Hardaway Concrete Co. v. Hall Contracting Corp.

647 S.E.2d 488, 374 S.C. 216, 2007 S.C. App. LEXIS 107
CourtCourt of Appeals of South Carolina
DecidedJune 8, 2007
Docket4252
StatusPublished
Cited by25 cases

This text of 647 S.E.2d 488 (Hardaway Concrete Co. v. Hall Contracting Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardaway Concrete Co. v. Hall Contracting Corp., 647 S.E.2d 488, 374 S.C. 216, 2007 S.C. App. LEXIS 107 (S.C. Ct. App. 2007).

Opinion

BEATTY, J.:

In this breach of contract action, Hall Contracting Corporation (Hall) appeals the master-in-equity’s finding for Hardaway Concrete Company, Inc. (Hardaway) and awarding Hard-away attorney’s fees. We affirm in part, reverse in part, and modify.

FACTS

The South Carolina Public Service Authority (Santee Cooper) sought bids for suppliers and contractors in the construction of a new power plant in Cross, South Carolina. Initially, Santee Cooper sought bids from suppliers of the materials to be used in the construction process. Hardaway submitted a successful bid to become the concrete supplier and entered into a contract with Santee Cooper. The contract provided that Hardaway set up two on-site concrete plants: a primary plant with a rated capacity of 150 cubic yards of concrete per hour and a backup plant with a rated capacity of 100 cubic yards of concrete per hour. The contract specified the concrete be delivered to the jobsite in a “timely and continuous manner.” Hardaway would be paid by the concrete placement contractor, not Santee Cooper, according to the cubic yards agreed to on the batch tickets. Further, the contract required Hardaway to furnish “[i]ce making and cooling equipment for temperature control during hot weather concrete placement” and provided for the price per pound of ice Hardaway would receive.

After accepting Hardaway’s bid, Santee Cooper sought bids for concrete placement contractors for the foundation of the chimney. Hall submitted the lowest bid at $1,746,652. The other bids were higher than Hall’s by at least $200,000. *222 Ultimately, Hall received the contract for the concrete placement work. Hall’s contract provided that it would pay for the concrete by the cubic yards agreed to on the batch tickets.

Hall sent Hardaway a facsimile (First Facsimile) stating, “Hall Contracting agrees to the unit rates, terms and conditions listed in Santee Cooper contract ... (see attached copy).” The attached copy of the contract contained Hardaway’s right to charge for ice. On March 17, 2003, Hall sent Hardaway a purchase order regarding the first pour, specifying how long the pour would take and stating it would be “using two pump and requires a minimum of 200 [cubic yards] per hour (100 [cubic yards] to each pump).” Although the purchase order contained a space for Hardaway to sign, Hardaway never signed the purchase order. Hall sent Hardaway a purchase order before each of the five pours, purporting to set out a specific schedule for the rate of the concrete. Hardaway never signed any of these purchase orders.

After the completion of the project, Hardaway billed Hall for the supplied concrete. Hall paid all but $45,123.84 and sent Hardaway a letter informing Hardaway that Hall was due a credit in that amount from Hardaway. Hardaway brought suit against Hall for breach of contract for failure to pay the $45,123.84. Hall answered and counterclaimed that it and Hardaway entered into an enforceable agreement to supply concrete at a minimum rate of 200 cubic yards per hour. Hall alleged Hardaway breached the contract and asked for damages of $45,123.84.

At trial, David Russell, a senior vice-president at Hall, testified that during the bid process, Hall contacted Hardaway to confirm the capacity of the concrete plants and learned the capacities Hall had been given were “rated capacities and not actual production capacities” and Hall could expect a maximum of 200 cubic yards per hour. He testified that Hall based a lot of its pricing on that information. Russell testified that Hall lost around $60,000 on the Santee Cooper job and probably made an error in estimating. Further he testified the error was made by an estimator who was fired, in part, for his mistakes in estimating.

