Central Ready Mix Co. v. John G. Ruhlin Construction Co.

139 N.W.2d 444, 258 Iowa 500, 1966 Iowa Sup. LEXIS 703
CourtSupreme Court of Iowa
DecidedJanuary 11, 1966
Docket51856
StatusPublished
Cited by7 cases

This text of 139 N.W.2d 444 (Central Ready Mix Co. v. John G. Ruhlin Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Ready Mix Co. v. John G. Ruhlin Construction Co., 139 N.W.2d 444, 258 Iowa 500, 1966 Iowa Sup. LEXIS 703 (iowa 1966).

Opinion

*502 Moore, J.

This is a mechanie’s lien foreclosure action for the balance claimed for ready-mix concrete and other building materials furnished by Central to Caldbeck, a subcontractor, fox-construction of an addition to Firestone’s plant. The parties stipulated and the trial court ordered Firestone to pay into court the $43,000, which was owing Ruhlin, the general contractor, and that the money stand in lieu of Firestone’s real property. Firestone was then dismissed from the action. Before trial Caldbeek took bankruptcy and did not defend. Ruhlin, the only defendant who litigated Central’s claim, asserted plaintiff had been fully paid by cheeks issued by Ruhlin to Central and Caldbeek as joint payees plus payments by Caldbeck. Ruhlin also defended on the ground Central had taken a $15,000 note from Caldbeck as security and therefore was not entitled to a mechanic’s lien.

From the trial court’s judgment and foreclosure decree for only $3807.75 of its $42,897.39 claim, plaintiff has appealed. Ruhlin has cross-appealed from denial of its claim Central had taken such security as to defeat a mechanie’s lien right. We affirm on both appeals.

For brevity we have and will continue to refer to plaintiff, Central Ready Mix Company as Central; to defendants, The John G. Ruhlin Construction Company as Ruhlin; Wendell Caldbeck, doing business as Caldbeck Construction Company, as Caldbeck, and The Firestone Tire and Rubber Company as Firestone.

The record fills 512 pages including many exhibits showing the numerous transactions between the parties in construction of the Firestone addition of over eight acres of floor space. Reasonable length of an opinion limits us to a general statement of the facts.

Prior to June 5, 1963, Ruhlin entered into a contract with Firestone to build the addition according to plans and specifications set out therein for a total cost of $840,000.

On the above date Ruhlin in writing subcontracted part of the work to Caldbeck at a price of $450,000 which was later increased by approximately $28,000 for extra work. The work to be done by Caldbeck required the use of a large amount of ready-mix concrete, reinforcing wire and other materials sold by Cen *503 tral. Before contracting with Ruhlin, Caldbeek obtained price quotations from Central.

Before contracting with Caldbeek, Ruhlin made an investigation concerning his reputation as a builder. C. A. Duke, vice-president of Central, advised Ruhlin Caldbeek was experienced and capable of doing the job. Duke had known Caldbeek more than 15 years.

After getting the job Caldbeek made an agreement with Central, partly written and partly oral, providing Central would furnish him ready-mix concrete, wire mesh and certain other materials for the Firestone project. Central agreed to bill Caldbeek at $16.45 per cubic yard for #3000 concrete and $17.45 for #3000 limestone ready-mix. From this Caldbeek was to be allowed a quantity discount of 70‡ per cubic yard and also $1.00 per cubic yard upon prompt payment of account. By oral agreement the 70‡ quantity allowance was reduced to 55^5 in August 1963.

Beginning June 19 and continuing until December 30, 1963, Central furnished Caldbeek ready-mix and other materials for a total of $190,587.13. Central made delivery to the Firestone project.

To avoid cost of a performance bond, Caldbeek and Ruhlin agreed that each month Caldbeek was to submit a progress report supported by invoices of the suppliers of materials showing what had been furnished on the job and then Ruhlin would issue its cheek for the amount due, payable jointly to the supplier and Caldbeek. There is no direct evidence Central knew the exact details of the plan but the conclusion is inescapable that Duke was aware of the general plan.

