Merrill Lynch v. Pac Group, No. Cv 02 0814811 S (Sep. 3, 2002)

2002 Conn. Super. Ct. 11531, 33 Conn. L. Rptr. 241
CourtConnecticut Superior Court
DecidedSeptember 3, 2002
DocketNo. CV 02 0814811 S, CV 02 0814812 S
StatusUnpublished

This text of 2002 Conn. Super. Ct. 11531 (Merrill Lynch v. Pac Group, No. Cv 02 0814811 S (Sep. 3, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merrill Lynch v. Pac Group, No. Cv 02 0814811 S (Sep. 3, 2002), 2002 Conn. Super. Ct. 11531, 33 Conn. L. Rptr. 241 (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The above encaptioned companion cases have been brought for the purpose of reducing or discharging mechanic's liens pursuant to § 49-35 (a) of the General Statutes. As noted by the parties, most of the underlying facts are not seriously disputed, but the consequences of the facts are most seriously, and impressively professionally,1 contested.

The dispute arises in the context of several contractual relationships. The applicant Northland CityPlace II, LLC ("Northland") is the owner of an office building in downtown Hartford. On January 16, 2001, Northland leased two floors of the building to the applicant Merrill Lynch, Pierce, Fenner Smith, Inc. ("Merrill"). The lease contemplated a tenant build out of the leased premises. Pursuant to § 10-21 of the lease:

To the extent and insofar as there is any work required to prepare the premises for . . . occupancy (herein referred to as "Tenant's Work"), the same shall be performed by Tenant at its sole cost and expense (subject to reimbursement of Landlord's Contribution, as hereinafter defined) in accordance with the terms and provisions of this Lease, including, without limitation, the requirement that Landlord approve Tenant's plans and specifications for Tenant's Work prior to the commencement thereof

And further:

Provided that there shall be no outstanding violation of law or lien affecting the property by reason of Tenant's Work (unless such lien is bonded over by Tenant to Landlord's reasonable satisfaction), and provided that Tenant's Work shall CT Page 11532 not materially deviate from the plans and specifications therefore previously approved by Landlord, Landlord shall contribute up to $988,980.00 (i.e., $30.00 per square foot of rentable area of the Premises) (Landlord's Contribution") towards the leasehold improvements to be constructed by Tenant as part of Tenant's Work (including any necessary demolition work prior thereto) and the unaffiliated third-party design, architectural, engineering and filing fees related thereto.

Merrill Lynch subsequently entered into a Construction Management Agreement with Caswell Corporate Interiors, Inc. ("Caswell"), apparently on May 29, 2001. Although the agreement seems to contemplate a relationship of special trust, for our purposes it establishes Caswell as the general contractor for the Tenant's Work. Caswell hired the respondent PAC Group, LLC ("PAC") to perform much of the Work: the contract and approved change orders totaled more than $2,000,000. PAC ultimately was not paid $167,030.68 of the amount it was owed by Caswell, and it filed mechanic's liens as to Northland and Merrill. Because PAC claims that several payments by Merrill to Caswell were made too soon, and thus not entitled to good faith status sufficient to reduce the "lienable fund"; see § 49-36 (c) of the General Statutes; several of the provisions of the agreement between Merrill and Caswell are significant.

Article 7(B) of the contract provided that by the tenth of each month of the agreement Caswell was to submit to Merrill and to the architect, if required by Merrill, a notarized AIA form showing in detail the money actually paid and the costs incurred during the month for which reimbursement was requested, together with the amount of the contractor's fee for the month, together with payrolls and other data supporting the contractor's right to payment for subcontracts and materials. The contractor was to obtain the approval of the architect and the engineer, and Merrill was not obligated to pay more than the amount approved by the architect and the engineer. Article 7(G) allowed Merrill to withhold any payment to protect itself from loss, if, inter alia, proper documentation was not provided.

