3D Entersprises Contracting Corp. v. Louisville Jefferson & County Metropolitan Sewer District

174 S.W.3d 440, 2005 Ky. LEXIS 224, 2005 WL 2043581
CourtKentucky Supreme Court
DecidedAugust 25, 2005
Docket2003-SC-0249-DG
StatusPublished
Cited by163 cases

This text of 174 S.W.3d 440 (3D Entersprises Contracting Corp. v. Louisville Jefferson & County Metropolitan Sewer District) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
3D Entersprises Contracting Corp. v. Louisville Jefferson & County Metropolitan Sewer District, 174 S.W.3d 440, 2005 Ky. LEXIS 224, 2005 WL 2043581 (Ky. 2005).

Opinions

Opinion of the Court by Justice

JOHNSTONE.

This appeal arises from a judgment of the Jefferson Circuit Court granting summary judgment in favor of Appellant, 3D Enterprises Contracting Corporation; for claims arising from a construction project for Appellee, Louisville and Jefferson County Metropolitan Sewer District. The Court of Appeals reversed and remanded, [443]*443ordering the circuit court to enter summary judgment in favor of the Appellee. This Court granted discretionary review. For the reasons set forth herein, we reverse the judgment of the Court of Appeals and reinstate summary judgment in favor of the Appellant.

Factual & Procedural Background

At the center of this matter is the construction of two bioroughing towers. These towers were designed to contain eleven layers of plastic bioroughing media, a material employed in the wastewater treatment process. In June of 1992, Louisville and Jefferson County Metropolitan Sewer District (“MSD”) contracted with 3D Enterprises Contracting Corporation (“3D”) to build the two bioroughing towers and an associated pumping station at MSD’s main wastewater treatment plant in Louisville. Pursuant to the contract, 3D was to build these towers according to the plans and specifications prepared by Camp, Dresser, & McKee, Inc. (“CDM”), the consulting engineers on the project.

American Surfpac Corporation (“Surf-pac”) was chosen as the media supplier. Pursuant to the contract between 3D and MSD, 3D provided a general one-year warranty on the project. In addition, and also pursuant to the contract, 3D procured from Surfpac a manufacturer’s warranty that extended four years beyond the one-year general warranty.

In May of 1994, CDM advised 3D that Surfpac was experiencing financial difficulties, and in fact was in the process of selling some of its assets. The parties consequently became concerned about Surfpac’s ability to pay its own suppliers and its ability to honor the extended warranty on the media. At this time, 3D had paid Surfpac all sums due except $184,214.28 of its purchase order price for the media. 3D withheld this amount because of its concerns about the value of Surfpac’s extended warranty.

When Surfpac did not receive payment, it filed a mechanic’s lien against the funds due to 3D from MSD pursuant to KRS 376.210 et seq. 3D filed a protest. Also, in response to Surfpac’s lien action, 3D filed a counterclaim against Surfpac, arguing that Surfpac would not be able to honor the extended warranty for the bio-roughing media. 3D also filed a cross-claim against MSD and sought a declaration releasing itself from any obligation under the contract for the extended warranty. MSD did not file a counterclaim to 3D’s cross-claim, but did withhold the lien amount from 3D.

On December 23, 1995, one of the bio-roughing towers collapsed, destroying most of the media in that tower. MSD immediately began to investigate the collapse. As part of this investigation, it undertook discovery of Surfpac regarding its ability to honor its media warranty. By this time, Surfpac’s financial picture was bleak: shortly after the collapse, Surfpac’s attorneys admitted the company’s insolvency.

In August of 1996, MSD filed suit against 3D and CDM to recover damages arising from the collapse. 3D filed a counterclaim seeking recovery of unpaid contract balances, including the $184,214.28 withheld as a result of the Surfpac lien. Meanwhile, because any recovery from Surfpac seemed unlikely, MSD entered into its own negotiations with the media supplier. Those negotiations culminated in a settlement agreement by which Surf-pac surrendered all claims to any remaining contract funds, and MSD released Surfpac from any warranty claims.

