United States Ex Rel. O.L.S., Inc. v. Southwind Construction Services, LLC

510 F. App'x 688
CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 7, 2013
Docket12-6132
StatusUnpublished
Cited by1 cases

This text of 510 F. App'x 688 (United States Ex Rel. O.L.S., Inc. v. Southwind Construction Services, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. O.L.S., Inc. v. Southwind Construction Services, LLC, 510 F. App'x 688 (10th Cir. 2013).

Opinion

ORDER AND JUDGMENT *

WADE BRORBY, Senior Circuit Judge.

O.L.S., Inc. (“Ozark”) was a third-tier subcontractor on a federal construction project at Tinker Air Force Base in Oklahoma. When it did not get paid for the equipment it leased to a second-tier subcontractor, Ozark brought an action on the payment bond against the first-tier subcontractor, the prime contractor, and the surety under the Miller Act, 40 U.S.C. §§ 3131, 3133. 1 The district court dismissed the suit for lack of jurisdiction, concluding that because Ozark was a third-tier subcontractor, it was not protected by the bond and could not sue under the Miller Act. Ozark appeals, arguing that the prime contractor and the first-tier subcontractor should be treated as a single, unitary prime contractor, thereby eliminating a tier of the contractual structure and making Ozark a second-tier subcontractor entitled to protection under the bond.

In 2005, Southwind Construction Company, Inc. (“Southwind”) received a multi-year Indefinite Duration, Indefinite Quantity contract from the government known as a SABER contract. Over the course of *690 five years, the government issued multiple delivery orders to Southwind for maintenance, repair, and construction services at Tinker Air Force Base. At issue here is an order issued to Southwind in September 2009 to perform a project known as “Repair RAC FirePond” (“RAC Project”). In connection with this project, Southwind, as principal, and Fidelity & Deposit Company of Maryland (“Fidelity”), as surety, executed a payment bond.

Southwind subcontracted the majority of the work on the RAC Project to South-wind Construction Services, LLC (“Services”), which then subcontracted part of that work to Johnson & Johnson Utility (“Johnson”). Johnson later entered into a contract with Ozark to lease equipment. The RAC Project had significant cost-overruns, and Johnson failed to pay Ozark $22,288.21. Ozark seeks to recover that amount from Southwind’s payment bond.

The Miller Act requires every contractor who is awarded a government construction contract of $100,000 or more to furnish a payment bond “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract for the use of each person.” Id. § 3181(b)(2). The Act defines a “contractor” as “a person awarded a contract ... for the construction, alteration, or repair of any public building or public work of the Federal Government.” Id. § 3131(a), (b). The Act further provides that a person who provides labor or material to the contractor may bring an action on the payment bond, id. § 3133(b)(1), as can “[a] person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond,” id. § 3133(b)(2).

Although the Miller Act defines the term “contractor,” it does not define the term “subcontractor.” The Supreme Court has held that Congress intended to give the term its “technical meaning, as established by usage in the building trades.” Clifford F. MacEvoy Co. v. U.S. ex rel. Calvin Tomkins Co., 322 U.S. 102, 108-109, 64 S.Ct. 890, 88 L.Ed. 1163 (1944). Accordingly, a “subcontractor” is “one who performs for and takes from the prime contractor a specific part of the labor or material requirements of the original contract.” Id. at 109, 64 S.Ct. 890. “[A] contract with the prime contractor is a prerequisite to being a ‘subcontractor.’ ” J.W. Bateson Co. v. U.S. ex rel. Bd. of Trs. of Nat’l Automatic Sprinkler Indus. Pension Fund, 434 U.S. 586, 590, 98 S.Ct. 873, 55 L.Ed.2d 50 (1978).

Looking at the contractual scheme here, Southwind, as the company that had the contract with the government and posted the payment bond, was the prime contractor. Services, as a company who had a contract with Southwind to take from Southwind a part of the labor or material requirements of Southwind’s contract with the government, was a subcontractor (or first-tier subcontractor). And Johnson, which had a direct contract with Services but no contract with Southwind, was a sub-subcontractor (or second-tier subcontractor) entitled to make a claim against the payment bond. See 40 U.S.C. § 3133(b)(2). Ozark, which had no contract with either Southwind or Services, was a third-tier subcontractor and had no right to make a claim against the bond. See Bateson, 434 U.S. at 591-92, 98 S.Ct. 873.

Ozark argues, however, that the court should look at the substance, rather than the form, of the parties’ respective contractual relationships and recognize that although Services was nominally a subcontractor, in reality, it was the de facto prime contractor. Accordingly, Ozark argues, the court should treat Southwind and Ser *691 ■vices as a unitary prime contractor and Johnson as a first-tier subcontractor, which would make Ozark a second-tier subcontractor entitled to protection under the Miller Act. Ozark relies on this court’s decision in Glens Falls Insurance Co. v. Newton Lumber & Manufacturing Co., 388 F.2d 66 (10th Cir.1967), as authority for disregarding the parties’ formal contractual relationships.

In Glens Falls, two third-tier subcontractors sought the protection of the prime contractor’s payment bond by arguing that the nominal first-tier subcontractor, Campbell, was a sham and that the nominal second-tier subcontractor, Whiteside, was the true first-tier subcontractor. Following a bench trial, the district court found that Campbell was a sham; that he permitted DMH, the prime contractor, to use his name in the contract "with Whiteside in order to protect DMH; that DMH did not intend to impose any contractual obligation on Campbell despite its contract with him; that the purpose of executing a contract between DMH and Campbell and then a contract between Campbell and Whiteside was to insulate DMH from liability to Whiteside’s materialmen by making Campbell appear to be the subcontractor; and that Campbell’s true relationship with DMH was that of employee or agent. Id. at 69.

On appeal, this court concluded that the district court “properly regarded substance, rather than form,” in concluding that Whiteside was the true first-tier subcontractor, because “[otherwise, the purpose of the remedial statute, to protect suppliers of materials to the actual subcontractors of the prime contractor, could be defeated by setting up by formal contract a straw man as a subcontractor between the prime contractor and one who in substance and intent is the actual subcontractor.” Id. at 69-70. We therefore affirmed the district court’s judgments against DMH and its surety in favor of the plaintiffs who supplied materials to Whiteside.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Constr. Corp. v. Slone Assocs., Inc.
385 F. Supp. 3d 449 (D. Maryland, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
510 F. App'x 688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-ols-inc-v-southwind-construction-services-llc-ca10-2013.