Big Sandy Company, L.P. v. Eqt Gathering, LLC

CourtCourt of Appeals of Kentucky
DecidedJune 28, 2024
Docket2022-CA-1481
StatusUnpublished

This text of Big Sandy Company, L.P. v. Eqt Gathering, LLC (Big Sandy Company, L.P. v. Eqt Gathering, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Big Sandy Company, L.P. v. Eqt Gathering, LLC, (Ky. Ct. App. 2024).

Opinion

RENDERED: JUNE 28, 2024; 10:00 A.M. NOT TO BE PUBLISHED

Commonwealth of Kentucky Court of Appeals NO. 2022-CA-1393-MR

EQT GATHERING, LLC AND EQT PRODUCTION COMPANY APPELLANTS

APPEAL FROM PIKE CIRCUIT COURT v. HONORABLE EDDY COLEMAN, JUDGE ACTION NO. 13-CI-00617

BIG SANDY COMPANY, L.P. APPELLEE

AND

NO. 2022-CA-1481-MR

BIG SANDY COMPANY, L.P. CROSS-APPELLANT

CROSS-APPEAL FROM PIKE CIRCUIT COURT v. HONORABLE EDDY COLEMAN, JUDGE ACTION NO. 13-CI-00617

EQT GATHERING, LLC AND EQT PRODUCTION COMPANY CROSS-APPELLEES OPINION AFFIRMING IN PART, REVERSING IN PART, AND REMANDING ON APPEAL NO. 2022-CA-1393-MR AND AFFIRMING ON CROSS-APPEAL NO. 2022-CA-1481-MR

** ** ** ** **

BEFORE: EASTON, ECKERLE, AND LAMBERT, JUDGES.

EASTON, JUDGE: A jury found the Appellants EQT Gathering, LLC, and EQT

Production Company (we will refer to them collectively as “EQT”) breached the

terms of a Pipeline Easement Agreement (“Agreement”) with Appellee, Big Sandy

Company, L.P. (“Big Sandy”) and awarded damages. After the trial, the circuit

court awarded Big Sandy prejudgment and post judgment interest, as well as

attorneys’ fees and costs. For the reasons which follow, we affirm all but the

award of prejudgment interest, and we remand that issue for further proceedings.

FACTUAL AND PROCEDURAL HISTORY

Big Sandy owns thousands of acres of property in Pike County. For

some acres, it owns the surface rights, while on others, it owns only the mineral

rights. Big Sandy leases its property to coal mining companies, who then mine the

coal and pay royalties to Big Sandy. EQT is a company that produces and

transports natural gas. The transport of this gas is through pipelines.

The Agreement is dated August 1, 2003. The original parties were

Big Sandy and EQT’s predecessor-in-interest. The Agreement allowed for transfer

to EQT. The Agreement permitted installation and maintenance of an underground

-2- pipeline across tracts of Big Sandy’s property. For this purpose, both temporary

construction easements and permanent easements for the pipeline and access to it

were provided.

The Agreement recognized the right of Big Sandy to get the coal in

the land where the pipeline was placed. If such work was done, loss of ground

support could impact the pipeline. The Agreement created a process for this

development. Paragraph 7 stated that if Big Sandy “has a reasonable basis to

believe” that operations for underground mining “may” occur within twelve

months then Big Sandy was to provide notice to EQT. Operations were not just

the actual mining but also work preparatory for that purpose like building roads.

EQT could move the pipeline or purchase the unmined coal. The

purchase of unmined coal presented challenges about what would need to be paid.

A determination would have to be made on the amount of the coal in the ground.

The purchase option, Paragraph 7(b), required each side to select an engineer to see

if they could agree to the amount. If they could not do so, an “umpire” engineer

could decide the amount. Due to litigation, the parties never got that far. If the

amount had ever been agreed upon, the price was fixed by Paragraph 8.

On January 23, 2013, Big Sandy sent a letter to EQT which stated it

had a lessee who intended to begin mining operations near the pipeline within

twelve months. Big Sandy believed this letter served as sufficient notice under the

-3- Agreement. Under Paragraph 10 of the Agreement, EQT had thirty days to make

an election to either relocate the pipeline or pay for the coal.

EQT made no response to Big Sandy’s notice letter until the evening

of February 22, 2013. This response was an email which requested additional

information. This email did not contain an election to move the pipeline or to pay

for the coal in place.

Communications then took place between Big Sandy and EQT in an

attempt to resolve the issue. EQT did not believe the Agreement covered three out

of four tracts of property on which the pipeline was located. Big Sandy disagreed,

as it believed the Agreement covered the entire portion of EQT’s pipeline.

On June 7, 2013, EQT filed a Declaratory Judgment in the Pike

Circuit Court. In this action, EQT asked the court for an order stating it did not

have to pay to move the pipeline on tracts 1-3. Big Sandy counterclaimed for

breach of contract. EQT subsequently amended its Complaint to include a claim of

reimbursement for costs it claimed it incurred in its plans to relocate the pipeline.

