Laurel Hill, Inc., 271 S.C. 360, 364, 247 S.E.2d 434, 436 (1978); Hughes v. Edwards, 265 S.C. 529, 535, 220 S.E.2d 231, 234 (1975) (“For a contract to arise there must be an agreement between two or more parties.”). 

The master ruled the subcontract forwarded by Contractor to Subcontractor five months after the Acceptance of Bid was signed did not constitute the agreement between the parties because the document was unsigned and there was no meeting of the minds as to its terms.  We conclude the aforementioned evidence is sufficient to support that determination. [2]   Therefore, the Master did not abuse his discretion.

II.              Breach of Contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ward v. Epting
351 S.E.2d 867 (Court of Appeals of South Carolina, 1986)
Republic National Bank v. DLP Industries, Inc.
441 S.E.2d 827 (Supreme Court of South Carolina, 1994)
Columbia Hyundai, Inc. v. CARLL HYUNDIA, INC.
484 S.E.2d 468 (Supreme Court of South Carolina, 1997)
Elledge v. Richland/Lexington School District Five
534 S.E.2d 289 (Court of Appeals of South Carolina, 2000)
JKT Co., Inc. v. Hardwick
265 S.E.2d 510 (Supreme Court of South Carolina, 1980)
Hughes v. Edwards
220 S.E.2d 231 (Supreme Court of South Carolina, 1975)
Moore Electric Supply, Inc. v. Ward
450 S.E.2d 96 (Court of Appeals of South Carolina, 1994)
Elliott v. Black River Electric Cooperative
104 S.E.2d 357 (Supreme Court of South Carolina, 1958)
RESORT DEVELOPMENT CO. v. Phillips
178 S.E.2d 813 (Supreme Court of North Carolina, 1971)
Edens v. Laurel Hill, Inc.
247 S.E.2d 434 (Supreme Court of South Carolina, 1978)
Hofer v. St. Clair
381 S.E.2d 736 (Supreme Court of South Carolina, 1989)
Small v. Springs Industries, Inc.
357 S.E.2d 452 (Supreme Court of South Carolina, 1987)
Anderson v. Aetna Casualty and Surety Co.
178 S.E. 819 (Supreme Court of South Carolina, 1934)
Du Bose v. Bultman
56 S.E.2d 95 (Supreme Court of South Carolina, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
Capital Coatings & Co. v. Browning Construction Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/capital-coatings-co-v-browning-construction-co-scctapp-2003.