Shea v. Sewerage & Water Board

50 So. 166, 124 La. 299, 1909 La. LEXIS 467
Supreme Court of Louisiana·Decided June 30, 1909·No. No. 16,856·Published·Cited by 13 cases

Opinion

PROVO STY, J.

The plaintiff, T. J. Shea, was awarded contracts O -and F of the numerons contracts for the laying of sewers and their appurtenances in the city of New Orleans. He completed contract F, and had constructed the sewers under contract C, and had cleaned the most of them, ready for inspection, when differences arose between him and the defendant board, over the responsibility for failures which had developed in the sewers, which led him to abandon' the contract and bring this suit. He avers that he fulfilled these contracts, and demands $145,483.60, which, he alleges, is the balance due him. The claim is divided into amounts for regular work under the contracts, for extras, and for damages. The claims for extras and damages are itemized in exhibits annexed to the petition.

The defenses are a general denial and the special defenses: that plaintiff was paid all that was due under contract F; that he abandoned contract C incomplete; that there was to his credit at that time on the books of defendant $79,607.28; but that defendant [305] has since then completed the sewers at the expense of plaintiff, as it had. a right to do under the contract, at a cost of $54,-014.92, and has, moreover, expended, in repairing damage caused by plaintiff and in other extra work, as set forth in detail, $1,564.26; that these expenses offset pro tanto the said credit of plaintiff; and that, plaintiff owes, in addition, $41,100, liquidated damages for delay in the completion of said contract, being 411 days at $100 per day, as stipulated in said contract, which more than offsets the balance to the credit of plaintiff, leaving him - indebted to defendant in the sum of $16,318.90, for which defendant prays judgment.

Defendant filed in this court an exception of no cause of action based on the grounds that plaintiff has annexed and made part of his petition the contract upon which his suit is brought, and yet has failed to allege that the work for the price of which he sues has been completed to the satisfaction of defendant’s general superintendent, or that said officer, in withholding his approval, has been actuated by fraud or bad faith, although said contract provides that no payment shall be due until the work contracted for is completed to the satisfaction of said officer; and, also, that plaintiff is asking payment for extra work, and yet has not alleged that such extra work was ordered in writing, although said contract provides that no extra work shall be paid for unless ordered in writing.

It is needless to consider what merit this exception might have had if filed in limine, while the suit stood on the naked petition. 'Perhaps defendant might have then contended that it had the right to withhold payment until plaintiff had shown that he had completed the work to the satisfaction of the engineer, and that.it owed nothing for extra work not shown to have been ordered in writing; but in its answer defendant alleged that it had forbidden plaintiff to go on with the work, and had, itself, completed it at the expense of plaintiff, and that it had done so under and by virtue of clause 265 of the contract. If so, plaintiff certainly has-a cause of action for whatever balance may be left of the money earned by (him under-the contract after deduction of the expense of completing the work. By going into possession of the work, thereby accepting the benefit of it so far as beneficial, defendant most unquestionably incurred liability to the extent of such benefit; that is to say, to the amount due plaintiff for work done after deduction of the expense of completing the work. More than this, the said clause 205' expressly provides that any balance left over after completion of the work must be paid to the contractor. The suit is for this balance. Whether there is one, and how large it is, is the matter in litigation. In other words, the- suit, as it stands on this appeal,, is simply one in settlement of accounts.

So far as the petition not showing a cause of action for failure to allege that the extra work was ordered in writing is concerned,, the answer expressly admits that more than $10,000 is due for extra work, and it intimates that a further admission will in all probability be made later. After such an admission there is not much room for an exception of no cause of action.

Touching the necessity of a written order for these extras, we may say here, once for all, that most of the claims are for damages and repair work, and work necessary for the construction of the sewers, such as plaintiff had no discretion about, but had to do, or else abandon the work of construction. For all such extras no written order can be necessary. If among the extras there are some for which a written order would have been necessary, we are not aware of it. The case was not tried on that line in the lower court, and such claims, if any there are, are [307] not specially noted in the briefs. If any such there be, perhaps written orders could have been produced for them, if called for in the lower court.

The main dispute is over the expense of repairing the failures. Of course, responsibility for these expenses follows responsibility for the failures themselves. Hence we pass at once to that question. Plaintiff can be held responsible for the failures only in so far as they appear to have resulted from fault in his work. In that connection we' will allude to some general features of the case before coming to the details. Even before mentioning these general features, however, it might be well to give a word of explanation touching the manner of constructing the sewers.

Free access — add to your briefcase to read the full text and ask questions with AI

Shea v. Sewerage & Water Board, 50 So. 166, 124 La. 299, 1909 La. LEXIS 467 (La. 1909).

50 So. 166 (Shea v. Sewerage & Water Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Newspaper Production Co. v. Perry
404 So. 2d 1331 (Louisiana Court of Appeal, 1981)
Delta Southern Co. v. Louisiana & Arkansas Railway Co.
394 So. 2d 1299 (Louisiana Court of Appeal, 1981)
Baker v. KELLER CONSTRUCTION CORPORATION
219 So. 2d 569 (Louisiana Court of Appeal, 1969)
Istrouma Mercantile Co. v. Northern Assur, Co., Limited
165 So. 11 (Supreme Court of Louisiana, 1935)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
State v. Cloutier
159 So. 330 (Supreme Court of Louisiana, 1935)
Caulfield v. Yazoo & M. v. R. Co.
127 So. 585 (Supreme Court of Louisiana, 1930)
Hooven v. First Nat. Bank in Ardmore
1928 OK 665 (Supreme Court of Oklahoma, 1928)
Fritz Jahncke, Inc. v. Fidelity & Deposit Co.
117 So. 729 (Supreme Court of Louisiana, 1927)
State v. Christian
107 So. 393 (Supreme Court of Louisiana, 1926)
State v. Perry
90 So. 406 (Supreme Court of Louisiana, 1921)
Reynolds v. Board of Com'rs
71 So. 787 (Supreme Court of Louisiana, 1916)