Reynolds v. Board of Com'rs

71 So. 787, 139 La. 518, 1916 La. LEXIS 1581
CourtSupreme Court of Louisiana
DecidedApril 24, 1916
DocketNo. 20721
StatusPublished
Cited by7 cases

This text of 71 So. 787 (Reynolds v. Board of Com'rs) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reynolds v. Board of Com'rs, 71 So. 787, 139 La. 518, 1916 La. LEXIS 1581 (La. 1916).

Opinion

O’NIELL, J.

The plaintiff, appellee, is the successor to Reynolds & Co., contractors, who built levees for the defendant under four separate contracts. When the work' was completed and accepted by the board of commissioners, the plaintiff demanded compensation for extra work and losses which he claimed had been imposed upon him, amounting to $40,255.08 in excess of the original contracts. The board of levee commissioners referred the claims to its executive committee, who met and adopted a resolution, referring the matter to the board’s attorney, and authorizing him to appoint an expert engineer to examine into the claims and make a report to the board or to the executive committee. It was suggested that Capt. Hardie, a member of the executive committee of the board and city ‘ engineer for New Orleans, pass upon the claims as an expert; but he declined on account of his official position, and suggested that the matter be referred to H. S. Douglas for his expert opinion as an engineer. The minutes of the meeting of the executive committee disclose that the plaintiff was present and expressed his willing[522]*522ness to have the matter settled by an expert examination into his claims, and agreed to pay half of the expense.

It appears that the executive committee of the board approved four of the plaintiff’s bills, agregating $2,385.86, viz.: Bill No. 4, contract No. 2 (for loss of time of the laborers in the plaintiff’s employ getting out of the way of dynamite explosions by another contractor who was employed by the board to remove piling from the river near the new levee), $1,137.50, and force account bill on contract No. 2, $99.01, on contract No. 3, $209.83, and on contract No. 4, $939.52.

Pursuant to the resolution of the executive committee, the attorney for the board referred the remaining claims to the engineer, H. S. Douglas, for his expert opinion. Thereafter the plaintiff abandoned nine of his claims, aggregating $17,148.71, and of the remaining claims Mr. Douglas, in a detailed report to the attorney for the board recommended payment of the following, viz.:

(1) Contract No. 2, bill No. 5, for additional cost of hauling 6,000 cubic yards of earth a greater distance. than was contemplated in the contract, caused by the alleged arbitrary withdrawal of permission to use the batture near the new levee ............................$ 1,500.00
(2) Contract No. 2, bill No. 7, for extra compensation for constructing a levee from the middle of Poland street, that is, from the end of the levee described in the contract, to Kentucky street, the claim- being for the difference- between the contract price of the work described in the contract and the alleged value of the extra work.................. 4,200.00
(3) Contract No. 3, bill No. 1, for the loss of dirt deposited in place by the contractor and lost by the sinking of the foundation (plaintiff claimed $1,687.50), allowed................ 199.99
(4) Contract No. 4, bill No. 1, for earth lost by the sinking of the levee foundation in the vicinity of Eighth street, 2,700 cubic yards at 90 cents 2,430.00
(5) Contract No. 1, bill No. 5....... 2,039.13
(6) Contract No. 2, bill No. 9....... 3,419.55
Total recommended by ' Engineer Douglas for payment............$13,788.67

Mr. Douglas advised that oue of the plaintiff’s bills, referred to as contract No. 2, bill No. 6, amounting to $6,050, be not paid. It is for the loss of 11,000 cubic yards of earth that the plaintiff claims was blown out into the river from the batture in front of the levee between Poland and Mazant streets by the explosions of dynamite used by a contractor employed by the levee board to remove the old piling from the river. The plaintiff contends that it was stipulated in the contract that he might use the batture, and that by the loss of it he was compelled to haul the material a greater distance at an extra cost of 55 cents per cubic yard.

Col. S. E. Lewis, engineer for the levee board, advised the board’s attorney that the claims approved by Mr. Douglas should not be paid, excepting the four bills approved by the executive committee, amounting to $2,385.86. The attorney was of the same opinion, and submitted the matter to the levee board, with the report of Mr. Douglas and with his (the attorney’s) advice that only the four bills approved by the executive committee, amounting to $2,385.86, should be paid. By a resolution of the board the advice and recommendation of the attorney was approved and adopted.

The plaintiff sued for $22,224.53; that is, for the claims approved by the executive committee, amounting to $2,385.86, for those approved by Mr. Douglas, amounting to $13,788.67, and for bill No. 6, contract No. 2, rejected by Mr. Douglas, amounting to $6,050. Thereafter the defendant paid the amount of the four bills approved by the executive committee of the board, $2,385.86, less $250, being half of the fee of the expert, Douglas; and the plaintiff prosecuted his suit for the balance, $19,838.67.

Judgment was rendered in favor of the plaintiff for $14,379.98, with legal interest from judicial demand. The district judge [524]*524did not state in his reasons for judgment what claims were allowed or rejected; but, as the difference between the amount claimed by the plaintiff and the amount of the judgment is $5,458.69, and the sum of the two bills, contract No. 1, bill No. 5, $2,039.13, and contract No. 2, bill No. 9, $3,419.55, amounts to $5,458.68, it is assumed that the district judge rejected these two items, and that the judgment contains an error of one cent in the addition of the remaining items. The defendant has appealed, and, as the plaintiff has neither appealed nor answered the defendant’s appeal, the claims referred to as contract No. 1, bill No. 5, $2,039.13, and contract No. 2, bill No. 9, $3,419.55, are eliminated from the case.

Opinion.

[1] The defendant contends that the ruling of the executive committee was binding upon the parties to the contracts and is not subject to review by the courts, under the following stipulation in each contract, viz.:

“Should differences arise between the contractor and the engineer in charge, the matter shall be submitted to the executive committee of the board, whose decision shall be final and binding upon the parties.”

The plaintiff contends that the foregoing clause refers only to disputes or differences as to matters over which the engineer is given authority within the terms of the contract, and particularly the following provisions, viz.:

“The work shall be done under the direction and supervision of the engineer designated by the board, whose directions shall be complied with, and of such local inspectors as may be appointed by the board of commissioners. He shall have the right to condemn all work not in accordance with the spirit or text of this agreement, or which shall not be in accordance with the dimensions, locations, and methods of construction prescribed by him or provided in these specifications.”

Construing similar clauses in a contract, in the case of Shea v. Sewerage & Water Board, 124 La. 299, 50 South.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Colon v. Wyman
63 Misc. 2d 1053 (New York Supreme Court, 1970)
Bernard Lumber Co. v. John F. Cerise Co.
148 So. 2d 819 (Louisiana Court of Appeal, 1963)
State v. Aucoin
20 So. 2d 136 (Supreme Court of Louisiana, 1944)
Motors Securities Co. v. Tullos
178 So. 634 (Louisiana Court of Appeal, 1938)
Board of Levee Com'rs of Orleans Levee Dist. v. Hulse
120 So. 589 (Supreme Court of Louisiana, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
71 So. 787, 139 La. 518, 1916 La. LEXIS 1581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reynolds-v-board-of-comrs-la-1916.