International Building Supply, LLC f/k/a International Supply, LLC, et al. v. Hudson Meridian Construction Group, LLC

CourtDistrict Court, D. Connecticut
DecidedNovember 6, 2025
Docket3:22-cv-01167
StatusUnknown

This text of International Building Supply, LLC f/k/a International Supply, LLC, et al. v. Hudson Meridian Construction Group, LLC (International Building Supply, LLC f/k/a International Supply, LLC, et al. v. Hudson Meridian Construction Group, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Building Supply, LLC f/k/a International Supply, LLC, et al. v. Hudson Meridian Construction Group, LLC, (D. Conn. 2025).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF CONNECTICUT

International Building Supply, LLC f/k/a International Supply, LLC, et al., Civil No. 3:22-cv-01167 (TOF) Plaintiffs,

v. November 6, 2025 Hudson Meridian Construction Group, LLC,

Defendant.

MEMORANDUM OF DECISION This case arises out of a construction industry dispute. The Plaintiffs are two affiliated companies, International Building Supply, LLC f/k/a International Supply, LLC (“Supply”) and International Framers, LLC (“Framers” and, together with Supply, “Plaintiffs”). The Defendant is Hudson Meridian Construction Group, LLC (“Hudson”). The Plaintiffs filed a five-count complaint against Hudson in September of 2022, alleging breach of contract, promissory estoppel, breach of the implied covenant of good faith and fair dealing, and violations of the Connecticut Unfair Trade Practices Act (“CUTPA”). (Compl., ECF No. 1.) The Court granted summary judgment on the implied covenant and CUTPA claims on June 21, 2025. (Ruling and Order on Def.’s Mot. for Summ. J., ECF No. 98.) The parties then tried the remaining three counts to the Court over three days in August. (See Minute Entries, ECF Nos. 112-14.) The Court has carefully considered the witnesses’ testimony, the documentary exhibits, the parties’ stipulations of fact, and the post-hearing briefs that the parties submitted in September. For the reasons set forth below, the Court will rule for Hudson on all three remaining counts of the Plaintiffs’ operative complaint. I. PROCEDURAL POSTURE The Court begins by setting forth the relevant procedural history of the case. The Plaintiffs filed their initial complaint on September 15, 2022. (Compl., ECF No. 1.) They alleged that Hudson made, and later breached, two contracts with respect to a residential real estate

development project at 201 Munson Street and 23 Shelton Avenue in New Haven, Connecticut (the “Project”). (See id.) Specifically, they claimed that Hudson had agreed to buy wood framing materials for the Project from Supply, and to procure the installation labor from Framers, in two letters of intent dated February 8, 2022. (Id. Counts One and Three.) They alleged that these letters of intent were binding contracts, which Hudson breached when it purported to rescind them in June of 2022. (Id.) The Plaintiffs’ five-count complaint alleged breach of the Supply contract in Count One, promissory estoppel as to Supply in Count Two, breach of the Framers contract in Count Three, breach of the covenant of good faith and fair dealing in Count Four, and violations of CUTPA in Count Five. (Id. Counts One through Five.) The Clerk of the Court initially assigned the case to the Honorable Omar A. Williams.

Hudson appeared through counsel on October 13, 2022. (ECF Nos. 9, 10.) On November 17, 2022, it moved to dismiss the entire complaint for failure to state a claim upon which relief could be granted. (Mot. to Dismiss, ECF No. 16.) After full briefing (ECF Nos. 16, 25, 28), Judge Williams denied Hudson’s motion in a fifteen-page ruling dated February 21, 2024. (Ruling on Def.’s Mot. to Dismiss, ECF No. 33); Int’l Supply, LLC v. Hudson Meridian Constr. Grp., LLC (“Int’l Supply I”), No. 3:22-cv-1167 (OAW), 2024 WL 707014 (D. Conn. Feb. 21, 2024). Hudson then answered the complaint on March 6, 2024. (ECF No. 37.) On April 17, 2024, the parties “consent[ed] to have a United States magistrate judge conduct all proceedings in this case including trial, the entry of final judgment, and all post-trial proceedings.” (Notice, ECF No. 43.) Judge Williams transferred the case to the undersigned the next day. (Reference Order, ECF No. 44.) On December 31, 2024, the Plaintiffs moved for leave to amend their complaint with Hudson’s consent. (Am. Compl., ECF No. 70.) The motion was evidently prompted by a change

in Supply’s legal name (id. ¶ 24), but the proposed amended complaint also added some factual allegations to the then-existing five-count framework, and it withdrew the jury demand that had been made in the original complaint. (Id. at pp. 6, 10.) The Court granted leave to amend, making the Amended Complaint the operative pleading. (ECF No. 71.) A few days later, the Plaintiffs sought to reinstate their jury demand by way of a proposed Second Amended Complaint. (See Mot. to File 2d Am. Compl., ECF No. 74.) A brief dispute then ensued over whether they could properly do so under Rule 39. (See Def.’s Obj., ECF No. 80.) Ultimately, however, the Plaintiffs concluded that they wanted a bench trial after all (Br. Stmt. Re: Trial Preference, ECF No. 92), mooting their request to file a second amendment. (ECF No. 93.) Hudson answered the Amended Complaint on March 4, 2025 (ECF No. 94), and the

