Weiss v. Johnson & Johnson Construction Co.

107 S.E.2d 708, 98 Ga. App. 858, 1959 Ga. App. LEXIS 1000
CourtCourt of Appeals of Georgia
DecidedJanuary 9, 1959
Docket37299
StatusPublished
Cited by3 cases

This text of 107 S.E.2d 708 (Weiss v. Johnson & Johnson Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weiss v. Johnson & Johnson Construction Co., 107 S.E.2d 708, 98 Ga. App. 858, 1959 Ga. App. LEXIS 1000 (Ga. Ct. App. 1959).

Opinion

Quillian, Judge.

Counsel for the plaintiff insists that the trial judge erred in not sustaining his demurrer to the amendment and in not sustaining his motion to compel the defendant to pay all accrued costs because the defendant did not attach an affidavit to the amendment .stating that it was not filed for the purpose of delay. The defendant filed an affidavit on the date of the hearing which did not meet all the requirements of Code § 81-1310, but did aver that the amendment was not offered for purposes of delay. Generally it is within the court’s discretion as to whether the amendment will be allowed without the affidavit. Roberson v. Weaver, 145 Ga. 626 (2) (89 S. E. 769); Robinson v. DeVaughn, 59 Ga. App. 37 (200 S. E. 213). The affidavit having supplied the general information that the amendment was not filed for the purpose of delay, the trial court did *866 not abuse its discretion in this case. Moreover, after the affidavit was affixed-to the amendment, no further objection was made to the allowance of the amendment, and hence the objection made before the affidavit was attached to the amendment was waived.

We must decide in disposing of this case, as in every case where the breach of a contract is alleged, whether the instrument which is the basis of the action constituted a valid legal promise for the doing or not doing of a particular thing (Code § 20-101) and whether the defendant’s conduct amounted to a violation of that promise.

In reaching a conclusion as to these matters, consideration must be given to the consideration for the promise, its nature, the circumstances under which it was made, the subject matter with which it dealt and the rules of law under which it is to be construed and enforced.

A similar but by no means identical promise is referred to in Wehle v. Baker, 97 Ga. App. 111 (102 S. E. 2d 661) as a contract of guaranty. In that case the promise was properly catalogued because it was not the acceptance of an order, but an original and unconditional agreement to' pay a specified sum of money from a designated fund. The consideration of the promise was a benefit accruing to the promissor by reason of the promisee making a loan to a third party.

The promise made by the defendant in this case is the acceptance of a non-negotiable order.

The acceptor of such an order agrees to comply with it according to its tenor, and such conditions attached to the acceptance as arise from the nature of the order and the transaction with which it is connected. Mutual Investment Corp. v. Friedman, 83 Ga. App. 544 (64 S. E. 2d 298).

Where the order refers to a contract between the drawer and drawee, it is assumed, in the absence 'of a stipulation to the contrary contained in either the order or the acceptance of the same, that compliance with the order is as a matter of course to be in accord with and under the conditions contained in the contract. Third Nat. Bank of Atlanta v. Western & Atlantic R. Co., 114 Ga. 890 (2) (40 S. E. 1016); Mackin v. Blalock, 133 Ga. 550 (66 S. E. 265).

*867 Thus to the acceptance of a nonnegotiable order the rule stated by slightly varying language in the cases of Citizens Nat. Bank at Brownwood v. Ross Const. Co., 146 Tex. 236 (206 S.W. 2d 593, 595), and Wolters Village Management Company v. Merchants & Planters Nat. Bank of Sherman, 223 F. 2d 793, 801 is applicable. In the former case it is held, as quoted from the reporter system headnote: “If contractor having contracted with United States for erection of naval facilities, promised to make payments on contracts with subcontractor to subcontractor and bank jointly, contractor would not be liable to bank for breach of agreement where promise referred only to payments due to subcontractor under contracts, and balance in contractor’s hands was not payable to subcontractor but to materialman of subcontractor because of default of subcontractor in making payments to materialman. Miller Act, §§ 1, 2, 40' U. S. C. A. §§ 270a, 270b.” Page 593.

“But if it be contended that there is implicit in the wording of the letter, the attendant circumstances, and the subsequent dealings of the parties, a promise on the part of Ross to make the payments jointly, as claimed, still it is to be observed that the letter referred to 'payments to him (Campbell) under these contracts’ and acknowledged that these were the payments which Campbell had instructed Ross to make to himself and the Bank together. Ross made the payments in keeping with Campbell’s instructions until one of the latter’s creditors who had furnished material on the jobs asserted a paramount right to the balance which remained due on the subcontracts. And in fact, Campbell did owe this materialman and could not pay him. Accordingly, Campbell had no further payments (except the $4.46 item) due him, and the balance in the Construction Company’s hands was payable not to Campbell but to the material-man, and was properly so applied. Seaboard Surety Co. v. Standard Accident Ins. Co., 277 N. Y. 429, 14 N. E. 2d 778, 117 A. L. R. 658.” Page 595.

The language of the Wolters case at page 801 is: “The brief of appellant Wolters discusses numerous cases which are claimed to support its position, but most of these are so inapposite to the issues as we view them, having eliminated the assignment theory *868 from our ratio decidendi, that they require no discussion. One case, however, Citizens National Bank at Brownwood v. Ross Const. Co., 146 Tex. 236, 206 S.W. 2d 593, 594, bears some considerable similarity on its facts. There, the prime contractor wrote a letter to the bank, stating that the subcontractor ‘has requested that we give you this letter with instructions that all payments to him under these contracts are to be made payable jointly to Citizens National Bank, Brownwood, and the’ subcontractor. The Bank made the loan and the prime contractor made progress payments by checks made out jointly. The subcontractor breached his contract by failing to pay a materialman, whom the prime contractor then became obligated to pay by reason of a federal statute. The contractor took $10,000 of- the balance owing to the subcontractor and instead of paying it out by joint check as before, satisfied the claim of the materialman. The bank then sued the prime contractor, as in this case. The Texas Supreme Court held (1) that there was no assignment; (2) that there was no promise by the prime contractor to make out the checks jointly, but only a recitation that it had been instructed to do so by the subcontractor; and (3) even if there was such a promise inferred in fact, it was only to make ‘payments . . . under these contracts’, and since the contractor was not obligated under the contracts to> pay this $10,000 to the subcontractor, it had in no event breached its promise. The Bank therefore could not recover.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fulton County v. Morton
396 S.E.2d 65 (Court of Appeals of Georgia, 1990)
Whitfield v. State
154 S.E.2d 294 (Court of Appeals of Georgia, 1967)
Fricks v. Cole
135 S.E.2d 512 (Court of Appeals of Georgia, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
107 S.E.2d 708, 98 Ga. App. 858, 1959 Ga. App. LEXIS 1000, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weiss-v-johnson-johnson-construction-co-gactapp-1959.