Opinion

OPINION

HARBISON, Justice.

This action was brought by a subcontractor on a construction project against the general contractor and the surety on its performance bond. The general contractor, Marko Construction Company, was a partnership, and the other corporate parties, other than the surety, were partners in the firm. In the trial court there were other parties and other issues, including a claim of lien, but these are not involved in the present appeal.

*333 The subcontractor, Leslie Rhea d/b/a Leslie Rhea’s Landscaping and Grading, entered into a formal subcontract with Marko Construction Company under date of December 4, 1979. The contract was on a standard A.I.A. form. It called for the subcontractor to furnish concrete curbs, sidewalks, porches, and steps in an apartment project for the elderly. The subcontractor was to be paid $30,000 for this work, progress payments to be made regularly upon the submission of invoices and progress estimates, subject to a retainage of ten percent, the latter to be paid upon completion and acceptance of the project.

The subcontractor, appellant here, commenced work and submitted requests for payment in the amount of $22,000 as construction progressed. The general contractor did not meet these requests, however, and as of June 27, 1980, had paid appellant a total of only $6,450. Appellant was distressed for lack of funds and was unable to pay his labor or suppliers. He purchased materials in the amount of $3,721.50, charging them to the general contractor with the consent of the latter. Because of nonpayment of these accounts, the suppliers filed claims of lien against the project.

As of June 27, 1980, therefore, the general contractor was seriously delinquent in making progress payments to appellant who, as found by the Chancellor, had by that time completed ninety percent of the work called for under the subcontract. Since there was no transcript of the evidence and the record on appeal contains only a narrative summary, it cannot be said that the evidence preponderates against the finding of the Chancellor, despite the fact that there was testimony from the general contractor that the work was only sixty percent complete.

An examination of the status of the parties at that time reveals that the subcontractor would have been justified in treating the contract as rescinded and in suing for the value of his labor and materials in quantum meruit. Failure to make a progress payment under a building contract such as this is ordinarily considered a material breach, and there is no indication that that principle would not be applicable here. The rule is stated as follows:

“The failure to pay an instalment of the contract price as provided in a building or construction contract is a substantial breach of the contract, and gives the contractor the right to consider the contract at an end, to cease work, and to recover the value of the work already performed.” 13 Am.Jr.2d Building and Construction Contracts § 102 (1964).

This rule has been recognized in a number of cases in this state. In Ross-Meehan Foundry Co. v. Royer Wheel Co., 113 Tenn. 370, 83 S.W. 167 (1904), it was held that where the defendant agreed to pay for metal castings as delivered, failure to make such payments entitled the other party to terminate the contract. See also Brady v. Oliver, 125 Tenn. 595, 147 S.W. 1135 (1911), where it was held that upon breach of a building contract by the owner, the contractor was entitled to treat the contract as rescinded and to sue for funds expended in preparation for performance and money actually earned in the course of performance.

In the present case appellant did not seek to rescind. Instead appellant and an official of the general contractor met on June 27, 1980, and entered into a short informal written agreement as follows:

“CONTRACT
“We, Richard Patterson and Leslie Rhea have this day entered into a contract for Patterson Construction Co. to finish the concrete work on Meadowview Elderly Apartments at Covington Tennessee. It is also agreed that Marko Construction Co. with whom Patterson Construction Co. is a limited partner, shall pay Mr. Rhea $10,000 for work that he has done on this project.”

There was some question in the Court of Appeals as to whether this document had been properly filed in the record, but there is no disagreement between the parties as to the fact that such a contract was made and as to its terms. The only *334 dispute between the parties is as to further testimony of appellant Rhea as contained in the narrative statement of evidence. There it is stated that Mr. Rhea testified that a condition of this agreement was that the sum of $10,000 was to be paid to him within one week from the date of its execution. No other witness testified to the contrary, but appellees contend that this testimony violated the parol evidence rule. The record contains no indication that there was any objection made to it, however, so that that question is not properly before us.

It is agreed by the parties that no amount whatever was paid to appellant by appellees, under this contract or otherwise, after June 27, 1980. The record indicates that on August 2,1980, several weeks after the June 27 agreement, a check for $3,000 was issued to appellant, but this check was returned for insufficient funds. At the time of trial on May 26, 1981, appellees had still made no payments to appellant, and their witnesses were unable to give any explanation for this.

It is the insistence of appellant that the June 27,1980, agreement was nothing more than an executory accord which was never completed. Appellant contends that he is entitled to proceed on his original claim for labor and materials furnished pursuant to the formal subcontract. The Chancellor so held.

The Court of Appeals, however, concluded that the June 27,1980, agreement represented a novation or a substituted contract. It accordingly held that appellant’s rights were limited by that contract. It reduced the judgment in favor of appellant to $10,-000. The Chancellor had awarded $17,634.

Appellees insist that the Court of Appeals was correct in its analysis and that the June 27, 1980, agreement superseded the formal subcontract entered into on December 4, 1979. They point out that either the general contractor or one of its partners relieved appellant of his obligation to complete the work, thereby furnishing new or additional consideration not previously involved. Ap-pellees state that they did in fact complete the work and that appellant is bound by the terms of the subsequent agreement.

Under the authorities cited above, however, it is clear that appellant was not necessarily obligated to continue the work to completion after the original material breach of the payment provisions by appel-lees. Therefore the promise by appellees to relieve appellant of further performance is not dispositive. There has been no claim that the quality of appellant’s work was unsatisfactory or that appellees had to perform extra or corrective work by reason of any breach by appellant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony Arrington v. Barbara Bryant
Court of Appeals of Tennessee, 2019
TWB Architects, Inc. v. The Braxton, LLC
Tennessee Supreme Court, 2019
TWB Architects, Inc. v. The Braxton, LLC
Court of Appeals of Tennessee, 2018
Emory v. Memphis City Schools Board of Education
514 S.W.3d 129 (Tennessee Supreme Court, 2017)
In re Estate of Dennie Lamar Trent
Court of Appeals of Tennessee, 2016
Jim Ferguson v. Middle Tennessee State University
Court of Appeals of Tennessee, 2013
John H. Key, II, and Wanda Morrison v. Carolyn Lyle
Court of Appeals of Tennessee, 2010
Scipio v. Sony Music Entertainment, Inc.
173 F. App'x 385 (Sixth Circuit, 2006)
Christian Yeubanks v. Methodist LeBonheur
Court of Appeals of Tennessee, 2002
Ward v. Wilkinson
Court of Appeals of Tennessee, 1999
Quality Care Nursing Services, Inc. v. Coleman
728 S.W.2d 1 (Tennessee Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
652 S.W.2d 332, 1983 Tenn. LEXIS 650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rhea-v-marko-construction-co-tenn-1983.