United States ex rel. Global Building Supply, Inc. v. WNH Ltd. Partnership

995 F.2d 515
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 9, 1993
DocketNos. 92-1467, 92-1775
StatusPublished
Cited by7 cases

This text of 995 F.2d 515 (United States ex rel. Global Building Supply, Inc. v. WNH Ltd. Partnership) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Global Building Supply, Inc. v. WNH Ltd. Partnership, 995 F.2d 515 (4th Cir. 1993).

Opinion

OPINION

PHILLIPS, Circuit Judge:

The Miller Act, 40 U.S.C. § 270a et seq., requires persons awarded substantial public works contracts with the United States to post a payment bond protecting some of those supplying the contract’s labor and materials from defaults in payment. In this case we consider whether two materials suppliers victimized by such a default can lay claim to the bond or whether they are too distant from the party contracting with the government to do so. The district court took the latter view, and we affirm its summary judgment rejecting their claims.

[517]*517I

In September of 1989, Thomas P. Harkins, Inc. (Harkins Inc.) contracted with the United States Navy to construct and lease a large apartment complex. Harkins Inc. had been organized in 1965. At the time of contracting, its shareholders were its president, J.P. Blase Cooke, and its chairman, Thomas P. Harkins (Harkins).

Harkins and Cooke later formed another entity to execute the project, WNH Limited Partnership. They installed Harbor Land Company — a corporate shell wholly owned by Harkins — as the general partner and themselves as limited partners. Harbor Land Company held only one percent of the partnership; Harkins and Cooke owned the remainder. On May 10, 1990, WNH assumed Harkins Inc.’s obligations under the lease/construction contract with the Navy pursuant to agreements among WNH, Har-kins Inc., and the United States; Harkins Inc. remained involved in the contract solely as guarantor of performance for WNH.

That same day WNH also contracted with another entity, Harkins Builders, Inc.1 (Builders), to construct the complex, thereby subcontracting a substantial portion of WNH’s total contractual obligation to the Navy. Organized in 1974, Builders is wholly owned by its chairman, Harkins, and its president, Cooke.

A week later WNH posted the payment bond required by the Miller Act, with Federal Insurance Company as surety. Federal had conditioned its agreement to serve as surety on execution of an indemnity agreement by all members of the Harkins Group, which included Harkins Inc., WNH, Builders, and two other corporate entities not otherwise relevant here. Shortly thereafter Builders commenced construction. In late 1990 and early 1991 it retained Today Contractors, Inc. and Toledo Drywall, Inc. to furnish and install drywall on the project. Global Building Supply, Inc., one of the plaintiffs-appellants here, supplied materials to Toledo. Superior Supply Associates, Inc., the other plaintiff-appellant, supplied materials to Toledo and Today.

Neither supplier was paid. Consequently, both sued. Global sought relief against Toledo on the supply contract and also brought a use-suit against Harkins Inc., WNH, Builders, and Federal (as surety) on the Miller Act payment bond; Superior filed a similar claim on amounts owed it by both Toledo and Today. Following submission of stipulated exhibits, memoranda, and oral argument in the Global suit, the district court entered a default judgment for Global on its contract claim against Toledo but also granted summary judgment for Harkins Inc., WNH, Builders, and Federal on the Miller Act claim, holding that Global’s relationship to WNH was of too remote a degree to permit recovery under the Miller Act. Superior agreed to rest on Global’s exhibits and arguments and submitted its case on the briefs. The district court granted summary judgment for Superior on its contract claims against Toledo and Today but once again, and for identical reasons, granted summary judgment for Harkins Inc. and its associates on the Miller Act claim.

Both Global and Superior appealed the grants of summary judgment for Harkins Inc., WNH, Builders, and Federal on the Miller Act payment bond. Global also appealed the. district court’s denial of its own motion for summary judgment on the Miller Act claim, but Superior filed no equivalent motion. We consolidated the two appeals at the request of all parties.

II

A

In reviewing the district court’s decision, we apply the same standard it did, viewing all facts and inferences in the light most favorable to the nonmovant to determine whether summary judgment was appropriately granted. Moore v. Winebrenner, 927 F.2d 1312, 1313 (4th Cir.), cert. denied, — U.S. -, 112 S.Ct. 97, 116 L.Ed.2d 68 (1991). The Miller Act protects those who furnish labor or material for substantial federal public works contracts from defaults in payment by compelling the party [518]*518awarded the government contract (the “contractor”) to post a payment bond against which the suppliers of labor or materials may claim in the event of such a default. 40 U.S.C. § 270a(a)(2), 270b(a). This provides laborers and materialmen on federal projects with a substitute for the common law materi-alman’s lien and its relatives, which can’t attach to federal property.2 J.W. Bateson Co. v. United States ex rel. Board of Trustees, 434 U.S. 586, 589, 98 S.Ct. 873, 875, 55 L.Ed.2d 50 (1978).

The statute doesn’t apply to everyone who supplies labor or materials toward the completion of the federal public works contract, however; it’s limited to those who “deal directly with the prime contractor” and those who “have [a] direct contractual relationship with a subcontractor.”3 Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 894, 88 L.Ed. 1163 (1944). Global and Superior claim no express or implied contractual relationship with the prime contractor in this case; instead, they assert direct relationships with the “subcontractors” Toledo and Today.

Bateson, however, essentially limited statutory “subcontractors” to first-tier subcontractors, i.e. those having direct contractual relations with the prime contractor. 434 U.S. at 594, 98 S.Ct. at 877.4 That means parties other than first-tier subcontractors and those having direct contractual relations with them are too remote to recover under the statute. This poses problems for Global and Superior, because a formal approach to this case would label WNH the prime contractor, Builders the subcontractor, and Toledo and Today second-tier subcontractors. Global and Superior only had contracts with Toledo and Today, so this approach would identify them as third-tier subcontractors, placing the Miller Act payment bond posted by WNH beyond their reach.

Not surprisingly, Global and Superior seek to avoid this harsh result by taking a different tack. They argue for a functional, rather than formal, definition of “prime contractor” that, given the inbred nature of the contractual relationships here and the alleged virtual identity of WNH and Builders, would collapse those two entities into one prime contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
995 F.2d 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-global-building-supply-inc-v-wnh-ltd-partnership-ca4-1993.