Rene Dry Wall Co. v. Strawberry Hill Associates

438 A.2d 774, 182 Conn. 568, 1980 Conn. LEXIS 1022
CourtSupreme Court of Connecticut
DecidedDecember 23, 1980
StatusPublished
Cited by51 cases

This text of 438 A.2d 774 (Rene Dry Wall Co. v. Strawberry Hill Associates) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rene Dry Wall Co. v. Strawberry Hill Associates, 438 A.2d 774, 182 Conn. 568, 1980 Conn. LEXIS 1022 (Colo. 1980).

Opinion

Peters, J.

This is an action by a subcontractor to foreclose a mechanic’s lien against a landowner whose property was improved by the subcontractor’s work. The plaintiff, Rene Dry Wall Co., Inc., sued the defendant, Strawberry Hill Associates, to recover for work done pursuant to a contract with the defendant’s general contractor, United Construction Ltd. 1 The defendant’s principal defense was that it was excused from obligation to the plaintiff because of good faith payments to the general contractor before notice of the plaintiff’s lien and because of expenditures reasonably incurred to complete the construction project after the general contractor’s default. The trial court found that this special defense had been proved and rendered judgment accordingly. The plaintiff has appealed.

Many of the facts underlying this litigation are no longer in dispute. Strawberry Hill Associates (hereinafter Strawberry Hill), as owner, entered into a written contract on November 1, 1977, with *570 United Construction, Ltd. (hereinafter United Construction), as general contractor, for the construction of a commercial building in Guilford, at a contract price of $411,734. In February of the following year, United Construction hired Rene Dry Wall Co., Inc. (hereinafter Rene Dry Wall) to supply the labor and the materials for the dry wall work for this project at a contract price of $35,050. Rene Dry Wall worked on the job from April to June of 1978. At the time it stopped working, it had virtually completed the job, and was owed $34,050. Strawberry Hill decided, in mid-June, that United Construction was unable to complete the job and, on June 14, 1978, notified United Construction that it was terminated. Thereafter Strawberry Hill itself completed the project by entering into separate contracts with various contractors and subcontractors.

Rene Dry Wall had no direct contact with Strawberry Hill while United Construction was on the job. With respect to Rene Dry Wall’s first bill of April 27, 1978, in the amount of $10,060, Rene Dry Wall executed a partial lien waiver at the request of United Construction and of Strawberry Hill’s attorney. Rene Dry Wall never received this payment or any others, nor did it execute any further lien waivers. The day after Strawberry Hill’s termination of United Construction, on June 15, 1978, Rene Dry Wall served a notice of mechanic’s lien on Strawberry Hill. On June 19,1978, its mechanic’s lien was recorded on the Guilford land records. In late June, Rene Dry Wall, in a meeting with Strawberry Hill, made a direct demand for payment, which was refused.

During the spring of 1978, Strawberry Hill had made various progress payments, less ten percent *571 retainages, to United Construction for work then completed and approved by the architect. Certain of these progress payments, although payable to United Construction, were pre-endorsed by Strawberry Hill to designated subcontractors. At the time of these progress payments, Strawberry Hill had heard rumors that United Construction was delinquent in paying subcontractors and suppliers.

When Strawberry Hill took the project over from United Construction in mid-June of 1978, the work was not complete. Although Strawberry Hill then held retainages of $38,000, it eventually spent $49,311.85 in excess of the contract price to finish the job. Bene Dry Wall does not contest the fact that Strawberry Hill incurred these expenses, but it does challenge their reasonableness.

The legal issues in this case are framed by the statutory provisions governing mechanic’s liens. The two provisions most directly relevant are G-eneral Statutes §§ 49-33 2 and 49-36, 3 which define and *572 delimit the fund to which a properly noticed 4 mechanic’s lien may attach. Both of these sections start with the proposition that no mechanic’s lien may attach to any building or land in an amount greater than the price which the owner has agreed to pay to the general contractor for the building being erected or improved. This amount may be diminished to the extent that it exceeds “the reasonable cost ... of satisfactory completion of the contract plus any damages resulting from . . . default for which [the general contractor] might be held liable to the owner.” General Statutes §49-33. The amount may be diminished further by “bona fide payments, as defined in section 49-36, made by the owner [to the general contractor] before receiving notice of [the mechanic’s] lien or liens.” General *573 Statutes § 49-33. See Seaman v. Climate Control Corporation, 181 Conn. 592, 593-94, 605, 436 A.2d 271 (1980).

