Vic Davis Construction, Inc. v. Lauren Engineers & Constructors, Inc.

CourtCourt of Appeals of Tennessee
DecidedMarch 20, 2019
DocketE2017-00844-COA-R3-CV
StatusPublished

This text of Vic Davis Construction, Inc. v. Lauren Engineers & Constructors, Inc. (Vic Davis Construction, Inc. v. Lauren Engineers & Constructors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vic Davis Construction, Inc. v. Lauren Engineers & Constructors, Inc., (Tenn. Ct. App. 2019).

Opinion

03/20/2019 IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 20, 2018 Session

VIC DAVIS CONSTRUCTION, INC. v. LAUREN ENGINEERS & CONSTRUCTORS, INC.

Appeal from the Chancery Court for Hawkins County No. 2014-CH-99 Douglas T. Jenkins, Chancellor ___________________________________

No. E2017-00844-COA-R3-CV ___________________________________

A subcontractor brought suit against the general contractor for breach of contract and violations of the Prompt Pay Act. The subcontractor sought both damages, including punitive damages, and reformation of the subcontract based on fraud or mutual mistake. The general contractor counterclaimed for breach of contract. Upon the parties’ agreement, the trial court reformed the subcontract based on mutual mistake. The trial court also granted the general contractor summary judgment on the subcontractor’s claims for fraud and punitive damages. Then, following a bench trial, the court awarded a judgment to the subcontractor on its breach of contract claim and dismissed the general contractor’s counterclaim. The court declined to award the subcontractor a statutory penalty or attorney’s fees under the Prompt Pay Act. We affirm the trial court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

W. NEAL MCBRAYER, J., delivered the opinion of the court, in which JOHN W. MCCLARTY and THOMAS R. FRIERSON II, JJ., joined.

Mark S. Dessauer, Kingsport, Tennessee, (on appeal) for the appellant, Vic Davis Construction, Inc.

Robert P. Noell and William F. Clayton, Knoxville, Tennessee, for the appellee, Lauren Engineers & Constructors, Inc. OPINION

I.

A.

BAE Systems Ordnance Systems, Inc. contracted with Lauren Engineers & Constructors, Inc. to build a new acetic acid refining facility at the Holston Army Ammunition Plant in Kingsport, Tennessee. Lauren, in turn, subcontracted with Vic Davis Construction, Inc. to supply, fabricate, and install underground piping, paving, and grading for the project.

1. Scope of Work

During the bidding process, the parties understood that the design work for underground piping was incomplete. Jerry Hobbs, Lauren’s vice president, explained that, for at least a year, there was a constant flow of revised drawings and scope changes from BAE. After Vic Davis Construction submitted an initial bid, Lauren requested revised pricing based on January 2012 design drawings. Vic Davis Construction submitted a revised bid on February 13, 2012, and a final bid on April 20, 2012. Vic Davis Construction based its final bid on the underground piping shown in the January design drawings.

In early July, Brian Rogers, the contracts manager for Lauren, sent Vic Davis Construction a proposed subcontract. In the subcontract, Lauren agreed to pay Vic Davis Construction a lump sum of $2,105,582 to perform the work shown in drawings and specifications, which were attached as Exhibit C to the subcontract. Although Vic Davis Construction’s project manager, Todd Johnson, reviewed the proposed subcontract, he did not review the attachments. He wrongly assumed that the subcontract included only the drawings and specifications that Vic Davis Construction had priced in the bidding process. In fact, the proposed subcontract included drawings from March and April 2012 that Vic Davis Construction had never seen or priced (the “March drawings”). Unbeknownst to Mr. Rogers, the March drawings significantly increased the quantity of the underground piping. On July 13, 2012, Vic Davis Construction executed the subcontract with the March drawings included as Exhibit C.

In the contract between Lauren and BAE, Lauren also based its budget for underground piping on the January 2012 drawings, the same drawings on which Vic Davis Construction had based its final bid. In October, using the price per linear feet of pipe from Vic Davis Construction’s revised February bid, a Lauren cost analyst estimated that the revisions in the March drawings would cost an additional $577,061 to complete. Assuming that Vic Davis Construction’s final bid included pricing for the March

2 drawings, the analyst suggested using price data from the final bid for a more accurate cost estimate.

Fred Gibson, Lauren’s project budget manager, initially questioned whether Vic Davis Construction’s final bid included the March drawings. In an e-mail to Lauren’s onsite manager and others, Mr. Gibson wrote, “If [Vic Davis Construction] believe[s] they have captured the [March drawings in the subcontract price] then all the better,” but he then followed up with the statement, “Keep in mind these drawings were issued in the March/April timeframe.” After further review, Mr. Gibson concluded that the March drawings were included in the subcontract pricing, but other subsequent revisions were not. So he recommended asking Vic Davis Construction to price the subsequent revisions to obtain a more complete estimate.

