Meagher v. DIACRI

3 A.3d 120, 123 Conn. App. 707, 2010 Conn. App. LEXIS 407
CourtConnecticut Appellate Court
DecidedSeptember 14, 2010
Docket30651, 31155
StatusPublished
Cited by2 cases

This text of 3 A.3d 120 (Meagher v. DIACRI) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meagher v. DIACRI, 3 A.3d 120, 123 Conn. App. 707, 2010 Conn. App. LEXIS 407 (Colo. Ct. App. 2010).

Opinion

Opinion

PELLEGRINO, J.

These are consolidated appeals arising out of the alleged breach of a home improvement contract. The plaintiffs, Kenneth P. Meagher and Bethilda Meagher, 1 filed a six count complaint alleging breach of contract and a violation of the Connecticut Unfair Trade Practices Act (CUTPA) 2 against the defendant Chrisdon Builders (counts one and two), breach of contract and a violation of CUTPA against the defendants Donna Diacri and Christopher Diacri (counts three and four), a violation of CUTPA against Diacri Builders, Inc. (count five), and requesting the discharge of a mechanic’s lien that Chrisdon Builders had filed against the plaintiffs’ property (count six). In response, the defendants filed a counterclaim 3 in which they alleged that the plaintiffs had breached the home improvement contract by failing to pay for extra work and materials. After a twelve day trial, the court, Shaban, J., on December 8, 2008, rendered judgment in favor of the plaintiffs as to counts one, two, three, four and six of the complaint, and rendered judgment in favor of Diacri Builders, Inc., as to count five. On appeal, *709 in AC 30651 and AC 31155, the defendants claim that the court improperly (1) awarded CUTPA damages to the plaintiffs for the defendants’ alleged failure to comply with the Home Improvement Act (the act), 4 and (2) denied the defendants’ motion to open the judgment and failed to determine the amount due the defendants’ under their counterclaim. We affirm the judgment of the trial court.

The following facts as found by the court, and procedural history as revealed by the record, are relevant to our resolution of the issues on appeal. On October 12, 2004, the plaintiffs entered into a written contract with Chrisdon Builders for renovations and improvements to their home at 261 Wilton Road West in Ridgefield. The parties agreed to a price of $550,000 for the work, which included construction of a new garage with a living area above it and extensive renovations to the existing home, which was built in the 1800s. The contract included a start date of November 15, 2004, and a “time is of the essence” completion date of July 15, 2005. Plans and specifications, as well as payment schedules, were appended and incorporated into the contract by reference. On October 12,2004, the contract was signed and executed by both plaintiffs and Donna Diacri, on behalf of Chrisdon Builders. 5

On the second page of the contract, there was a line for the entry of the contractor’s state license number. The telephone number of Diacri Builders, Inc., rather than a contractor’s registration number, was entered on that line. 6 In soliciting the job from the plaintiffs, *710 either Christopher Diacri or Donna Diacri gave the plaintiffs a business card that contained the name Chris-don Builders but did not include a contractor’s registration number. Also, a “Chrisdon Builders” sign was placed on the plaintiffs’ property during construction, but it did not disclose a contractor’s registration number.

Following execution of the contract, applications were made with the town of Ridgefield for an alteration permit, development application and zoning permit. The alteration permit was issued on November 30, 2004, and listed the contractor as “Diacri/Chrisdon Builders, I.” The development application was issued on the same date and listed the contractor as “Diacri/Chrisdon Builders.” The application had been signed by Donna Diacri on November 2, 2004, and referenced “CT license # 550053,” which was the home improvement contractor license number of Diacri Builders, Inc. The zoning permit application was issued by the town on November 15, 2004. In order to commence work on the project, Donna Diacri also submitted an insurance affidavit to the town, indicating that Chrisdon Builders was the entity submitting the information.

Work began on the property on November 30, 2004, and continued through the summer of 2005. By July 15, 2005, the addition to the property had been substantially completed. The garage itself was completed on July 19, 2005. As of that time, work on the existing house was nowhere near finished. In order to allow construction on the house to progress, the plaintiffs and their daughters gradually moved into the extra room above the garage, which they used as their living quarters for the summer.

Following the July 15, 2005 deadline, a significant amount of interior and exterior work remained to be done. At trial, the plaintiffs introduced photographs *711 detailing the extent of the demolition and construction work that had been started but remained to be completed. As of August, 2005, the kitchen, bathroom, parlor, master bedroom, basement and other areas were uninhabitable. The demolition had left a first floor area open and exposed to the basement, which was dangerous, and prevented the plaintiffs’ family from using that area of the first floor. In September, the wood flooring in the kitchen was installed, but treatment of the wood was never completed. The flooring in the master bedroom had not been completed. Some of the roofing, plumbing and exterior painting had yet to be completed. As the court noted in its memorandum of decision, “[d] espite the delay in completion, the plaintiffs continued to work with the defendants toward the common goal of completing the project. At this point in time, the plaintiffs still considered their relationship with the defendants to be a reasonable one.”

With the input and consent of the plaintiffs, work continued through November, 2005. Nonetheless, substantial amounts of work still had not been completed. Insulation to the old part of the house was not approved by the town’s inspector until November 30, 2005, an exterior electrical conduit was not laid until approximately November 18, 2005, and the electric meter was not installed until December 2, 2005, which prevented the power company from turning power on to parts of the house. Moreover, a gas line was not hooked up until approximately December 29, 2005, after twice having failed inspection. As of that date, some of the plumbing was not completed or did not function correctly, several lolly columns in the basement were not as they should have been, loose wires were hanging in several places, and there were no stairs down to the basement. While there were some beams supporting the house, they were not building code compliant.

*712 As of late December, 2005, the house was not close to being in a condition such that a certificate of occupancy could be issued. By that time, the defendants had begun to slow or even stop some of the work on the property, as they had begun work on another job in November. The defendants’ progress became sporadic and unpredictable. In an attempt to keep things moving, the plaintiffs began to pay some of the subcontractors directly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meagher v. DIACRI
10 A.3d 523 (Supreme Court of Connecticut, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
3 A.3d 120, 123 Conn. App. 707, 2010 Conn. App. LEXIS 407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meagher-v-diacri-connappct-2010.