Caldbeck’s first progress report to Ruhlin for materials furnished by Central was supported by invoices furnished for that purpose by Central. Thereafter Ruhlin’s check of $9430.86 dated August 14, 1963, and payable jointly to Central and Caldbeek together with the attached remittance advice was received by Caldbeek. It was endorsed by Duke’s penned signature as vice-president of Central and released to Caldbeek who in turn deposited it in his general account on August 20. No credit was entered in Central’s ledger of this payment.. Duke testified no *504 remittance advice was attached to the check when he signed it for Central at Caldbeck’s office.

About the same time as the endorsement of this check, Central, acting through Duke, took Caldbeck’s promissory note for $15,000 dated August 15, 1963. The amount of this note plus a discount credit of $2724.84 was entered as a credit on Caldbeck’s account for materials on the Firestone job. Duke testified he was aware Caldbeck needed financial help. The note provided for no interest and was payable January 1, 1964. Part of the agreement was reduction of the quantity discount. This credit remained on Central’s books until after the note became due and unpaid. Central then removed the credit and filed its mechanic’s lien on January 7, 1964.

The next progress report by Caldbeck resulted in Ruhlin’s issuance of its check for $57,249.27 dated September 16, 1963, made payable jointly to Central and Caldbeck. This check was endorsed in pen by Duke for Central and released to Caldbeck. No record of this check was made in Central’s books. At that time Caldbeck made a payment of $43,589.58 to Central.

The September progress report was followed by Ruhlin’s check for $55,428.50 dated October 15, 1963, payable jointly to Central and Caldbeck. Again Duke endorsed this check by pen and released it to Caldbeck. A payment of $41,169.38 was then made to Central by Caldbeck.

Caldbeck’s October progress report was followed by Ruhlin’s check for $45,627.28 dated November 18, 1963, payable jointly to Central and Caldbeck. This cheek was endorsed by Caldbeck and released to Central. Central credited this check to Caldbeck’s account and endorsed it for deposit to its bank account. This transaction was handled by Duke.

Central’s records after allowing cash payments, quantity and cash discounts show Caldbeck’s balance as $42,897.39. Full credit for the Ruhlin checks results in an additional credit of $37,349.67 to which must be added a $1739.97 cash discount for a total of $39,089.64. We agree with the trial court’s allowance of this additional credit and the resulting judgment for Central of $3807.75.

I. Central contends evidence of the agreement between *505 Ruhlin and Caldbeek for progress payments to Caldbeck’s materialmen of which it had no knowledge and to which Central objected should not be considered. We agree. As we have pointed out, however, Central furnished invoices and assisted in preparing the first progress report. It thereafter furnished invoices to Caldbeek for other reports to Ruhlin.

II. The facts here clearly establish Central knew the Ruhlin joint-payee checks were issued as payment on its account with Caldbeek for materials furnished on the Firestone job. Under the circumstances Central was required to retain these cheeks and enter the full amounts as payments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Builders Kitchen & Supply Co. v. Pautvein
601 N.W.2d 72 (Supreme Court of Iowa, 1999)
Iowa Supply Co. v. Grooms & Co. Construction
428 N.W.2d 662 (Supreme Court of Iowa, 1988)
FirstCentral Bank v. White
400 N.W.2d 534 (Supreme Court of Iowa, 1987)
Clemens Graf Droste Zu Vischering v. Kading
368 N.W.2d 702 (Supreme Court of Iowa, 1985)
Broadlawns Polk County Hospital Ex Rel. Fenton v. Estate of Major
271 N.W.2d 714 (Supreme Court of Iowa, 1978)
DeWaay v. Muhr
160 N.W.2d 454 (Supreme Court of Iowa, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
139 N.W.2d 444, 258 Iowa 500, 1966 Iowa Sup. LEXIS 703, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-ready-mix-co-v-john-g-ruhlin-construction-co-iowa-1966.