Rather than asking Vic Davis Construction, Lauren instead chose to submit a change request to BAE based on its own estimate of the cost of the additional work. Ralph Elkins, Lauren’s construction manager, directed Jeff Campbell, a project manager, to draft the change order without any discussion with Vic Davis Construction. On January 18, 2013, Lauren submitted a change order request to BAE for $399,909.82. BAE approved the change order the following May and paid Lauren in June. Vic Davis Construction was unaware of this change order.

Meanwhile, Adam Hendrickson, Vic Davis Construction’s onsite project manager, noticed that the underground pipe quantities in Lauren’s work schedule exceeded those upon which Vic Davis Construction based its bid. As it turned out, the extra pipe reflected in Lauren’s work schedule was directly attributable to the March drawings. Mr. Hendrickson discussed the additional pipe with Dean Thomason, Lauren’s onsite manager. Together they decided that the extra work could be addressed through a change order, which was required for any work outside the scope of the subcontract.

The parties’ subcontract anticipated the potential for changes to the scope of work. But changes had to be memorialized in writing and approved by Lauren. Under the subcontract, Vic Davis Construction agreed not to “perform any work outside the Scope of Work without receipt of an executed change order or other form of written communication from [Lauren].” Vic Davis Construction further agreed that any work outside the scope of work would be uncompensated “unless written approval [wa]s obtained . . . prior to performance of the Work.”

Despite recognizing the need for a change order and the language of the subcontract, Mr. Hendrickson, at Mr. Thomason’s urging, agreed to delay in requesting a change order. Vic Davis Construction already had a number of unrelated change order

3 requests pending,1 and Mr. Thomason thought it best to get the pending requests resolved first.

By March 2013, Vic Davis Construction had nearly completed the underground piping that it believed to be in its scope of work. Because Mr. Thomason was no longer with Lauren, Mr. Hendrickson notified Mr. Gibson by email that he would soon be submitting a change order request for the additional underground piping on the schedule.

Apparently, Mr. Hendrickson’s email came as a surprise. Mr. Gibson responded, “THIS Sounds like we are missing a huge piece in the forecast!!” Internally, he also behaved as if the March drawings were an intended part of the subcontract. In an April email to Mr. Campbell, Mr. Gibson wrote: “[t]he bulk of the [additional quantities] that [Vic Davis Construction] believes are not included would be [included] if the [March] drawings were his contract basis” and added that “[o]nly minor changes have occurred since those March drawings.” For his part, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Betty Saint Rogers v. Louisville Land Company
367 S.W.3d 196 (Tennessee Supreme Court, 2012)
April Hunter Rigsby (Edmonds) v. Aaron R. Edmonds
395 S.W.3d 728 (Court of Appeals of Tennessee, 2012)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
Lee Medical, Inc. v. Paula Beecher
312 S.W.3d 515 (Tennessee Supreme Court, 2010)
Tennie Martin, et.al. v. Southern Railway Company, et.al.
271 S.W.3d 76 (Tennessee Supreme Court, 2008)
Eadie v. Complete Co., Inc.
142 S.W.3d 288 (Tennessee Supreme Court, 2004)
Blair v. West Town Mall
130 S.W.3d 761 (Tennessee Supreme Court, 2004)
Chrisman v. Hill Home Development, Inc.
978 S.W.2d 535 (Tennessee Supreme Court, 1998)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
Andrew K. Armbrister v. Melissa H. Armbrister
414 S.W.3d 685 (Tennessee Supreme Court, 2013)
A-C Construction, Inc. v. Bakke Corp.
956 P.2d 219 (Court of Appeals of Oregon, 1998)
Kincaid v. SouthTrust Bank
221 S.W.3d 32 (Court of Appeals of Tennessee, 2006)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
John P. Saad & Sons, Inc. v. Nashville Thermal Transfer Corp.
715 S.W.2d 41 (Tennessee Supreme Court, 1986)
Rhea v. Marko Construction Co.
652 S.W.2d 332 (Tennessee Supreme Court, 1983)
Rawlings v. John Hancock Mutual Life Ins. Co.
78 S.W.3d 291 (Court of Appeals of Tennessee, 2001)
Trinity Industries, Inc. v. McKinnon Bridge Co.
77 S.W.3d 159 (Court of Appeals of Tennessee, 2001)
Sikora v. Vanderploeg
212 S.W.3d 277 (Court of Appeals of Tennessee, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Vic Davis Construction, Inc. v. Lauren Engineers & Constructors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/vic-davis-construction-inc-v-lauren-engineers-constructors-inc-tennctapp-2019.