Mock v. Trustees of First Baptist Church of Newport

67 S.W.2d 9, 252 Ky. 243, 94 A.L.R. 716, 1934 Ky. LEXIS 764
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJanuary 9, 1934
StatusPublished
Cited by15 cases

This text of 67 S.W.2d 9 (Mock v. Trustees of First Baptist Church of Newport) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mock v. Trustees of First Baptist Church of Newport, 67 S.W.2d 9, 252 Ky. 243, 94 A.L.R. 716, 1934 Ky. LEXIS 764 (Ky. 1934).

Opinion

Opinion op the Coubt by

Stanley, Commissioner—

Reversing.

The appeal is from a judgment for the defendants, the appellees, Trustees of the First Baptist Church of Newport, in a suit to recover the balance claimed by Otto D. Mock, appellant, to be due for services as architect in preparing plans and specifications for a Sunday school building. After several conferences with the building committee of the church and the acceptance of preliminary sketches and views, a form of written contract of employment was submitted to the church authorities in February, 1924. It was not immediately signed by the committee, but the conferences continued with the architect, and substantial services had been rendered by him when the contract was executed and delivered to Mock in May, 1924. It became the basis of this litigation.

We need refer to only those parts of the contract which seem to be material to the issue.

Article 3 provided for the payment to .the architect of the sum of 2% per cent, of the total cost of the completed building. But, if it should be found that the church was unable to erect the building at the time of *245 opening the contractors’ estimates, Re should then receive his full compensation based upon the lowest bona fide estimate. In this section it is stipulated that:

“Pending the contractors’ estimates of the cost of said building $55,000 will be used as a figure from which to calculate the architect’s fee, but final settlement to be made on the total cost of this portion of the building.”

Article 5 provided that payments should be made as follows: 1 per cent, upon the completion of the plans and scale details in accordance with the accepted sketch plans. Second payment should be sufficient to increase the total to 2 per cent, to be paid upon the opening of bids or the appointment of a builder. Final payment of a sufficient amount to increase the total to 2% per cent, was to be made when the building was accepted and approved by the architect. Article 6 stipulated the agreement that, if for some unknown reason the erection of the building should be deferred after the completion of the drawings and specifications, the architect should be paid for his services as stated in article 3.

Satisfactory plans and specifications having been completed in detail, bids for the construction were received in September, the lowest of which was $159,254. This was so much in excess of expectations that the bids were rejected. The committee and the architect set about to revise the plans in order to reduce the cost. In view of subsequent developments, it may be said that the evidence justifies the conclusion that from the time the project was initiated the church’s program or desire became progressively more ambitious until the bids were received, and thereafter the committee entertained the commendable hope to secure such a commodious structure as would be adequate for their needs, yet within what they regarded as their church’s financial limitations. It is not clear whether both the original and the modified plans had been abandoned for the time being, but in the latter part of September Mr. Mock rendered a bill for his services amounting to $3981, which was 2% per cent, of the lowest bid of $159,254 based on the original plans, less a credit of $650 previously paid him. This was in accordance with the terms of the contract. The chairman then advised Mock that the committee did not intend to abandon the project, but would continue their efforts to erect the building. It was further stated in the communication that *246 the committee did not feel that they owed him the sum ■claimed, and he was invited to confer with them. On October 4th a conference was held. The parties are not now quite agreed as to what was then verbally agreed. A day or so later $1,150 was sent to Mock as the “amount due to date”; it being said in the letter that this was sent “as per agreement.” Six months thereafter, in April, 1925, after securing some revised detailed drawings from the architect, the church began the erection of two stories of the four-story structure according to the original design. A temporary roof was put on, the idea being to complete the building at some future time. This work was done under the supervision of another architect, who lived in Newport, at a cost of about $80,000. To avoid any suggestion of wrong or impropriety, it should be said that no question is raised as to the right of the church to use these plans.