Article 7(I) defined "completion", for the purpose of the project, to mean "and be dependent upon final acceptance of the Work by Merrill's Project Manager [Caswell]." Upon acceptance, which required completed punch list work, issuance of all drawings and manuals, and removal of tools, the retainage would be paid. The retainage, or the amount withheld CT Page 11533 from each payment to secure proper completion, was defined in Article 6 (A)(2) to be 10% of each payment.2 Article 7(J) provided that when Merrill received notice that the work was completed, it would inspect the work; if all was acceptable and the appropriate certificates obtained from local authorities, Merrill agreed to issue a signed final certificate indicating that the work had been completed. Prior to Merrill's issuing the final certificate, Caswell was to submit evidence "satisfactory to Merrill that all payrolls, material, bills and other indebtedness connected with the Work have been paid."

Article 7(K) provided that "final payment shall be due" 45 days after the work is fully completed and Merrill has received evidence "satisfactory to Merrill that all payrolls, material bills, and other indebtedness connected with the Work have been paid. . . ." Merrill may nonetheless make a partial payment but withhold such sums as it deems sufficient to protect its interests. Caswell was to deliver to Merrill "upon demand, simultaneously and as a strict condition precedent to final payment, a release in respect to the Work performed and materials furnished by . . . any Subcontractors retained by [Caswell]. . . ."

Merrill's position, it will be foreshadowed, is that many of the provisions in the contract between it and Caswell provide powers to Merrill but do not impose duties, such that Merrill had the ability to require various items of documentation and to condition payment on various factors, but it did not have the obligation to do so. Merrill relies as well on common law authority, most notably Hubbell, Hall andRandall Co. v. Pentecost, 89 Conn. 262 (1915), for the proposition that so long as payment is not made for work not yet done, the owner's payment to the general contractor is not premature for the purpose of determining the amount of the lienable fund available to the unpaid subcontractor. PAC, on the other hand, posits that § 49-36 (c) of the General Statutes clearly states that "[n]o payments made in advance of the time stipulated in the original contract may be considered as made in good faith. . .", and that several of the payments, particularly the last two, were accordingly made prematurely.

With this framework in mind, I turn to the history of payments. PAC's applications for payments from Caswell for the first few months were processed and paid without incident. The final application, dated November 15, 2001, is in the amount of $276,575.49. Caswell did not pay all of the amount, and PAC has been left with $167.030.68 in unpaid bills. There have been no questions raised about the quality of work done by PAC or the amount owed to it by Caswell. No evidence was submitted regarding what happened to Caswell: for whatever reason, it did not pay PAC the full amount owed. CT Page 11534

The history of Merrill's payments to Caswell are critical to the present dispute, however. Again, the first months' payments are not controversial3 and, again, it is not disputed that Merrill did indeed pay Caswell the full amount of its contractual obligation to Caswell. But, because of the operation of § 49-36

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lopinto v. Haines
441 A.2d 151 (Supreme Court of Connecticut, 1981)
Rene Dry Wall Co. v. Strawberry Hill Associates
438 A.2d 774 (Supreme Court of Connecticut, 1980)
Ledgebrook Condominium Assn., Inc. v. Lusk Corporation
376 A.2d 60 (Supreme Court of Connecticut, 1977)
J. Frederick Scholes Agency v. Mitchell
464 A.2d 795 (Supreme Court of Connecticut, 1983)
Avery v. Smith
113 A. 313 (Supreme Court of Connecticut, 1921)
Hubbell, Hall & Randall Co. v. Pentecost
93 A. 672 (Supreme Court of Connecticut, 1915)
Wall v. Toomey
52 Conn. 35 (Supreme Court of Connecticut, 1884)
Hall v. Peacock Fixture & Electric Co.
475 A.2d 1100 (Supreme Court of Connecticut, 1984)
State v. Bonello
554 A.2d 277 (Supreme Court of Connecticut, 1989)
Centerbrook, Architects & Planners v. Laurel Nursing Services, Inc.
620 A.2d 127 (Supreme Court of Connecticut, 1993)
State v. Davis
641 A.2d 370 (Supreme Court of Connecticut, 1994)
Miller v. Commissioner of Correction
700 A.2d 1108 (Supreme Court of Connecticut, 1997)
Newtown Associates v. Northeast Structures, Inc.
546 A.2d 310 (Connecticut Appellate Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 11531, 33 Conn. L. Rptr. 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merrill-lynch-v-pac-group-no-cv-02-0814811-s-sep-3-2002-connsuperct-2002.