Kaltoft v. Nielsen

106 N.W.2d 597, 252 Iowa 249, 1960 Iowa Sup. LEXIS 732
CourtSupreme Court of Iowa
DecidedDecember 13, 1960
Docket50098
StatusPublished
Cited by16 cases

This text of 106 N.W.2d 597 (Kaltoft v. Nielsen) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaltoft v. Nielsen, 106 N.W.2d 597, 252 Iowa 249, 1960 Iowa Sup. LEXIS 732 (iowa 1960).

Opinion

Larson, C. J.

Plaintiffs, as contractors, bring this action in equity under chapter 572, Code of 1954, to enforce two mechanics’ liens for material and labor furnished by them in 1956 and 1957 in the construction of a Texaco service station in Harlan, Iowa, under a written contract of July 16, 1956, between them and the defendants Alfred H. Nielsen and Helen Nielsen. Plaintiffs’ liens were for $6356.38 as the balance due *252 on the written contract, and $3051.17 for extras furnished for defendants Alfred H. Nielsen and wife and Texaco, Incorporated.

Defendants’ answer denied any extras were ordered or furnished them except for $120 worth of grading, and by way of counterclaim asked $2100 for a seven-month delay in completion of the structure.

The trial court found that Texaco, Incorporated, had paid into the clerk’s office $941.13 for extras ordered by it under Miscellaneous Bid and Work Contract, Exhibit 5, that with the exception of items of $120 and $8.10 ordered by defendants Nielsen they were not liable for the alterations and extras furnished by plaintiffs, that plaintiffs’ failure to complete the structure within three months was such an unexcused delay as to justify a recoupment by said defendants of $1950, entered judgment for plaintiffs in the sum of $634.48 plus interest and costs, and ordered foreclosure of plaintiffs’ superior lien on the property involved. The matter before us involves only issues between plaintiffs and Alfred H. and Helen Nielsen, so for convenience the Nielsens shall be referred to herein as “defendants.”

Plaintiffs contend the evidence shows that extras were furnished at defendants’ instance and approval, that the delays were occasioned by defendants’ subsequent requirements, by changes in plans and specifications furnished by their lessee, Texaco, Incorporated, and were necessary to satisfy it as a prospective tenant, and by the State Highway Commission’s work on the abutting streets. Furthermore, they claim that under a subsequent oral agreement plaintiffs allowed defendants a $100 credit to cover interest accruing on the Nielsen loan during the delay period.

I. Exhibit 3, executed by both parties, is a sworn construction statement dated June 28, 1957, required by defendant North American Life and Casualty Company to release the balance of its construction loan and, in effect, was an account stated as to all sums due plaintiffs under the contract. It was conceded in argument before us that the execution of that instrument by plaintiffs, showing a balance due them of $6456.38, *253 effectively bars any plaintiff recovery for extras. In addition, we are persuaded that, except for' two small items, no other sums were due plaintiffs at that time, and that plaintiffs had failed to produce any substantial evidence that defendants required or promised to pay for any changes or alterations in the station. We, therefore, conclude that the trial court’s denial of plaintiffs’ claim for extras was correct. The remaining issue involved is that of the responsibility for the delay in completion of the station. The trial court held plaintiffs solely responsible for the delay, but we cannot agree.

II. It is true that plaintiffs have the burden not only to prove the contract declared upon by them, but must also prove by a preponderance of the evidence their contention that the provision in the written contract as to time of completion was complied with, or that that requirement was excused or waived by defendants. If, as plaintiffs contend, such proof was furnished, defendants were not entitled to recoupment of damages for the delay. Lautenbach v. Meredith, 240 Iowa 166, 35 N.W.2d 870, and eases cited.

The question in the case, then, is one of fact as to whether the delay in date of completion under the contract terms was excused or whether the date requirement for completion was waived. As usual in such matters, there appears a wide divergence of testimony. The cause being in equity, it is our duty to consider and determine the matter for ourselves, although the opinion of the trial court on matters involving the veracity of witnesses is very persuasive. Nevertheless, conclusions to be drawn from all the evidence submitted in such matters are for this court alone, and in this case we believe the undisputed facts are significant.