In June, 1925, Mock asked for the payment of $700 on account, but the committee advised him that under the agreement there was no money due him. In June, 1928, Mock filed this suit to recover his fee of $3,980, less the $1,800 previously paid. The church denied that the plaintiff had performed his contract, and further pleaded that the contract sued upon had been obtained by misrepresentation, in that the plaintiff had represented that the building planned could be erected for $55,000, whereas it developed that it would cost $160,-000, and the sum was so excessive as to be beyond the church’s financial ability, and therefore the bids for the work had been rejected. The further defense was interposed that there had been a settlement and compromise on October 4, 1924, under which the architect had accepted a sum sufficient to bring the total payment to him of $1,800, and had agreed to wait the future payment of fees and compensation until such time as the church in its judgment and discretion was financially able and deemed it advisable to erect and complete the building; that two stories had been completed, but the church, in its judgment and discretion and in fact, had been financially unable to erect or complete the four-story building as contemplated by the contract. The issue as to the terms of the compromise agreement alone was submitted to the jury, and, as stated, the verdict was for the defendant.

All the evidence respecting the procurement and execution of the contract sued on, which was admitted *247 under the plea of misrepresentation, must he placed in the background. It would seem that the defendant re-lized by the time the evidence was concluded that this plea, was untenable. The facts clearly bring the case within the legal principle thus well stated in Cox v. Riggins, 223 Ky. 510, 4 S. W. (2d) 403, 405:

“When knowledge of the fact that fraud has been committed in procuring a contract is brought home to him, the party to it thereby aggrieved is put upon his election. The election to repudiate or rescind the contract for the fraud must be made seasonably. Any further pursuit of the benefits accruing to him under the contract constitute his election to abide by the contract and condone the fraud. Such an election is irrevocable, and he may not thereafter again seek to be relieved of the obligations placed upon him by the terms of the contract because of the fraud practiced upon him in procuring him to become a party to it, because, by electing to pursue the benefits accruing to him under the contract, he has elected to abide by it, and thereby he has condoned the fraud.”

See, also, McKenzie v. Eschmann’s Executors, 174 Ky. 450, 192 S. W. 521; Johns v. Masterson, 176 Ky. 399, 195 S. W. 819; Hofgesang v. Silver, 232 Ky. 503, 23 S. W. (2d) 945, 68 A. L. R. 1481; Cornett v. Kentucky River Coal Co., 175 Ky. 718, 195 S. W. 149.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Backer v. Manning Family Trust
51 F. App'x 522 (Sixth Circuit, 2002)
Hale v. Vencore Nursing Centers East, LLC
54 F. Supp. 2d 1272 (S.D. Alabama, 1999)
Mathews Corp. v. Tutten Enterprises, Inc.
343 So. 2d 902 (District Court of Appeal of Florida, 1977)
Edward J. Gerrits, Inc. v. Astor Electric Service, Inc.
328 So. 2d 522 (District Court of Appeal of Florida, 1976)
Knisley v. Parsons
474 P.2d 599 (Supreme Court of Colorado, 1970)
A. J. Wolfe Co. v. Baltimore Contractors, Inc.
244 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1969)
Stansberry v. Manson
420 P.2d 449 (Alaska Supreme Court, 1966)
Sanford v. Luce
60 N.W.2d 885 (Supreme Court of Iowa, 1953)
North American Graphite Corp. v. Allan
184 F.2d 387 (D.C. Circuit, 1950)
Toppass v. Perkins' Administratrix
104 S.W.2d 423 (Court of Appeals of Kentucky (pre-1976), 1937)
Vansant v. Vansant
69 S.W.2d 724 (Court of Appeals of Kentucky (pre-1976), 1934)

Cite This Page — Counsel Stack

Bluebook (online)
67 S.W.2d 9, 252 Ky. 243, 94 A.L.R. 716, 1934 Ky. LEXIS 764, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mock-v-trustees-of-first-baptist-church-of-newport-kyctapphigh-1934.