Middletown Engineering Co. v. Main Street Realty, Inc.

839 S.W.2d 274, 1992 Ky. LEXIS 149, 1992 WL 298078
CourtKentucky Supreme Court
DecidedOctober 22, 1992
Docket91-SC-1005-DG
StatusPublished
Cited by12 cases

This text of 839 S.W.2d 274 (Middletown Engineering Co. v. Main Street Realty, Inc.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Middletown Engineering Co. v. Main Street Realty, Inc., 839 S.W.2d 274, 1992 Ky. LEXIS 149, 1992 WL 298078 (Ky. 1992).

Opinion

REYNOLDS, Justice.

This is an action in which an unpaid subcontractor has appealed from a judgment which dissolved its mechanic’s lien as being improperly perfected against the owner.

Main Street Realty, Inc., owner of the Belknap Building in Louisville, Kentucky, engaged Coleman Building Corporation, as the general contractor, to renovate its building. Coleman, which is not a party in this Court, entered into a subcontract with Middletown Engineering Company for the installation and completion of the heating and air conditioning work on the project. Coleman hired Middletown Engineering in February of 1989, and made a partial payment of $9,475 on April 14, 1989, but made no further payment. Middletown complet *275 ed its work May 12, 1989, and claimed a balance due of $49,513 for both materials and labor. On July 31, 1989, Middletown filed a mechanic’s lien against the owner in the Jefferson County Clerk’s office and mailed a copy of the lien statement to Main Street Realty within seven days after that filing so as to satisfy the notice requirements of KRS 376.080(1). This action was filed by Middletown on September 22,1989.

The owner moved to dismiss because the subcontractor failed to provide a prelien notice pursuant to KRS 376.010(3) and Jefferson Circuit Court entered judgment sustaining the motion.

The Court of Appeals reversed and stated that the agency of the general contractor for the owner was a material issue of fact and that a lien statement (KRS 376.-080) is not a substitute for the prelien written notice required by KRS 376.010(3).

Granting discretionary review, we consider the issues raised to be as follows: Was the subcontractor required to send notice of its intent to file a mechanic’s lien to the owner and, if so; was the statutory requirement satisfied by mailing a copy of the recorded lien to the owner?

The unambiguous statutory procedure for perfecting and enforcing a mechanic’s lien in this state is set forth in KRS 376.-010, 376.080 and 376.090. Laferty v. Wickes Lumber Company, Ky.App., 708 S.W.2d 107 (1986) provides that:

Within 120 days after furnishing the last labor or material, the owner must be notified in writing of the claimant’s intent to claim a lien if he is not paid. Within six months after furnishing the material, a lien statement must be filed with the county court clerk.. KRS 376.-080. Finally, an action to enforce the perfected lien must be commenced within one year after the filing of the statement with the clerk. KRS 376.090. Failure to take any of these steps dissolves the lien.

Specifically, the subcontractor did not comply with KRS 376.010(3) which requires as follows:

No person who has not contracted directly with the owner or his agent shall acquire a lien under this section unless he notifies in writing the owner of the property to be held liable or his authorized agent, within seventy-five (75) days on claims amounting to less than $1,000 and one hundred twenty (120) days on claims in excess of $1,000 after the last item of material or labor is furnished, of his intention to hold the property liable and the amount for which he will claim a lien.

The purpose of the required notice to the property owner is to so inform the owner of both the nature and the amount of the claim in order that he may protect himself in his future dealings with the person (general contractor) with whom the subcontractor claimant has contracted, and particularly to enable him, in the majority of cases, to retain whatever money may be due the contractor and to apply it to the payment of the lien claimed.

Actual notice does not serve as a substitute for the required statutory notice. Therefore, the perfected lien of the mechanic or materialman does not depend on the knowledge of the owner, but on whether the mechanic or materialman has followed the requirements of the statute as to notice and as to the filing of the statement required by the statute. The knowledge or the lack of knowledge by the owner is immaterial. Powers v. Brewer, 238 Ky. 579, 38 S.W.2d 466 (1931). We observe, however, that when the filing of a lien is almost simultaneous with the furnishing of the written prelien notice, an identifiable purpose may not manifest itself. This, however, is the extreme situation.

We find no compelling reason to adopt new law or reinterpret Kentucky’s mechanic’s lien statutes. Kentucky law relative to the acquisition, perfection and enforcement of mechanic’s liens is both established and grounded in public policy.

Appellant contends that for purposes of the mechanic’s lien statute, a general contractor is the agent of the owner as a matter of law and therefore prelien notice is not required. Kentucky authority is not cited as there is none, and we decline to adopt such other authority which appellant *276 cites in support of his “hire the people for me” theory. Appellant’s argument is thus so since it did not send the owner a prelien notice. KRS 376.010(3). Only if the subcontractor dealt directly with the owner or its agent is appellant exempt from the pre-lien notice requirement.

Agency continues to be a question of fact to be determined from the circumstances and the conduct of the parties. Crump v. Sabath, 261 Ky. 652, 88 S.W.2d 665 (1935). Summary judgment was, therefore, improper as a material question of fact, as to agency, existed. Steelvest, Inc. v. Scansteel Service Ctr., Ky., 807 S.W.2d 476 (1991).

Appellant’s argument, while appealing, is not persuasive and his reliance upon “liberal construction” decisions including Campbell & Summerhays, Inc. v. Greene, Ky., 381 S.W.2d 531 (1964), and upon Guarantee Electric Co. v. Big Rivers Electric Corp., 669 F.Supp. 1371 (W.D.Ky.1987), is clearly distinguishable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nirupama Kulkarni v. Dennis Horlander
Kentucky Supreme Court, 2024
Prodigy Construction Corp. v. Brown Capital, Ltd.
525 S.W.3d 108 (Court of Appeals of Kentucky, 2017)
In re: Johnson v.
Sixth Circuit, 2007
Brock v. Pilot Corp.
234 S.W.3d 381 (Court of Appeals of Kentucky, 2007)
Schumacher Electric, Inc. v. DeBruyn
604 N.W.2d 39 (Supreme Court of Iowa, 1999)
Concrete Materials Corp. v. Bank of Danville & Trust Co.
938 S.W.2d 254 (Kentucky Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
839 S.W.2d 274, 1992 Ky. LEXIS 149, 1992 WL 298078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/middletown-engineering-co-v-main-street-realty-inc-ky-1992.