From the record we learn that negotiations between the defendants Nielsens and Texaco, Incorporated, culminated in a written lease January 25, 1956, wherein the Nielsens were to erect a service station on their corner lot in Harlan and lease same to Texaco, Incorporated, for ten years “from and after the date certain improvements hereinafter provided for are completed by the lessor and accepted by the lessee, which date shall be established in writing.” These improvements were to *254 conform to lessee’s requirements and lessee furnished an inspector to oversee the work done.

Plans and specifications for the proposed station were furnished plaintiffs by Texaco, Incorporated, on January 10, 1956, but even before the construction contract with plaintiffs was signed there were discussions as to proposed changes in the plans submitted. It is clear, however, plaintiffs’ bid was based upon the type and kind of material, as well as the amounts required in the original plans and specifications. Negotiations between the plaintiffs and defendants resulted in the execution of a construction contract, Exhibit 4, on July 16, 1956. A form contract provided by the Texaco people permitted no changes in the plans and specifications except on written order of the owner, and provided that the building and improvements shall be “substantially ready for occupancy not later than a reasonable time or date not to exceed three monthsThe italicized words were inserted at the time of execution, and apparently were upon the request of defendants.

Work was started upon the structure immediately after the contract was signed. Very shortly thereafter a series of changes and alterations followed, none of which was upon written order of the owner. On September 21, 1956, a new set of plans and specifications, Exhibit 7, furnished by the Texaco people, was delivered to plaintiffs showing a revised general arrangement and an additional storage tank and suction lines to the pump stand. It was accompanied by a letter to the Nielsens, Exhibit 12, suggesting a continuous approach from State Highway 39, and stating these plans and specifications were to be followed exactly. Thereafter a revised plat plan with additional changes in elevation on the north portion, Exhibit 8, was submitted to plaintiffs. On September 28 and on October 3, 1956, extra foundation walls were installed through the overhead doorways which were not requested by defendants, but were approved by them and the Texaco representative. On October 2 and 3, 1956, improved interior footings were installed to prevent cracked footings and walls. Nielsen was advised it would increase the cost. On October 5, 6 and 8, 1956, more substantial sign bases deemed necessary were installed, with the approval of Nielsen *255 and the Texaco representative, as was extra work on refinishing the banjo signs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Freese
119 B.R. 1019 (N.D. Iowa, 1990)
Zobel & Dahl Construction v. Crotty
356 N.W.2d 42 (Supreme Court of Minnesota, 1984)
Sieg v. CIV. SERV. COM'N OF WEST DES MOINES
342 N.W.2d 824 (Supreme Court of Iowa, 1983)
Sheer Construction, Inc. v. W. Hodgman & Sons, Inc.
326 N.W.2d 328 (Supreme Court of Iowa, 1982)
Capitol City Drywall Corp. v. C. G. Smith Construction Co.
270 N.W.2d 608 (Supreme Court of Iowa, 1978)
Stewart v. Cunningham
548 P.2d 740 (Supreme Court of Kansas, 1976)
Federal Deposit Insurance Corp. v. Farrar
231 N.W.2d 602 (Supreme Court of Iowa, 1975)
Babb's, Inc. v. Babb
169 N.W.2d 211 (Supreme Court of Iowa, 1969)
Grandon v. Ellingson
144 N.W.2d 898 (Supreme Court of Iowa, 1966)
MORRIS PLAN LEASING COMPANY v. Bingham Feed and Grain Co.
143 N.W.2d 404 (Supreme Court of Iowa, 1966)
Central Ready Mix Co. v. John G. Ruhlin Construction Co.
139 N.W.2d 444 (Supreme Court of Iowa, 1966)
Axtell v. Harbert
129 N.W.2d 637 (Supreme Court of Iowa, 1964)
Hardin v. Eska Company
127 N.W.2d 595 (Supreme Court of Iowa, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
106 N.W.2d 597, 252 Iowa 249, 1960 Iowa Sup. LEXIS 732, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaltoft-v-nielsen-iowa-1960.