These provisions make it clear that a contractor’s right to recover on a mechanic’s lien is not unlimited, despite the contractor’s own good faith observance of the statutes. We have often noted that mechanic’s lien legislation is remedial in nature, designed to furnish security for a contractor’s labor and materials. Camputaro v. Stuart Hardwood Corporation, 180 Conn. 545, 550, 429 A.2d 796 (1980); Stone v. Rosenfield, 141 Conn. 188, 191, 104 A.2d 545 (1954); City Lumber Co. v. Borsuk, 131 Conn. 640, 645, 41 A.2d 775 (1945); Balch v. Chaffee, 73 Conn. 318, 320, 47 A. 327 (1900). Although this understanding of legislative purpose counsels generous construction in favor of the mechanic’s lien, it does not permit us to extend the mechanic’s lien beyond that which is authorized by the statutes. In Camputaro, supra, the contractor could not prevail because his work was not, within the statutes, lienable; here, the contractor’s work is unquestionably lienable but his recovery is nonetheless subject to curtailment because of the conduct of the general contractor. If, as in this case, a general contractor receives progress payments that are not turned over to those who have done the work represented by the progress payments, and ultimately defaults entirely, the owner making such payments and completing such a job is protected as long as the owner acts in good faith and reasonably, as defined by the statutes. In determining whether the owner has met the statutory requirements of good faith and reasonableness, the trial court is making a finding of fact. See Purcell, Inc. v. Libbey, 111 Conn. 132, 139-41, 149 A. 225 (1930).

*574

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strazza Building & Construction, Inc. v. Harris
207 Conn. App. 649 (Connecticut Appellate Court, 2021)
Commissioner of Public Health v. Colandrea
167 A.3d 471 (Connecticut Appellate Court, 2017)
Fernwood Realty, LLC v. Aerocision, LLC.
141 A.3d 965 (Connecticut Appellate Court, 2016)
Neighborhood Assn., Inc. v. Limberger
Supreme Court of Connecticut, 2016
PROBUILD EAST, LLC v. Poffenberger
45 A.3d 654 (Connecticut Appellate Court, 2012)
Intercity Development, LLC v. Andrade
942 A.2d 1028 (Supreme Court of Connecticut, 2008)
Intercity Development, LLC v. Andrade
901 A.2d 731 (Connecticut Appellate Court, 2006)
Angiolillo v. Tradesource, Inc., No. Cv-01-0186513 S (Oct. 1, 2002)
2002 Conn. Super. Ct. 12507 (Connecticut Superior Court, 2002)
Merrill Lynch v. Pac Group, No. Cv 02 0814811 S (Sep. 3, 2002)
2002 Conn. Super. Ct. 11531 (Connecticut Superior Court, 2002)
Connecticut Light Power Co. v. Dpuc, No. Cv-01-0510850s (Jul. 30, 2002)
2002 Conn. Super. Ct. 9663 (Connecticut Superior Court, 2002)
Forestville Lumber v. Quality Insulation, No. Cv00-0500719 (Apr. 9, 2002)
2002 Conn. Super. Ct. 5279 (Connecticut Superior Court, 2002)
Pg Construction v. Park Blue, No. Cv01-0165316s (Jan. 23, 2002)
2002 Conn. Super. Ct. 635 (Connecticut Superior Court, 2002)
Cluff's, Inc. v. Strafaci, No. 552519 (Jan. 23, 2002)
2002 Conn. Super. Ct. 961 (Connecticut Superior Court, 2002)
Kamco Supply v. Maplewood School Apt., No. Cv98 035 22 95 S (Sep. 19, 2001)
2001 Conn. Super. Ct. 13187 (Connecticut Superior Court, 2001)
All-Star Storage-Derby v. James Contract, No. Cv 01 0084961s (Sep. 18, 2001)
2001 Conn. Super. Ct. 13468-cr (Connecticut Superior Court, 2001)
Canino v. Iffland Lumber Company, Inc., No. Cv 01 85202 (Jul. 23, 2001)
2001 Conn. Super. Ct. 9727 (Connecticut Superior Court, 2001)
Connecticut Concrete v. Arc Icesports, No. X01-Cv00-0160662 (Feb. 8, 2001)
2001 Conn. Super. Ct. 2173 (Connecticut Superior Court, 2001)
Peltier v. Stevenson Lumber Company, No. Cv 99 0090651 (Mar. 23, 2000)
2000 Conn. Super. Ct. 3148 (Connecticut Superior Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
438 A.2d 774, 182 Conn. 568, 1980 Conn. LEXIS 1022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rene-dry-wall-co-v-strawberry-hill-associates-conn-1980.