Cianci v. ORIGINALWERKS, LLC

16 A.3d 705, 126 Conn. App. 18, 2011 Conn. App. LEXIS 523
CourtConnecticut Appellate Court
DecidedJanuary 11, 2011
DocketAC 30957
StatusPublished
Cited by2 cases

This text of 16 A.3d 705 (Cianci v. ORIGINALWERKS, LLC) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cianci v. ORIGINALWERKS, LLC, 16 A.3d 705, 126 Conn. App. 18, 2011 Conn. App. LEXIS 523 (Colo. Ct. App. 2011).

Opinion

Opinion

LAVINE, J.

The plaintiff, Pamela Cianci, appeals from the judgment of the trial court denying her application to discharge a mechanic’s lien recorded on her property by the defendant, Originalwerks, LLC. On appeal, the plaintiff claims that the trial court (1) misapplied the law in determining the amount of debt claimed by the defendant and (2) improperly concluded that the defendant filed its lien in a timely manner pursuant to General Statutes § 49-34. 1 We affirm the judgment of the trial court.

The following facts and procedural history are relevant to this appeal. On or about October 20, 2007, the plaintiff and the defendant entered into a contract, valued at $1,776,896, for the construction of a new house. The defendant began its duties on the property with the demolition of the plaintiffs then existing house and site work in preparation for the new construction.

The defendant continued working on the property until July 15,2008, when the plaintiff told the defendant to cease all activity and to vacate the property because of concerns the plaintiff had with the work being done. The plaintiff also hired a consulting company to review the work completed by the defendant and received a *20 report identifying the major problems. Robert Paltauf, the owner of the defendant company, subsequently e-mailed the plaintiff to notify her that he had been advised by his attorney not to continue construction on her property until the plaintiff identified the claimed problems and discussed them with him.

On September 19, 2008, the plaintiffs attorney provided the defendant’s attorney with a list of the identified deficiencies concerning the work performed on the plaintiffs property and requested that the defendant notify the plaintiff when corrections would be made. 2 In response to the plaintiffs report, on September 23, 2008, Paltauf returned to the property to meet with the supplier and the architect of the house, Doug MacMil-lan. In order to verify the deficiencies listed in the plaintiffs report, Paltauf removed plywood from the house to examine some of the beams and then replaced the plywood once he had completed the inspection. Paltauf also removed some tools from the property, which he had left there when he ceased work in July.

Upon completion of the examination of the property, Paltauf prepared and delivered to the plaintiff a report responding to the plaintiffs report detailing the alleged deficiencies. 3 On October 1,2008, after Paltauf delivered this report, the plaintiff terminated the contract she had with the defendant.

Shortly after October 1, 2008, Paltauf returned to the plaintiffs property for a second time. During this trip, Paltauf removed some remaining tools and scaffolding from the premises. To remove the scaffolding, Paltauf unbolted wall brackets and removed planks and roof brackets that were attached to the house.

On October 15, 2008, the defendant recorded a mechanic’s lien on the plaintiffs property in the amount *21 of $151,647, representing the outstanding value of materials and services furnished in connection with construction of the plaintiffs new house, plus attorney’s fees. On November 6, 2008, the plaintiff filed an amended application to discharge the mechanic’s hen.

On December 1 and 15, 2008, the court held eviden-tiary hearings concerning the plaintiffs application to discharge the lien. During these hearings, the plaintiff argued that there was no probable cause to sustain the lien because the amount of money claimed was improper and the lien was not timely filed pursuant to § 49-34, having been filed more than ninety days after the defendant had ceased providing services on the property.

In a memorandum of decision issued on February 20, 2009, the court concluded that there was probable cause to sustain the lien. Concerning the amount of the lien, the court concluded that “[reviewing the evidence cumulatively (including Plaintiff’s Exhibits B, C, D, E and F), 4 the court finds that while there is some evidence to support the plaintiffs position [that the amount of the lien is improper], it does not reach the necessary level of clear and convincing evidence to justify action under General Statutes § 49-35b (b).” 5 Additionally, the court concluded that the defendant filed the lien in a timely manner. Specifically, the court found that the services rendered by the defendant on September 23, 2008, and thereafter, albeit minimal, were done at the plaintiffs request and were not rendered at the defendant’s own initiative to extend the commencement of the ninety day period. Therefore, the court concluded that the lien was timely pursuant to § 49-34. This appeal followed.

*22 I

The plaintiff first claims that the court failed to apply the proper legal standard in determining that there was probable cause to sustain a lien in the amount of $151,647. Specifically, the plaintiff argues that the court improperly relied on evidence concerning the defendant’s lost profits and the total value of the contract. We disagree.

General Statutes § 49-33 (a) provides in relevant part: “If any person has a claim for more than ten dollars for materials furnished or services rendered in the construction, raising, removal or repairs of any building or any of its appurtenances or in the improvement of any lot or in the site development or subdivision of any plot of land, and the claim is by virtue of an agreement with . . . the owner of the land upon which the building is being erected or has been erected or has been moved . . . then the plot of land, is subject to the payment of the claim.” The plaintiff correctly argues that, pursuant to this statute and our case law, a mechanic’s hen provides security for the amount of materials furnished or services rendered, rather than for lost profits or the total contract price. The plaintiff, however, has not established that the court relied on evidence concerning the defendant’s lost profits or the total value of the contract between the parties in evaluating the amount of the hen.

The court found that the defendant filed a hen on the plaintiffs property in the amount of $151,647, and, in doing so, clearly indicated that the hen was for the value of the materials and services furnished by the defendant. We will not disturb the court’s finding unless it is clearly erroneous. See Dreambuilders Construction, Inc. v. Diamond, 121 Conn. App. 554, 562, 997 A.2d 553 (2010). “A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. . . . Because it is the trial court’s function to weigh the evidence and determine credibility, we give great deference to its findings. ... In reviewing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herron v. Daniels
208 Conn. App. 75 (Connecticut Appellate Court, 2021)
Cianci v. Originalwerks, LLC
17 A.3d 1043 (Supreme Court of Connecticut, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
16 A.3d 705, 126 Conn. App. 18, 2011 Conn. App. LEXIS 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cianci-v-originalwerks-llc-connappct-2011.