A. L. Pickens Company, Inc. v. Youngstown Sheet & Tube Company

650 F.2d 118
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 8, 1981
Docket79-3603
StatusPublished
Cited by34 cases

This text of 650 F.2d 118 (A. L. Pickens Company, Inc. v. Youngstown Sheet & Tube Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. L. Pickens Company, Inc. v. Youngstown Sheet & Tube Company, 650 F.2d 118 (6th Cir. 1981).

Opinion

BAILEY BROWN, Circuit Judge.

This breach of contract action was brought in the Western District of Kentucky to recover commissions allegedly due appellant, A. L. Pickens Co., Inc. (Pickens) under its contract with appellee, Youngstown Sheet & Tube Co. (Youngstown). As Youngstown’s sales agent, Pickens procured an order for Youngstown steel products from the Tennessee Valley Authority *119 (TVA). The order was partially filled, and Pickens received a commission on that part of the order delivered and paid for. Because Pickens received no commission on the unfilled portion of the TVA order, it brought suit to compel payment. On cross motions for summary judgment, the district court held that the contract included a condition precedent to Youngstown’s obligation to pay the commission that had not been fulfilled and entered summary judgment in favor of Youngstown. For the reasons expressed below, we reverse and remand.

On May 5,1975, Youngstown and Pickens entered into a contract which provided that, within a territory, Pickens would act as Youngstown’s sales agent with respect to certain of its products and Pickens agreed to forego handling competing products. 1 Pickens was to be paid commissions in accordance with paragraph 5 of the contract which states as follows:

We will pay you a sales commission of 5% on our F.O.B. net realized mill value of our products covered by this agreement. This commission will be paid once each month on sales of our products on the invoices which have been fully paid. Beyond this 5% commission, we will make no allowance for any expenses you may incur in the solicitation or furtherance of business for us.

In April, 1976, Pickens procured an order from the TVA for approximately $3,000,000 worth of Youngstown steel products. On September 19, 1977, Youngstown stated that financial exigency forced the closing of its Campbell Works plant, which manufactured the steel products that were the subject of the TVA order. In this press release, Youngstown also stated that production of steel products from this plant would be “suspended after presently accepted orders are produced and shipped.” In a letter dated September 21, 1977, Youngstown informed Pickens that portions of the Youngstown facility were closing 2 and that Youngstown was terminating its contract with Pickens. The letter also stated that: “We will ship those orders now on our books and any additional orders that can be supplied from existing stocks.”

As of September, 1977, Youngstown had delivered, and received payment for, approximately $350,000 worth of the TVA order, for which Pickens duly received its commission. The remainder of the order, however, was never filled and Youngstown did not receive payment, nor Pickens a commission, on this unfilled portion.

Youngstown argues that paragraph 5 contains a condition precedent under which it is required to pay Pickens a commission only if it has received full payment for an order. Youngstown argues that because it has not received payment for the unfilled portion of the TVA order, the condition has not been met, and the commission is not due. Pickens, on the other hand, argues that paragraph 5 merely concerns the timing of, and not the right to, payment. In the alternative, Pickens argues that if paragraph 5 is a condition precedent, it should not operate in this case to relieve Youngstown of its obligation to pay the commission.

Initially we note that summary judgment is proper when “there is no genuine issue as to a material fact and ... the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). The parties agree that Kentucky law applies to this diversity case, and that no material issues of fact remain unresolved. Under Kentucky law, construction of a contract term is a question of law. See, e. g. Fox v. Buckingham, 228 Ky. 176, 14 S.W.2d 421 (Ky.1929), appeal after remand, 35 S.W.2d 897, 237 Ky. 415 (Ky.1931). Thus, the only question raised in this case is the proper construction to be *120 given the contract provision in dispute. The district court held that the “straightforward and unambiguous” contract language and the course of performance that existed between the parties compelled the conclusion that paragraph 5 embodies a condition precedent that was not fulfilled. We disagree.

The sentence in paragraph 5 that the district court found to be unambiguous, and which Youngstown argues establishes a condition precedent, states as follows:

This commission will be paid once each month on sales of our products on the invoices which have been fully paid.

It is true that this sentence may be interpreted as restricting Pickens’ right to commissions to those orders for which Youngstown has received full payment. The sentence is, however, also susceptible to the interpretation that although Pickens’ right to payment accrues when the order is secured, it agreed to postpone receipt of its commission until the invoices were paid.

In Mock v. Trustees of First Baptist Church of Newport, 252 Ky. 243, 67 S.W.2d 9 (1934), an architect agreed to prepare plans and specifications for a Sunday school building in consideration for a percentage of the total cost of the building. Difficulties arose concerning the church’s ability to finance the venture, however, and the architect, having been partially compensated, agreed to wait for the balance due him “until the building was completed,” the amount to be determined “based upon the cost of the building.” Id., 67 S.W.2d at 11. The building remained uncompleted for some time, and the architect brought suit to collect his commission. The court held that the completion of the building was not a condition precedent to the church’s duty to pay, but operated merely to fix the time of payment. Id. The court held that the church had an implied obligation to pay the fee within a reasonable time. Id.

Similarly, in Thos. J. Dyer Co. v. Bishop International Engineering Co., 303 F.2d 655 (6th Cir. 1962), a subcontractor agreed to perform certain services in return for a fee of $115,000. The contract provided that “no part of [the fee] shall be due until five (5) days after Owner shall have paid Contractor.” Id. at 656. The owner became insolvent before paying the contractor and the subcontractor was likewise not paid. This court, in an opinion by Shackelford Miller, J., held, under Ohio and Kentucky law, that the relevant contract provision was not a condition precedent, but merely a timing-of-payment provision. Id. at 661.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Witty
W.D. Kentucky, 2022
Acquisition-II, LLP v. EQT Production Co.
830 F.3d 444 (Sixth Circuit, 2016)
Rochelle Johnson v. Patrick Donahoe
642 F. App'x 599 (Sixth Circuit, 2016)
Bradley v. Miller
96 F. Supp. 3d 753 (S.D. Ohio, 2015)
Journey Acquisition-II, L.P. v. EQT Production Co.
39 F. Supp. 3d 877 (E.D. Kentucky, 2014)
NFC ACQUISITION, LLC v. Comerica Bank
640 F. Supp. 2d 964 (N.D. Ohio, 2009)
Foster v. D.B.S. Collection Agency
463 F. Supp. 2d 783 (S.D. Ohio, 2006)
Weaver v. Caldwell Tanks, Inc.
190 F. App'x 404 (Sixth Circuit, 2006)
F.R.C. International, Inc. v. United States
278 F.3d 641 (Sixth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
650 F.2d 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-l-pickens-company-inc-v-youngstown-sheet-tube-company-ca6-1981.