Ross-Meehan Foundry Co. v. Royer Wheel Co.

113 Tenn. 370
CourtTennessee Supreme Court
DecidedSeptember 15, 1904
StatusPublished
Cited by10 cases

This text of 113 Tenn. 370 (Ross-Meehan Foundry Co. v. Royer Wheel Co.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ross-Meehan Foundry Co. v. Royer Wheel Co., 113 Tenn. 370 (Tenn. 1904).

Opinion

Mr. Chief Justice Beard

delivered the opinion of the Court.

The controversy in this case grows out of a contract entered into on the 28th of March, 1899, between the complainant company and the Koyer Wheel Company, by which the first party agreed to make for the second party, from metal patterns to be furnished by the second party, all malleable or other castings required, as set out in the contract, and the second party agreed to order from the first party all such castings as were required by it between the first day of September, 1899, and the first of September, 1903, and to"pay for such castings as were delivered under the contract in sixty days from the date of each delivery, or in cash within ten days thereof with a discount of two per cent.

Soon after the making of the contract, disagreements between the parties thereto arose. The Royer Wheel Company complained of delays in the delivery of castings, as well as of defects in some of those delivered, and the foundry company complained of the defendant company for its failure to make payment for deliveries made. Finally, upon the continued delay on the part of the Roy-er Wheel Company for a term of about nine months'to make payment for castings received by it, the Ross-Mee-han Company notified the Royer Wheel Company that it regarded this nonpayment as such a breach of the contract as relieved it from the obligation to make any future delivery. The present bill was soon thereafter filed [372]*372upon an open account to recover the value of these castings delivered. The Royer Wheel Company filed an answer, in which it set up the contract, and insisted that the complainant had failed to make deliveries as were required by its terms; that many of the castings furnished were defective and that by its renunciation of the contract the complainant, company had inflicted serious losses upon the defendant in view of the advanced price of such castings which it would have now to obtain in the open market. These alleged damages the defendant set up by way of recoupment. The case went to trial, and the chancellor, treating the continued failure on the part of the defendant company to pay as a breach going to the whole contract, released the complainant company from all obligations to make future deliveries, and gave it a decree for the full value of the castings covered by its account, with interest, less a small sum allowed the defendant company by way of recoupment. Upon reference of the cause to the court of chancery appeals, this decree was affirmed.

That court finds as facts that the complainant company substantially complied with the obligations imposed upon it by the contract, and that only a short time before the complainant company notified it of a purpose to rescind because of the long failure to pay for castings delivered the defendant company expressed to the complainant entire satisfaction with the manner in which it had performed its part of the contract. Under this finding the only question really open is, did com[373]*373plainant have a right to rescind, or, rather, to decline to go on with, the contract, upon the mere failure of the defendant to make payment for castings delivered as provided therein?

The contract in question, it will be observed, covers a period of three years, to he executed, however, in installments; that is, the castings were to be made and delivered by the complainant in lots as ordered or required by the defendant, and the defendant was to pay for each delivery in the mode set out in the "opening paragraph of this opinion.

The rights of the respective parties under such a contract had been made a subject of much discussion, which resulted in discordant opinions in England. By some of the courts of that country the contract was regarded as severable or divisible, so that a failure to pay one or more installments due on delivery would not authorize the other party to rescind the contract, as for such failure he could obtain adequate compensation. The English cases are grouped and analyzed by Mr. Benjamin in his work on Sales, and it would seem that some of the earlier of these cases were decided in view of this principle. Others, however, treated such a failure as eviden-tiary in character, leaving the question open for the court or jury whether by such failure the party guilty intended to abandon the contract and set the other party at large. This rule, after more or less fluctuation, seems to have been at last established so as to be beyond fur[374]*374ther controversy in tbe leading case of Mersey Steel & Iron Co. v. Nailor [1884], 9 App. Cas., 434.

In America it will be found that the courts are by no means in accord. However, in the now leading case in this country of Norrington v. Wright, 115 U. S., 188, 6 Sup. Ct., 12, 29 L. Ed., 366, the supreme court of the United States has announced the rule. that, where a seller has provided in a contract with a buyer for a suc- . cession of deliveries, a failure upon the part of the seller to make one or more of the earlier deliveries, went to the whole contract, and relieved the buyer of all obligation to accept. In that case the facts were that Nor-rington sold to Wright & Son 5,000 tons of iron rails to be shipped from a European port or ports, at the rate of about 1,000 tons per month beginning with February, 1880, but the whole contract to be shipped before August 1, 1880. Norrington shipped 400 tons by one vessel in February, 885 tons by two vessels in M'arch, 1,571 tons by five vessels in April, 850 tons by three vessels in May, 1,000 tons by two vessels in June, and 300 tons by one vessel in July, and notified the Wrights of each shipment. The Wrights received and paid for the February shipment upon its arrival in March, and in April gave directions as to what wharves the March shipment should be discharged, but on May 14, having been for the first time informed of the amounts shipped in February, March, and April, gave the agent of Norrington written notice that. they should decline to accept the shipments made in March and April, because none of [375]*375them were in accordance with the contract. Thereafter tender of delivery of other cargoes shipped by Norring-ton to fill this contract was made by his agent to the Wrights, which they declined to accept upon the ground that the earlier shipments had not been made in accordance with the contract, and they thereupon announced their purpose to rescind the same. Suit was brought by the Norringtons, and they sought to recover for a breach of this contract, placing the right of recovery upon two grounds: “(1) That under the contract Nor-rington had six months in which to ship the 5,000 tons, and any deficiency in the earlier months could be made up later, provided that the defendant would not be required to take more than 1,000 tons in any one month. (2) That, if this was not so, the contract was a divisible contract, and the remedy of the defendant for the default in any month was not by rescission of the whole contract, but only by deduction of the damages caused by the delays in shipment on the part of the plaintiff.” To these contentions, ruled against them in the tri'al court, and renewed in the supreme court of the United States, this latter court responded in an elaborate opinion, reviewing, among others, English cases for the purpose of reconciling these latter with the conclusion reached by that court. As to the first of these contentions the court said: “In the contracts of merchants time is of the essence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rhea v. Marko Construction Co.
652 S.W.2d 332 (Tennessee Supreme Court, 1983)
In re Smithdale Industries, Inc.
219 F. Supp. 862 (E.D. Tennessee, 1963)
O. L. Shull Lumber Co. v. F. J. Paxton Co.
1 Tenn. App. 253 (Court of Appeals of Tennessee, 1925)
Tennessee Fertilizer Co. v. International Agr. Corp.
243 S.W. 81 (Tennessee Supreme Court, 1921)
H. R. Wyllie China Co. v. Vinton
192 P. 400 (Oregon Supreme Court, 1920)
Wildberg Box Co. v. Darby
143 Tenn. 73 (Tennessee Supreme Court, 1919)
John Deere Plow Co. v. Shellabarger
140 Tenn. 123 (Tennessee Supreme Court, 1918)
Alpha Portland Cement Co. v. Oliver
125 Tenn. 135 (Tennessee Supreme Court, 1911)
Henningsen v. Tonopah & Goldfield Railroad
33 Nev. 208 (Nevada Supreme Court, 1910)
L.A. Gas & Elec. Co. v. Amalgamated Oil Co.
106 P. 55 (California Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
113 Tenn. 370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ross-meehan-foundry-co-v-royer-wheel-co-tenn-1904.