L. G. Defelice & Son v. Globe Indemnity Co.

189 F. Supp. 455, 1960 U.S. Dist. LEXIS 3216
CourtDistrict Court, S.D. New York
DecidedJuly 20, 1960
StatusPublished
Cited by2 cases

This text of 189 F. Supp. 455 (L. G. Defelice & Son v. Globe Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. G. Defelice & Son v. Globe Indemnity Co., 189 F. Supp. 455, 1960 U.S. Dist. LEXIS 3216 (S.D.N.Y. 1960).

Opinion

THOMAS F. MURPHY, District Judge.

This claim for damages is brought by a general contractor against a joint venture subcontractor and its surety, and has its origins in the construction of part of the New York State Thruway. Jurisdiction is based on diverse citizenship.

Plaintiff entered into a contract with the Thruway Authority and subcontracted part of the work to defendants, a joint venture consisting of A. J. San-taniello, Inc., Clement Anthony Batti-farano and Alfred Emilio Battifarano, co-partners doing business under the firm name and style of Battifarano Trucking Company (hereinafter sometimes called S & B). Under such contract the subcontractor agreed to excavate an estimated 610,600 cubic yards between stations 328 and 373 at 56$ a cubic yard. For the faithful performance and payment of labor and material, etc. S & B gave a surety bond of defendant Globe Indemnity Company.

The complaint has six causes of action. For its first cause of action it claims it expended $179,043.54 to finish excavating 38,977.33 cubic yards left unfinished when the subcontractor S & B quit the job on November 16, 1954. Giving $21,-827.30 credit for such yardage at the contract rate of 56$ a cubic yard and for $65,748.55 retained for work actually performed by the subcontractor it claims a balance of $91,467.69.

The second cause of action is to recover $17,742.38, the amount paid by it to Geo. M. Brewster & Sons, Inc. for equipment rented by the subcontractor. The third cause of action is to recover $2,545.14, the amount paid by it to David Weber & Co. for materials furnished to the subcontractor. The fourth cause of action is to recover $10,295.73, the amount paid by it to Elmhurst Contracting Company, Inc. for equipment furnished to the subcontractor. The fifth cause of action is to recover $10,770, the amount paid by it to Charles P. Allen, agent for Talbott Contracting Corp. for equipment rented by the subcontractor. The sixth cause of action is to recover $60,462.79, the total amount for equipment rented and labor and material supplied to the subcontractor.

The subcontractor at trial interposed three counterclaims. The first counterclaim seeks recovery of $95,159.63 based upon the claimed excavation of 653,471 cubic yards at 56$ a cubic yard ($365,T [457]*457943.76) less $270,784.13, the amount actually paid. The second counterclaim seeks recovery of $160,830.19 for additional expenses in making long hauls to distant “fill” areas because of plaintiff’s breach of contract. The third counterclaim is for $480,906.01 as the fair and reasonable value of extra work, materials and equipment for excavating 469,843 cubic yards of “unsuitable materials.”

The defendant surety denies liability (1) because the claims of plaintiff are not within the intendment of the bond; (2) the payments plaintiff made to the material and equipment companies were voluntary, and (3) that in connection with plaintiff’s claims in causes of action two, three, four and five, § 137 of the New York State Finance Law required lien foreclosure as a condition precedent and that plaintiff failed to foreclose such liens.

Since there is little or no factual dispute concerning plaintiff’s second, third, fourth, fifth and sixth causes of action it is fitting to dispose of them first.

With reference to plaintiff’s second, third, fourth and fifth causes of action it was stipulated that plaintiff made the payments alleged; that the equipment and materials were used on the job site by the subcontractors; that payment of the equipment was guaranteed by plaintiff and that the surety had notice of the claims.

The only factual dispute relates to the Talbott equipment in the fifth of plaintiff’s causes of action. Even as to that there is little in support of the subcontractor’s denial of the rental. At most it is a lapse of memory which is amply controverted. Accordingly, we find as a fact that the subcontractor rented the equipment from Talbott, paid $2,450 on account, used the equipment and failed to pay the balance of $10,700 which plaintiff paid.

The only legal issue is the one raised by the surety and even that requires little discussion. It claims non-liability on these four causes of action on the theory that § 137 of the New York State Finance Law requires the unpaid materialmen and equipment lessors to file liens and then foreclose as a condition precedent for plaintiff to recover. The short answer to this contention is that the bond in question was not a bond required by any law. The obligation that was created by its terms is not a statutory obligation but a common law obligation. The cases of Chittenden Lumber Co. v. Silberblatt & Lasker, Inc., 288 N.Y. 396, 43 N.E.2d 459, and Triple Cities Construction Co. v. Dan-Bar Contracting Co., Inc., 285 App.Div. 299, 136 N.Y.S.2d 459, affirmed 309 N.Y. 665, 128 N.E.2d 318, are not apposite.

The subcontractor agreed to do the work called for in the contract and agreed to pay for material, men, etc. The bond of the surety guaranteed performance of work and furnishing of materials. This promise implies a correlative promise to pay for such work and materials. Seaboard Surety Company v. Standard Accident Insurance Co., 277 N.Y. 429, 14 N.E.2d 778, 117 A.L.R. 658.

The surety’s other objections that such claims are not within the intendment of the bond and that the payments by plaintiff were voluntary are without substance and are rejected.

As to plaintiff’s sixth cause of action its uncontradicted proof showed that for a period of one year while the subcontractor was on the job it furnished materials and labor and rented equipment to the subcontractor of the total value of $60,771.85. It withdrew, however, from the claim the sum of $309.61.

Accordingly, plaintiff is entitled to judgment against both the subcontractor and the surety on the second, third, fourth, fifth and sixth causes of action, together with interest as follows: On the second cause of action for the sum of $17,742.38 with interest on $12,800) from November 3, 1954, and on $4,942.38'. from November 20, 1954; on the third cause of action for the sum of $2,545.14 with interest from November 8, 1954; on the fourth cause of action for the sum of $10,295.73 with interest from [458]*458July 8, 1954; on the fifth cause of action for the sum of $10,770 with interest on $6,600 from August 24, 1954, and on $4,170 from November 20, 1954, and on the sixth cause of action for the sum of $60,462.19 with interest from November 16, 1954.

The principal dispute relates to the work that was performed or not performed by the subcontractor; the work that was performed by plaintiff after the subcontractor left the area; the type of work by each and the cost thereof, together with charges and countercharg-es of breach of contracts and damages flowing from the same.

Although the trial lasted 11 days the necessary voluminous engineering exhibits far exceed in complication the rather one-sided credible testimony. Plaintiff subcontracted part of its contract with the New York State Thruway to defendants S & B. This was an imposing written contract which made specific reference to plaintiff’s general contract, the state’s plans and the state’s 'specifications, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
189 F. Supp. 455, 1960 U.S. Dist. LEXIS 3216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-g-defelice-son-v-globe-indemnity-co-nysd-1960.