pleadings closed. The parties completed discovery, and Hudson moved for summary judgment on all five counts. (Mot. for Summ. J., ECF No. 82.) The Plaintiffs filed an objection to Hudson’s motion (Obj., ECF No. 95), and Hudson filed a reply. (Reply, ECF No. 96.) The parties argued the motion on April 17, 2025. (ECF No. 97.) On June 21, 2025, the Court issued a forty-page ruling denying the motion as to the contract breach and promissory estoppel claims in Counts One through Three, but granting it as to the implied covenant and CUTPA claims in Counts Four and Five. (Ruling and Order on Def.’s Mot. for Summ. J., ECF No. 98); Int’l Bldg. Supply, LLC v. Hudson Meridian Constr. Grp. (“Int’l Supply II”), No. 3:22-cv-1167 (TOF), 2025 WL 1726365 (D. Conn. June 21, 2025). The parties then filed their Joint Trial Memorandum on July 16, 2025. (Joint Trial Memo., ECF No. 105.) In their memorandum, they stipulated to sixteen facts about themselves, their

employees, and the Project. (Id. at 13-14) (hereinafter “Stipulation”). On Friday, August 1, 2025, the Court ruled upon the motions in limine that had been filed contemporaneously with the Joint Trial Memorandum. (Order, ECF No. 109.) Trial began the following Monday, August 4, 2025. (Minute Entry, ECF No. 112.) At the trial, the Plaintiffs presented testimony from seven witnesses: (1) Daniel Soares, their vice president of finance and operations; (2) Kristopher Backman, their director of manufacturing; (3) Anthony Gallagher, their owner; (4) Daniel Hooker, Hudson’s senior project manager and vice president; (5) Kyle Little, the chief operating officer of one of their vendors, Sherwood Lumber; (6) Chris Schultz, a salesperson for National Lumber, a supplier-turned- competitor; and (7) Patrick Harkin, one of their construction estimators. (Trial Transcript, ECF

Nos. 120-22) (hereinafter “Tr.”). The Plaintiffs also submitted thirty-nine documentary exhibits into evidence. (ECF No. 110; see also Pls.’ Ex. List, ECF No. 115.) For its part, Hudson presented testimony from two witnesses: (1) Walter Haass, its senior vice president of risk management, and (2) Steven Calicchio, its senior vice president and director of operations. (Tr. 343-435.) Hudson also introduced seventeen documentary exhibits. (Def.’s Ex. List, ECF No. 117.) At the close of evidence on Wednesday, August 6, 2025, counsel agreed that in performing its fact- finding function, the Court could consider any of the fifty-six admitted exhibits even if they had not been referenced in the witnesses’ testimony. (Tr. 436:6-11.) After both parties rested, their counsel asked for leave to submit post-trial briefs. (Tr. 437:25-438:3.) The Court granted leave (Order, ECF No. 119), and the parties filed their briefs on September 8, 2025. (Pls.’ Post Trial Memo., ECF No. 124; Def.’s Post-Trial Br., ECF No. 123.) The case is now ripe for decision.

II. FINDINGS OF FACT Rule 52(a) of the Federal Rules of Civil Procedure provides that, “[i]n an action tried on the facts without a jury or with an advisory jury, the court must find the facts specially[.]” Fed. R. Civ. P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
3com Corporation v. Banco Do Brasil, S.A.
171 F.3d 739 (Second Circuit, 1999)
Krist v. Kolombos Rest. Inc.
688 F.3d 89 (Second Circuit, 2012)
Pace v. Sagebrush Sales Co.
560 P.2d 789 (Arizona Supreme Court, 1977)
Murphy v. Spelts-Schultz Lumber Co.
481 N.W.2d 422 (Nebraska Supreme Court, 1992)
Durable, Inc. v. Twin County Grocers Corp.
839 F. Supp. 257 (S.D. New York, 1993)
Omega Engineering, Inc. v. Eastman Kodak Co.
908 F. Supp. 1084 (D. Connecticut, 1995)
Hawkins Construction Co. v. Reiman Corp.
511 N.W.2d 113 (Nebraska Supreme Court, 1994)
Hudson v. Town & Country True Value Hardware, Inc.
666 S.W.2d 51 (Tennessee Supreme Court, 1984)
Auto Glass Express, Inc. v. Hanover Insurance
975 A.2d 1266 (Supreme Court of Connecticut, 2009)
Bayer v. Showmotion, Inc.
973 A.2d 1229 (Supreme Court of Connecticut, 2009)
Bazak International Corp. v. Tarrant Apparel Group
378 F. Supp. 2d 377 (S.D. New York, 2005)
Stein v. Gelfand
476 F. Supp. 2d 427 (S.D. New York, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
International Building Supply, LLC f/k/a International Supply, LLC, et al. v. Hudson Meridian Construction Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-building-supply-llc-fka-international-supply-llc-et-al-ctd-2025.