Mayor of Baltimore v. Schaub Bros.

54 A. 106, 96 Md. 534, 1903 Md. LEXIS 98
CourtCourt of Appeals of Maryland
DecidedFebruary 11, 1903
StatusPublished
Cited by13 cases

This text of 54 A. 106 (Mayor of Baltimore v. Schaub Bros.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayor of Baltimore v. Schaub Bros., 54 A. 106, 96 Md. 534, 1903 Md. LEXIS 98 (Md. 1903).

Opinions

Pearce, J.,

delivered the opinion of the Court.

On June 18th, 1901, the plaintiffs, dealers in coal, entered into a written agreement with the defendant to supply-certain departments of the City Government, including the School Board, with coal up to April 15th, 1902, to be delivered at such times, and in such manner as provided in specifications forming part of the agreement. This contract has been complied with by both parties except as to the coal required for the School Board. The approximate quantity required for the School Board, as stated in the blue print attached to the specifications, was 6290 tons, of which two-thirds was to be delivered during July and August, and one-third as needed; but the School Board reserved the right to order less than the estimated quantity, if less was needed.

The plaintiffs made the first delivery July 16th, 1901, and *547 continued to make deliveries up to August 29th, 1901, aggregating 2101 tons, when they refused to make further deliveries, alleging that the defendant had broken the contract by failing to make payment as provided, and had thereby discharged the plaintiffs from further liability under the contract, and this suit was brought October 28th, 1901, to recover for the coal delivered amounting to $1 i,o62.35. The defendant admitted the correctness of the statement of coal delivered, and that it was indebted to the plaintiffs in the sum of $5,326.42, but filed a plea of set off alleging that the plaintiffs had broken the contract by refusing to make further deliveries, and that they were indebted to defendant in the sum of $5,735-93 “for actual damage caused by the failure of the plaintiffs to fulfill and carry out said contract, as shown by the statement attached to this plea, and prayed to be taken as a part thereof.” Issues were properly joined on the pleadings, and the case went to trial before Judge Dennis sitting as a jury. The amount admitted to be due was paid before the actual trial, and a verdict was rendered for the plaintiffs for $6,175.46, being the full amount claimed after deducting the payment made. The only exception taken was to the rulings upon the prayers, and the only question thus presented is whether the defendant is entitled to the set off claimed.

The provisions of the contract material to the consideration of the case are as follows :

Payments. “Payments will be made once a month by each department for all the coal delivered to that department by the contractor during the previous month, and will be made on the basis of what the coal shows on analysis.” Provision is made for taking samples of coal for analysis from each shipment made to any department during the month. “At the end of the month all the samples thus accumulated will be thoroughly mixed, and a quart preserving jar will be filled with the mixture, labelled and sent to the City Chemist. The City Chemist will, at the end of each month, thoroughly mix the contents of all these jars, and from that mixture take three quart jars for analysis, and will send to each department the *548 result of his analysis of any one of these three jars, and the department will’then adjust the contractors bill, adding or deducting a given percentage of gain or loss upon given percentages of ash shown in the coal.”

Rejections. “If the analysis shows that the shipments of coal made by any contractor during the month, do not come within the specifications,' * * * then when the next shipment made by the contractor, of the same class of coal is received, an analysis will be made of a sample of this coal at once, and if that analysis shows that the coal does not come within the specifications, that shipment will be rejected, and must be removed at once at the contractor’s expense.”

Water Engineer to interpret contract. “ The contractors agree that the Water Engineer is to interpret the terms and conditions of this agreement, and the specifications accompanying ; and in event of any dispute as to the meaning of any of the provisions and clauses of same', the decision of the Water Engineer is to be final.”

The testimony in the case may^be summarized thus :

Lewis W. Schaub, one of the plaintiffs, testified that after the first month’s delivery, he took a statement to Mr. Owens, ■Supervisor of School Buildings, who had the matter in charge, and who went over the bill with him and corrected it; that he told Mr. Owens he would like to have the money, as the contract was taken at a low figure, and they needed the money, and that Mr. Owens told him they should have it as soon as possible. That they continued delivering through August, and that during that month he went to Mr. Owens more than once, and told him they must have the money, as their shippers had made an agreement with them according to their own specifications with the defendant, and if they did not pay the shippers accordingly, they would not ship any more coal. That they went again to urge payment, and were told the analysis had not been sent in, and that he replied, “ you have to’ look out for that yourself; we have only to deliver the coal.” That they went again in September and’were told there was nothing ■for them, and that he then went to see the shippers who replied, *549 “we can’t put up with that we must have money;” whereupon on September 3rd, they sent to the School Board the letter of that date set out in the evidence, stating that both Mr. Owens and Mr. McGill had told them they were unable to pay them — because no analysis had been received from the City Chemist, and that they would not be paid until such analysis was received, also stating that they had called on Prof. Lehman, the City Chemist, in reference to the matter, and that he told them that with an extra force, he could not furnish the analysis required by the School Board by Christmas; that it was apparent the defendant was unable to keep its part of the agreement, and having failed to do so, they must refuse to ship it any more coal. This witness further testified that he told Mr. Quick, the Water Engineer, that they had trouble about the payment and needed money, and that he said they would do the best they could, but could not say he asked Mr. Quick whether they had to wait for payment until an analysis was made; also that his brother, Francis J. Schaub, was with him when he talked with Mr. Quick, and that his brother did most of the talking at that time. Francis J. Schaub testifying for the plaintiffs, said he was a member of the bar, and attorney for the plaintiffs, and confirmed Lewis W. Schaub in detail. He said the plaintiffs understood that defendant had the month of August to make the analysis for July, and they so told Mr. Owens, when they presented the July bill, but asked him to hurry Prof. Lehman up, and he said he would; also that he went to see Prof. Lehman who said he would do the best he could, but that the way the School Board wanted the analysis he could not get them through by Christmas even with six assistants ; also that he had seen Mr. Quick and asked him if he could not hurry it up, and he said he had nothing to do with it; that after the letter of September 3rd, there was a meeting at the Mayor’s office when Mr. Quick and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ammendale Normal Institute, Inc. v. Schrom Construction, Inc.
288 A.2d 140 (Court of Appeals of Maryland, 1972)
Shriver Oil Co. v. Interocean Oil Co.
146 A. 223 (Court of Appeals of Maryland, 1929)
Speed v. Bailey
139 A. 534 (Court of Appeals of Maryland, 1927)
Roberts v. Link
121 A. 633 (Court of Appeals of Maryland, 1923)
Wilson & Co. v. Curlett
117 A. 6 (Court of Appeals of Maryland, 1922)
Hazel Hill Canning Co. v. Roberts Bros.
99 A. 424 (Court of Appeals of Maryland, 1916)
Dorrance v. Hoopes
90 A. 92 (Court of Appeals of Maryland, 1914)
Enterprise Manufacturing Co. v. Oppenheim, Oberndorf & Co.
79 A. 1007 (Court of Appeals of Maryland, 1911)
Henningsen v. Tonopah & Goldfield Railroad
33 Nev. 208 (Nevada Supreme Court, 1910)
Aetna Indemnity, Co. v. John Waters
73 A. 712 (Court of Appeals of Maryland, 1909)
Dryden v. Barnes
61 A. 342 (Court of Appeals of Maryland, 1905)
Ross-Meehan Foundry Co. v. Royer Wheel Co.
113 Tenn. 370 (Tennessee Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
54 A. 106, 96 Md. 534, 1903 Md. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayor-of-baltimore-v-schaub-bros-md-1903.