International Supply, LLC v. Hudson Meridian Construction Group, LLC

CourtDistrict Court, D. Connecticut
DecidedJune 21, 2025
Docket3:22-cv-01167
StatusUnknown

This text of International Supply, LLC v. Hudson Meridian Construction Group, LLC (International Supply, LLC v. Hudson Meridian Construction Group, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Supply, LLC v. Hudson Meridian Construction Group, LLC, (D. Conn. 2025).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF CONNECTICUT

International Building Supply, LLC f/k/a International Supply, LLC, et al., Civil No. 3:22-cv-01167 (TOF) Plaintiffs,

v. June 21, 2025 Hudson Meridian Construction Group, LLC,

Defendant.

RULING AND ORDER ON DEFENDANTS' MOTION FOR SUMMARY JUDGMENT I. INTRODUCTION This case is a construction industry dispute between two plaintiffs, International Building Supply, LLC, f/k/a International Supply LLC (“Supply”) and International Framers, LLC (“Framers” and, together with Supply, “Plaintiffs”), and one defendant, Hudson Meridian Construction Group, LLC (“Hudson”). The Plaintiffs allege that Hudson engaged them to supply and install the wood framing in a housing development in New Haven. (Am. Compl., ECF No. 70, Count One ¶ 40, Count Three ¶ 40.) Hudson prepared two Letters of Intent (“LOIs”), which the Plaintiffs characterize as binding contracts but Hudson regards as non-binding. (Compare Pls.’ Opp’n to Mot. for Summ. J., ECF No. 95, at 10-11 (“Opp’n”) with Def.’s Memo. of L. in Supp. of Mot. for Summ. J., ECF No. 82-17, at 7-10 (“Memo.”).) Hudson later “rescind[ed] and terminat[ed]” the LOIs (Ex. 13 to Memo., ECF No. 82-14), and this lawsuit ensued. The Plaintiffs’ suit is in five counts. (See generally Am. Compl., ECF No. 70.) In Count One, Supply alleges that the first of the two LOIs – the one for supplying the wood framing components – was an enforceable contract that Hudson breached with its rescission letter. (Id. at 7.) In Count Two, Supply alleges that Hudson is also liable in promissory estoppel. (Id.) In Count Three, Framers asserts that the second LOI – the one for installing the framing – was likewise an enforceable contract that Hudson breached with its repudiation. (Id. at 8.) And in Counts Four

and Five, both Plaintiffs allege that Hudson breached the implied covenant of good faith and fair dealing and violated the Connecticut Unfair Trade Practices Act (“CUTPA”) by its conduct. (Id. at 8-9.) Hudson has now moved for summary judgment on all counts. (Def.’s Mot. for Summ. J., ECF No. 82 (“Motion”).) First, it says that the two contract breach claims must fail because “[t]here is no question of law or fact” that the LOIs were not contracts. (Memo. at 9.) Next, it says that the promissory estoppel claim must fail because it is premised on a factual assertion that is “literally impossible” to be true. (Id. at 3, 11.) Finally, it argues that the implied covenant and CUTPA claims must fail because they require not only an enforceable contract, but also a breach of that contract arising out of “some interested or sinister motive” or “unfair” or “deceptive”

practice, all of which it denies. (Id. at 12-14.) The Plaintiffs oppose Hudson’s motion, arguing that all five claims are subject to genuine factual dispute if not entirely erroneous, making summary judgment inappropriate. (See generally Opp’n.) For the reasons set forth below, the Court agrees with the Plaintiffs that genuine disputes of material fact preclude summary judgment on the contract breach and promissory estoppel counts. But it agrees with Hudson that no such disputes have been presented on the implied covenant and CUTPA counts. Hudson’s motion will therefore be granted in part and denied in part. Counts Four and Five will be dismissed, but the case will proceed to trial on Counts One through Three. II. FACTUAL BACKGROUND Supply and Framers are two construction companies located in Naugatuck, Connecticut. (Am. Compl., ECF No. 70, at 1.) Anthony Gallagher is the sole member and manager of both companies (Decl. of A. Gallagher, ECF No. 95-3, ¶ 1), and Daniel Soares serves as their Vice

President of Finance and Operations. (Decl. of D. Soares, ECF No. 95-2, ¶ 1.) Kris Backman works for Supply as an estimator. (Decl. of K. Backman, ECF No. 95-4, ¶ 1.) Hudson is a construction company with an office in White Plains, New York. (Am. Compl., ECF No. 70, at 1.) Daniel Hooker is the company’s Senior Project Manager and Vice President. (Decl. of D. Hooker, ECF No. 82-16, ¶ 2.) Steven Calicchio is its Vice President and Project Executive . (Dep. Tr. of S. Calicchio, ECF No. 82-3, at 1.) This case involves a dispute over a construction project at 201 Munson Street in New Haven, Connecticut (the “Project”). (L.R. 56(a)2(i) Stmt., ¶ 2.) Hudson was the general contractor. (Id. ¶ 3.) In early 2022, “[t]he parties engaged in negotiations for [Supply] to provide the framing materials for the Project, and for [Framers] to provide labor for the framing work.”

