CONSTRUCTION KEN-NECTION, INC. v. Cipriano

45 A.3d 663, 136 Conn. App. 546, 2012 WL 2384398, 2012 Conn. App. LEXIS 317
CourtConnecticut Appellate Court
DecidedJuly 3, 2012
DocketAC 31778
StatusPublished
Cited by1 cases

This text of 45 A.3d 663 (CONSTRUCTION KEN-NECTION, INC. v. Cipriano) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CONSTRUCTION KEN-NECTION, INC. v. Cipriano, 45 A.3d 663, 136 Conn. App. 546, 2012 WL 2384398, 2012 Conn. App. LEXIS 317 (Colo. Ct. App. 2012).

Opinion

*548 Opinion

BEACH, J.

The plaintiff, Construction Ken-nection, Inc., 1 appeals from the judgment of the trial court concluding that the mechanic’s lien it filed in connection with a residential construction project for the defendants Dianne Cipriano and Joseph Cipriano (collectively, Ciprianos) was invalid and, accordingly, dismissing the plaintiffs action to foreclose its mechanic’s hen, which the plaintiff claims is prior in right to the construction mortgage held by the defendant Nauga-tuck Valley Savings and Loan. 2 On appeal, the plaintiff challenges as clearly erroneous the factual findings of the court that the Ciprianos did not knowingly consent to the expanded work done or proposed by the plaintiff, that certain work that was purportedly done was not within the contract, that the filing of the hen was beyond the ninety day statutory limitation, and that the plaintiff failed to estabhsh probable cause that any amounts claimed were within the terms of the contract, verbal amendments or change orders. Because the court’s findings were not clearly erroneous, we affirm the judgment of the trial court.

The following facts, as found by the court and as gleaned from the record, and procedural history are relevant to our resolution of the plaintiffs appeal. On *549 January 6, 2005, the plaintiff and the Ciprianos entered into a written contract providing that the plaintiff would construct a log home in Harwinton for $155,000, excluding site work such as foundation excavation and septic system installation. The contract provided: “Any alterations or deviations from the above scope of work involving extra costs, will be executed only upon written orders, and will become an extra charge [over] and above the estimate.” After the contract was signed, the Ciprianos had a septic system installed at a cost of $30,000. Subsequently, in or around early February, 2005, the parties learned that, in order to obtain a building permit to build the house, a new driveway would have to be constructed on the lot. The parties then modified and extended their contract by oral agreement that the plaintiff would perform site work, including building the driveway, at a cost of $45,000 to $50,000. It is undisputed that there were no change orders executed in writing.

On or about January 18, 2006, the Ciprianos obtained a construction loan secured by a mortgage from Nauga-tuck Valley Savings and Loan in the amount of $240,000 in order to finance both the cost of the original contract and the cost of the site work. 3 Without informing the Ciprianos, Kenneth Beaudoin, co-owner of the plaintiff, estimated in January, 2006, that the total work would cost approximately $283,000, which apparently included the original contract amount of $155,000, plus the amounts agreed on for site work, as well as estimates for additional work that he believed the project *550 required, but that went beyond the scope of the parties’ initial contract and subsequent oral agreement. Beau-doin did not provide a written estimate of this total to the Ciprianos until May, 2006. The plaintiff had commenced work on November 19, 2005, and, pursuant to invoices issued by the plaintiff, the Ciprianos had made periodic payments on January 20, 2006, January 25, 2006, May 23, 2006, and July 20, 2006. The court found: “The [Ciprianos] were not fully aware of all the changes that went beyond the scope of the initial contract and the costs associated therewith.”

On August 3, 2006, the plaintiff requested a payment of $44,325. The Ciprianos informed the plaintiff that they could no longer afford to continue paying for the construction of their log home. The funding on behalf of the Ciprianos from Naugatuck Valley Savings and Loan was suspended pursuant to bank guidelines because an insufficient amount of work had been performed since the previous construction loan draw request. The last invoice that the plaintiff sent to the Ciprianos reflected an outstanding balance of $63,303, due on August 29, 2006. The plaintiff filed a mechanic’s lien in that amount 4 on December 14, 2006. 5 In October, 2007, the plaintiff commenced an action to foreclose the mechanic’s hen, and the court rendered judgment in favor of the Ciprianos on December 2, 2009. 6 Both the plaintiff and Naugatuck Valley Savings and Loan *551 moved for an articulation, and the court subsequently issued a supplemental memorandum of decision on March 4, 2010. In that decision, the court set forth the parties’ respective positions as follows: “The [Cipri-anos’] position is that by August 3, 2006, 7 substantial performance on the subject residence had [been] completed. The plaintiffs position is that additional work [namely, dormer siding work] was done on the residence on or about September 21,2006, which brings the mechanic’s hen filing within the ninety-day perimeter of General Statutes § 49-34. 8 The [Ciprianos] raised various special defenses to the December 14, 2006 mechanic’s hen, which include: the untimely filing of the hen; that certain work and billings were beyond the written or oral agreements; and that [they] did not consent to some of the work.”

The court made the following findings of fact, which were, in their entirety:

“1. The [Ciprianos] did not knowingly consent to the expanded work done or proposed by the plaintiff, nor did they agree to the costs associated with such work.
“2. The work that was purportedly done by the plaintiff on September 21 and/or September 22, 2006, was *552 not within the contract, nor was the work ‘ongoing’ at that time. Moreover, even if that work was within the contract, it was done after an approximately one and one-half month delay. As a result, those dates do not represent the last day of substantial completion within the terms of the written or oral contract.
“3. The ninety-day period for lien filing purposes commenced on August 3, 2006, the last day on which agreed upon services or materials were furnished, thus representing the date of substantial completion. Therefore, the December 14,2006 lien filing was beyond the ninety-day statutory limitation.
“4. The plaintiff failed to establish probable cause that the amount ‘justly due’ and owing to the plaintiff was within [the] terms of the contract or any verbal amendments to the said contract and/or change orders to the underlying base contract.”

On appeal, the plaintiff challenges each of these factual findings as clearly erroneous. 9 We conclude that the plaintiffs arguments lack merit.

We first set forth the applicable standard of review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
45 A.3d 663, 136 Conn. App. 546, 2012 WL 2384398, 2012 Conn. App. LEXIS 317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-ken-nection-inc-v-cipriano-connappct-2012.