Ammendale Normal Institute, Inc. v. Schrom Construction, Inc.

288 A.2d 140, 264 Md. 617
CourtCourt of Appeals of Maryland
DecidedMarch 17, 1972
Docket[No. 184, September Term, 1971.]
StatusPublished
Cited by6 cases

This text of 288 A.2d 140 (Ammendale Normal Institute, Inc. v. Schrom Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ammendale Normal Institute, Inc. v. Schrom Construction, Inc., 288 A.2d 140, 264 Md. 617 (Md. 1972).

Opinion

Smith, J.,

delivered the opinion of the Court.

A property owner here complains because a party was permitted to continue to remove sand and gravel from *618 the owner’s property after bringing to date royalty payments which had been in arrears. We conclude that the chancellor properly denied injunctive relief, but gave the wrong reasons for that denial.

Appellant, Ammendale Normal Institute, Inc. (Ammendale) , a religious facility conducted by the “Christian Brothers,” entered into a written agreement in 1963 with appellee, Schrom Construction, Inc. (Schrom), under which Schrom was “to mine sand and/or gravel” from the land of Ammendale, paying certain specified sums per ton. The agreement provided “this ground for mining and processing materials may be available for approximately ten years or until sold.” The method of measurement was set forth. Payment was to “be on a monthly basis by the fifteenth of each month for all materials sold.” It provided “[u]pon completion of the mining or processing areas, Schrom [would] level all ground disturbed in a workmanship like manner so that it [would] have a gradual contour and [would] not impound water and have proper drainage.” It is silent as to any remedy in the event of default on the part of Schrom.

In May of 1969 Ammendale filed a bill of complaint reciting its ownership of property upon which were “located certain valuable deposits of sand and gravel”; that Schrom was in the business of excavating and processing sand and gravel; that Ammendale had permitted Schrom “to remove sand and gravel from certain areas under an informal memorandum”; that “[c]ontrary to the directions of [Ammendale], [Schrom] ha[d] invaded other areas forbidden by [Ammendale] and ha[d] been removing sand and gravel from [Ammendale’s] property against the direction and wishes of [Ammendale]” although Ammendale had “repeatedly notified [Schrom] of the termination of his permission to mine the sand and gravel and to desist from invading the forbidden area of [Ammendale’s] land”; that Ammendale had ordered Schrom to remove its equipment and cease operations but Schrom continued to come upon Ammendale’s land; and that the conduct of Schrom “and its contin *619 uation ha[d] in the past and [would] continue to cause [Ammendale] immediate substantial and irreparable damage unless [Schrom was] enjoined from doing so.” The prayer for relief was in the following form:

“1. That each of the defendants be enjoined pendente lite and permanently from going upon the plaintiff’s property located at Ammendale Road, Beltsville, Maryland, and from removing sand and gravel therefrom.
“2. That an ex parte injunction be granted immediately prohibiting, enjoining and restraining the defendants from going upon the plaintiff’s real estate located at Ammendale Road, Beltsville, Maryland, and removing any sand and gravel therefrom and that the requirement of bond pursuant to Maryland Rule BB75 be dispensed with, because it will constitute an extraordinary hardship for the plaintiff.
“3. That an Order to Show Cause be issued directing each of the defendants to show cause, if any they may have, why the Court should not grant the Plaintiff an injunction pendente lite, to enjoin the defendants from going on the land of the plaintiff located at Ammendale Road, Beltsville, Maryland and removing sand and gravel therefrom.
“4. That the defendants give a full and complete accounting to the plaintiff of the sand and gravel removed by the defendants and the plaintiff have judgment in such amount as may be found due.
“5. And for such other and further relief as the case may require.”

An ex parte injunction was issued.

Subsequently, Ammendale moved for summary judgment. The affidavit in connection with the motion included in it a statement that on July 17, 1970, Ammendale received a payment accompanied by a statement *620 setting forth the materials Schrom admitted removing during the month of April, 1970, but Schrom had “failed and refused to make any payments to [Ammendale] for any months thereafter,” although Schrom had been removing materials and was “in arrears on the payments for the months of May, June, July, August, September, and October.”

The motion for summary judgment was heard by Judge Loveless on January 14, 1971. He passed an order enjoining Schrom from going on Ammendale’s property, and removing sand and gravel until Schrom accounted with Ammendale “for all arrearages from April of 1970 for sand and gravel removed * * * from the premises.” He stated he was unwilling at that time to hold that the circumstances were such as to effect the termination of the entire contract. Accordingly, he denied “the balance of the motion for summary judgment.”

The matter ultimately came on for hearing before Judge Loveless. Apparently, the Schrom operations had been centered in the area known by the parties as “Chicken House Hill.” At the hearing before Judge Loveless it was brought out that Schrom claimed that it had an exclusive right to mine on Ammendale’s property and that this right extended to almost all of the Ammendale land, not being strictly limited to the “Chicken House Hill” vicinity. At the same time Ammendale alleged that the “Chicken House” area was designated by it as the primary site of operation and that this was understood by the parties at the time of the contract, but that it was further understood that mining rights could be extended to Schrom for other areas at the discretion of Ammendale. Judge Loveless in his opinion commented on the fact that Ammendale’s chief dissatisfaction was that payments were consistently late, that some payments were several months in arrears, that two checks were returned marked “Insufficient Funds,” and that after this the bill of complaint was filed. He further said:

“The issues before the Court are several. First, should an injunction issue to stop *621 Schrom’s mining operations on the Institute’s property at Beltsville? Secondly, does Schrom have an exclusive right to mine the property? Third, has there been an effective modification of the contract such that Schrom is entitled to make payments at times later than on the 15th of each month as specified by the contract? Fourth, does Schrom have an enforceable claim against Contee and the Institute for damages?”

All of these questions were answered in the negative. The bill for injunction was denied. Schrom was directed to “pay promptly by the 15th of each month as provided by the contract for all sand and gravel materials removed from [Ammendale’s] property,” and the contract was construed as not giving Schrom exclusive mining rights. The third paragraph of the resulting order read in part:

“[T]hat Schrom Construction, fully and promptly comply with the requirements of the Prince George’s County Zoning Ordinance.”

No appeal was entered from that decree.

This cause reaches us as a result of a petition filed in the same proceeding just over two months after passage of the decree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goss v. C.A.N. Wildlife Trust, Inc.
852 A.2d 996 (Court of Special Appeals of Maryland, 2004)
Matthews v. Amberwood Associates Ltd. Partnership, Inc.
719 A.2d 119 (Court of Appeals of Maryland, 1998)
Matthews v. Amberwood Associates Limited Partnership
719 A.2d 119 (Court of Appeals of Maryland, 1998)
Comptroller of the Treasury v. Shell Oil Co.
500 A.2d 315 (Court of Special Appeals of Maryland, 1985)
Chertkof v. Southland Corp.
371 A.2d 124 (Court of Appeals of Maryland, 1977)
Rose & Crown, Ltd. v. Shaw Enterprises, Inc.
346 A.2d 459 (Court of Special Appeals of Maryland, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
288 A.2d 140, 264 Md. 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ammendale-normal-institute-inc-v-schrom-construction-inc-md-1972.