(Id. ¶ 4.) Supply says that it initially proposed “turnkey” prices of between $9,000,000 and $10,000,000, but Hudson rejected those bids as too high, and “advised that the supply bid had to come in at under $7,000,000.” (Decl. of D. Soares, ECF No. 95-2, ¶¶ 11-13.) According to Supply, it responded by making two non-turnkey bids dated January 31, 2022 and February 2, 2022, in which it proposed to provide the lumber, floor trusses, and hardware for the Project for a total of $6,921,774. (Id. ¶¶ 16, 17; see also Exs. 1 & 3 to Opp’n, ECF Nos. 95-5, 95-7.) The parties met at Hudson’s White Plains office on the morning of February 8, 2022. (Decl. of D. Soares, ECF No. 95-2, ¶ 18.) Messrs. Gallagher, Soares, and Backman attended for the Plaintiffs, and Messrs. Hooker and Calicchio attended for Hudson. (Id.) The parties disagree on what happened at the meeting, and on much of what happened afterward. Mr. Soares says that Hudson and Supply “agreed . . . that the amount of the supply contract price would be $6,911,000, with a $150,000 credit for hardware and a $100,000 allowance for value engineering[.]” (Id. ¶ 22.) He adds that Hudson and Framers “agreed . . . that the framing contract price would be

$3,230,000.” (Id.) According to Mr. Soares, “Mr. Hooker advised us that both International Supply and Framers had been awarded the contracts for supply and labor and he promised us that LOIs would be issued to us that day,” and he further “told us to lock in our lumber pricing with our lumber supplier so that we would not be subject to the risk of the lumber prices rising the next day[.]” (Id. ¶¶ 23, 24.) As will be shown below, Hudson disagrees that any binding commitments were made at the meeting. After the meeting, two significant events happened within minutes of each other. First, Mr. Soares returned to his Naugatuck office and emailed a letter of intent to Supply’s own lumber supplier, Sherwood Lumber. (Id. ¶ 27; see also Ex. 4 to Opp’n, ECF No. 95-8.) Second, Mr. Hooker emailed two LOIs to the Plaintiffs – one to Supply for “the Furnish of Framing

Material/Trusses/Hardware/Building Wrap” for the Project (the “Supply LOI”), and one to Framers for “Labor for Framing/Material/Trusses/Hardware/Building Wrap” (the “Framers LOI”). (Exs. 5 and 6 to Opp’n, ECF Nos. 95-10, 95-11.) The parties once disputed the order in which these events occurred, but they apparently now agree that Mr. Soares’ LOI to Sherwood Lumber preceded Mr. Hooker’s LOIs to the Plaintiffs by fourteen minutes. (L.R. 56(a)2(i) Stmt. ¶ 7 (Plaintiffs’ admission “that Hudson Meridian emailed two LOIs at 5:08 p.m., which is 14 minutes after International Supply emailed its LOI to Sherwood Lumber”).) The sequence of events will be particularly relevant to the promissory estoppel claim, as will be discussed below. Both LOIs were labeled “Letter of Intent” in bold, capital letters at the top of the document. (Exs. 5 and 6 to Opp’n, ECF Nos. 95-10, 95-11.) The Supply LOI “confirm[ed Hudson’s] intent to enter into a Contract with [Supply] for . . . the Contract Price of . . . $6,911,000.00.” (Ex. 5 to Opp’n, ECF No. 95-10.) The Framers LOI likewise “confirm[ed Hudson’s] intent to enter into a

Contract with [Framers] for . . . the Contract Price of . . . $3,230,000.00.” (Ex. 6 to Opp’n, ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyman v. CSX Transportation, Inc.
364 F. App'x 699 (Second Circuit, 2010)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Kokkonen v. Guardian Life Insurance Co. of America
511 U.S. 375 (Supreme Court, 1994)
Waldner v. Carr
618 F.3d 838 (Eighth Circuit, 2010)
Hermine Hanlin v. Marvin M. Mitchelson
794 F.2d 834 (Second Circuit, 1986)
Bruce C. Shrader v. Csx Transportation, Inc.
70 F.3d 255 (Second Circuit, 1995)
Shelley Weinstock v. Columbia University
224 F.3d 33 (Second Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
International Supply, LLC v. Hudson Meridian Construction Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-supply-llc-v-hudson-meridian-construction-group-llc-ctd-2025.