The master found Hall was a third-party beneficiary in the contract between Hardaway and Santee Cooper, and Harda *223 way was a third-party beneficiary of the contract between Hall and Santee Cooper. Further, the master found Hardaway and Hall also formed a contract in the First Facsimile. The master determined Hardaway produced and delivered the concrete as contemplated in the agreements and accordingly, Hall owed Hardaway the remainder of $45,123.84. Further, it found Hall fraudulently, and in bad faith, generated a list of back charges. Additionally, the master granted Hardaway’s motion to amend its complaint to include a claim for attorney’s fees under section 27-1-15 of the South Carolina Code (1991).

On January 5, 2006, the master held a separate hearing on attorney’s fees. The master found that Hardaway had met its burden of showing Hall had not conducted a fair and reasonable investigation and was thus entitled to attorney’s fees under section 27-1-15. Accordingly, the master awarded Hardaway attorney’s fees of $53,592.56. This appeal followed.

STANDARD OF REVIEW

On appeal of an action at law tried without a jury, the findings of fact of the trial court will not be disturbed unless found to be without evidence which reasonably supports the trial court’s findings. Townes Assocs., Ltd. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976). The rule is the same whether the trial court’s findings are made with or without reference. Id. The trial court’s findings are equivalent to a jury’s findings in a law action. Chapman v. Allstate Ins. Co., 263 S.C. 565, 567, 211 S.E.2d 876, 877 (1975). This court must determine whether any evidence reasonably supports the factual findings of the trial court. Townes Assocs., Ltd., 266 S.C. at 86, 221 S.E.2d at 776. Additionally, the appellate court can correct errors of law. Okatie River, L.L.C. v. Southeastern Site Prep, L.L.C. 353 S.C. 327, 334, 577 S.E.2d 468, 472 (Ct.App.2003). “This scope of review is equally applicable to the factual determinations of a master when, as in the present case, he enters final judgment.” Wigfall v. Fobbs, 295 S.C. 59, 61, 367 S.E.2d 156, 157 (1988).

LAW/ANALYSIS

I. Interpretation of the contract

Hall argues the master erred in awarding judgment in favor of Hardaway. Specifically, Hall contends the master erred in *224 finding: (1) Hardaway was not bound by the concrete production rates provided in the purchase orders and pour specifications; and (2) Hardaway was entitled to charge for ice.

A. Pour Rate

Hall argues the master erred by not finding Hardaway was bound by the pour specifications requested by Hall. Hall argues the sale of concrete is a transaction of goods, and therefore, Article 2 of the U.C.C. governed the transaction. 1 Hall argues Hardaway was aware of the specifications and knew that Hall was relying on Hardaway to provide concrete consistent with those provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The State, Inc. v. Hampton County
Court of Appeals of South Carolina, 2025
Lisa Summer Rice v. Newberry Lions Club
Court of Appeals of South Carolina, 2025
J&H Grading & Paving v. Clayton Construction
Court of Appeals of South Carolina, 2023
Johnson ex rel. Estate of Valenzuela v. Sam English Grading, Inc.
772 S.E.2d 544 (Court of Appeals of South Carolina, 2015)
The Spriggs Group v. Slivka
Court of Appeals of South Carolina, 2013
Spriggs Group, P.C. v. Slivka
738 S.E.2d 495 (Court of Appeals of South Carolina, 2013)
Charleston Pool v. Moran
Court of Appeals of South Carolina, 2013
McCallum v. Eadon
Court of Appeals of South Carolina, 2013
Waccamaw Bank v. Myrtle Beach Smokestack
Court of Appeals of South Carolina, 2011
Dulaney v. Dulaney
Court of Appeals of South Carolina, 2011
MIA Funding, LLC v. Sizer
Court of Appeals of South Carolina, 2010

Cite This Page — Counsel Stack

Bluebook (online)
647 S.E.2d 488, 374 S.C. 216, 2007 S.C. App. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardaway-concrete-co-v-hall-contracting-corp-scctapp-2007.