In February 2015, the Pike Circuit Court entered a Judgment ruling

the Agreement applied to the entire pipeline at issue. The circuit court denied all

other motions for summary judgment, as all other rulings would have required a

choice between factual determinations. This ruling that the Agreement applied to

the entire pipeline was subsequently affirmed by a unanimous Kentucky Supreme

-4- Court. See Big Sandy Company, L.P. v. EQT Gathering, LLC, 545 S.W.3d 842

(Ky. 2018).

When the case returned to the circuit court, all that remained was Big

Sandy’s breach of contract claim, as well as EQT’s claim for reimbursement of

costs. Significant discovery ensued. The parties had considerable disagreements,

including what evidence was admissible and jury instructions.

The jury trial finally began on May 2, 2022. Many of the material

facts were undisputed. There was testimony regarding the negotiation and

formation of the Agreement, as well as Big Sandy’s notice letter. Every witness

generally agreed with what the terms of the Agreement were.

Chauncy Curtz (“Curtz”), who is the president of the general partner

of Big Sandy, testified first. Curtz testified that Big Sandy entered into a lease

agreement with a mining company by the name of Silver Slate in July 2011. Silver

Slate would mine the coal on Big Sandy’s property in exchange for royalties. The

coal seams to be mined were in the same area as the pipeline. Over the next

several months, Silver Slate worked to obtain a mining permit for this property. In

April 2012, Silver Slate’s permit was “technically approved.”1

1 If a permit is “technically approved,” all the application paperwork is completed. What remains to be completed before permit issuance is to submit bonds, an affidavit of ownership, certificate of insurance, and a check for any violations. Once “technically approved,” a permit can be issued in approximately one to two months.

-5- However, Silver Slate’s mining permit was never issued. Upon final

review, it was determined that an owner of Silver Slate had mining violations on

another property that needed to be resolved. Silver Slate was “permit-blocked,”

meaning that no new mining permits would be issued to Silver Slate unless and

until these violations were remedied. Silver Slate never remedied these violations.

Eric McPeek with McPeek Energy (we will refer to them collectively

as “McPeek”) approached Big Sandy and indicated an interest in taking over Silver

Slate’s lease. McPeek had a lease with Big Sandy on another piece of property, so

Big Sandy was very familiar with McPeek. Curtz said that Big Sandy and McPeek

had a good working relationship. It was at this point that an agreement was

reached that McPeek would take over Silver Slate’s lease and obtain a mining

permit for this property. However, due to the location of the pipeline, it would

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woodard v. Commonwealth
147 S.W.3d 63 (Kentucky Supreme Court, 2004)
Reliable Mechanical, Inc. v. Naylor Industrial Services, Inc.
125 S.W.3d 856 (Court of Appeals of Kentucky, 2004)
Equitania Insurance Co. v. Slone & Garrett, P.S.C.
191 S.W.3d 552 (Kentucky Supreme Court, 2006)
Frear v. P.T.A. Industries, Inc.
103 S.W.3d 99 (Kentucky Supreme Court, 2003)
Nucor Corp. v. General Electric Co.
812 S.W.2d 136 (Kentucky Supreme Court, 1991)
Cox v. Cooper
510 S.W.2d 530 (Court of Appeals of Kentucky (pre-1976), 1974)
Conseco Finance Servicing Corp. v. Wilder
47 S.W.3d 335 (Court of Appeals of Kentucky, 2001)
Alexander v. S & M MOTORS, INC.
28 S.W.3d 303 (Kentucky Supreme Court, 2000)
Church & Mullins Corp. v. Bethlehem Minerals Co.
887 S.W.2d 321 (Kentucky Supreme Court, 1992)
Hamilton v. CSX Transportation, Inc.
208 S.W.3d 272 (Court of Appeals of Kentucky, 2006)
Fields v. Fields
58 S.W.3d 464 (Kentucky Supreme Court, 2001)
Jackson v. Tullar
285 S.W.3d 290 (Court of Appeals of Kentucky, 2007)
Cummings v. Commonwealth
226 S.W.3d 62 (Kentucky Supreme Court, 2007)
Peters v. Wooten
297 S.W.3d 55 (Court of Appeals of Kentucky, 2009)
Metro Louisville/Jefferson County Government v. Abma
326 S.W.3d 1 (Court of Appeals of Kentucky, 2009)
Cummings v. Covey
229 S.W.3d 59 (Court of Appeals of Kentucky, 2007)
University of Louisville v. RAM Engineering & Construction, Inc.
199 S.W.3d 746 (Court of Appeals of Kentucky, 2005)
Commonwealth, Department of Highways v. Tyree
365 S.W.2d 472 (Court of Appeals of Kentucky (pre-1976), 1963)
Taylor v. Kennedy
700 S.W.2d 415 (Court of Appeals of Kentucky, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
Big Sandy Company, L.P. v. Eqt Gathering, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/big-sandy-company-lp-v-eqt-gathering-llc-kyctapp-2024.