Surfpac’s lien litigation was still pending at this time; it had been continued indefinitely following the tower’s collapse. [444]*444However, in July of 1997, the action was dismissed without prejudice for Surfpac’s failure to prosecute. Purportedly in accordance with KRS 376.250(4), MSD continued to retain the $184,214.28 lien amount, pending court order or judgment. No court order was ever issued regarding the lien funds.

In light of the suit filed by MSD against 3D and CDM for damages resulting from the collapse, mediation was commenced. A settlement agreement was finally reached in April of 1999. As part of the agreement, 3D paid MSD an agreed sum for settlement of the breach of contract, breach of warranty, and negligence claims asserted by MSD in connection with the collapse. In exchange, MSD released any and all claims against 3D arising from the construction of the towers. The agreement did provide that 3D would retain its counterclaim against MSD for recovery of its contract balances. As a result, MSD’s claims against 3D were dismissed with prejudice and 3D’s counterclaim was dismissed without prejudice.

After the MSD action was dismissed, 3D began seeking recovery of its contract balances to no avail. An action was commenced in Jefferson Circuit Court; it is this action that is the basis of the present appeal. In its complaint, 3D sought to collect the balance it alleges MSD owed on the contract, including the $184,214.28 amount originally liened by Surfpac, which MSD continued to retain. A motion for partial summary judgment was filed by 3D as to the lien amount, asserting that it was entitled to payment of the $184,214.28 pursuant to KRS 376.210 et seq. MSD filed a cross-motion for summary judgment with respect to the same funds, arguing that it was entitled to retain the funds because 3D had breached its contract by failing to deliver a warranty with value. The trial court entered summary judgment in favor of 3D as to the liened funds, concluding that MSD was obliged to pay the $184,214.28 to 3D because the lien had been released. KRS 376.210(3) provides that liens shall only attach to “any unpaid balance due the contractor for the improvement.” According to the circuit court’s reasoning, the lien represented monies otherwise due 3D; thus, when the lien was released, MSD should have complied with the statute and paid the $184,214.28 in liened funds directly to 3D. MSD appealed. 3D cross-appealed that portion of the trial court’s judgment denying prejudgment interest.

The Court of Appeals reversed the trial court’s summary judgment, determining that the trial court had erred in reviewing the claims solely pursuant to the lien statutes, without addressing MSD’s cross-motion contract claims. The Court of Appeals focused on the following facts: 3D had withheld $184,214.28 from Surfpac, based on 3D’s belief that Surfpac would be unable to honor its warranty. Although the lien was released, 3D was no longer entitled to these funds because it had breached its contract with MSD by delivering a worthless warranty on the media. The $184,214.28 represented the value of the warranty, and therefore MSD was permitted to -withhold this payment from 3D as a result of its breach.

This Court granted discretionary review. Both parties make several arguments on appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brenda M. Whitfill v. Dennis R. Whitfill
Court of Appeals of Kentucky, 2025
Carter L. Blevins v. E.G. Bertram, III
Court of Appeals of Kentucky, 2024
Big Sandy Company, L.P. v. Eqt Gathering, LLC
Court of Appeals of Kentucky, 2024
Eqt Gathering, LLC v. Big Sandy Company, L.P.
Court of Appeals of Kentucky, 2024
Adam Wheeler v. City of Pioneer Village, Kentucky
Court of Appeals of Kentucky, 2024
Joel Franklin v. Emery Law Office, Inc.
Court of Appeals of Kentucky, 2024
Steve Dismore v. Kentucky Parole Board
Court of Appeals of Kentucky, 2024
Kimberly Rogers v. Erie Insurance Exchange
Court of Appeals of Kentucky, 2024
David Partida v. Instant Auto Credit, Inc.
Court of Appeals of Kentucky, 2023
Anyconnect US, LLC v. Williamsburg Place, LLC
Court of Appeals of Kentucky, 2021
Salyersville National Bank v. Brandon Russell
Court of Appeals of Kentucky, 2021

Cite This Page — Counsel Stack

Bluebook (online)
174 S.W.3d 440, 2005 Ky. LEXIS 224, 2005 WL 2043581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/3d-entersprises-contracting-corp-v-louisville-jefferson-county-ky-2005.